| Owner | Filings | Most Recent |
|---|---|---|
| BLUE SKY 3RD AVENUE MANAGEMENT | 18 | 07/08/2026 |
| 1347 THIRD AVENUE | 2 | 03/21/2026 |
| 3RD AVENUE BLOCKFRONT | 7 | 03/21/2026 |
| 200 E 77TH ST DOROTHY MCBRIDE | 8 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/30/2023 | $247.6M | — | 3RD AVENUE BLOCKFRONT LLC → LENOX HILL HOSPITAL | $1,033/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| KZ ENGINEERING, P.C | 4 | 03/11/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| SYNERGY BUILDING CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ARSENAL SCAFFOLD INC | General Contractor | 8 | 07/08/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| PAUL OLSEN | Electrical | 1 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 03/13/2023 |
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 03/16/2022 |
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 03/19/2021 |
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 03/24/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 04/12/2019 |
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 04/12/2019 |
| DOB NOW | Supported Scaffold | Signed-off | ARSENAL SCAFFOLD INC | 04/08/2019 |
| BIS | — | ISSUED | PAR ENVIRONMENTAL CORPORA | 10/02/2019 |
| BIS | EQ | ISSUED | PAR ENVIRONMENTAL CORPORA | 10/02/2019 |
| BIS | OT | ISSUED | PAR ENVIRONMENTAL CORPORA | 04/09/2019 |
| BIS | EQ | ISSUED | PAR ENVIRONMENTAL CORPORA | 04/09/2019 |
| BIS | PL | ISSUED | A. M. PLUMBING COMPANY | 02/11/2016 |
| BIS | OT | ISSUED | JZB CONSTRUCTION CO LLC | 02/09/2016 |
| BIS | OT | ISSUED | VINCENT RUSCIANO CONSTRUCTION | 11/06/2014 |
| BIS | PL | ISSUED | EDGECOMBE PLBG & HTG INC | 11/30/2011 |
| BIS | OT | ISSUED | JZB CONSTRUCTION CO LLC | 11/21/2011 |
| BIS | OT | ISSUED | ULTIMATE SIGNS & DESIGNS | 07/13/2011 |
| BIS | PL | ISSUED | EDGECOMBE PLBG & HTG INC | 12/07/2010 |
| BIS | OT | ISSUED | JZB CONSTRUCTION CO LLC | 11/04/2010 |
| BIS | FS | ISSUED | ROCKWAY FUEL OIL CORP | 05/06/2010 |
| BIS | EQ | ISSUED | EMPIRE SCAFFOLDING SYSTEM | 10/07/2008 |
| BIS | OT | ISSUED | JT MAGEN & COMPANY INC | 11/29/2005 |
| BIS | OT | ISSUED | JT MAGEN & COMPANY INC | 11/29/2005 |
| BIS | OT | ISSUED | JT MAGEN & COMPANY INC | 09/08/2005 |
| BIS | EQ | ISSUED | COLGATE SCAFFOLDING | 09/24/1996 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/03/2019 | Complete | NASH ELECTRIC SERVICES IN | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/08/2019 | Final | Karol Zdancewicz | progress |