| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2024 | Complete | RIGHTWAY ELECTRICAL INC | General Wiring |
| 05/30/2024 | Complete | RIGHTWAY ELECTRICAL INC | General Wiring |
| 01/03/2024 | Complete | A.C. MORGAN ELECTRIC | General Wiring |
| 09/27/2023 | Complete | JONG HYUN KIM | — |
| 09/27/2023 | Complete | JONG HYUN KIM | — |
| 04/26/2022 | Complete | KJK ELECTRIC INC | — |
| 01/05/2022 | Complete | ILLUMINOUS ELECTRIC CORP. | General Wiring |
| 12/07/2018 | Complete | KILO WATT ELECTRIC CORP | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| PLATINUM SERVICES NY | 7 | 03/22/2026 |
| MAIN NORTHERN PARTNERS | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/10/2021 | $8.0M | — | — → — | $349/sf building |
| 03/31/2021 | $11.2M | — | — → — | $490/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| HPL ENGINEERING P.C. | 25 | 07/10/2026 |
| WJY ELECTRIC INC. | 3 | 01/03/2024 |
| ALLEN SHINFELD, P.E. PLLC | 2 | 06/08/2023 |
| ASHRAF CORP | 2 | 08/09/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| H Z BUILDING NY | 40 | 03/21/2026 |
| PLATINUM SERVICES NY | 4 | 03/21/2026 |
| J R CONSULTING SERVICE | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BUILDERS CONSTRUCTION NYC | General Contractor | 14 | 07/08/2026 |
| H&Z BUILDING CONSULTING I | General Contractor | 9 | 07/08/2026 |
| JRL SKYLINE INC | General Contractor | 5 | 07/08/2026 |
| CONSTRUCTION MNGT. AA,LLC | General Contractor | 4 | 03/22/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 3 | 03/21/2026 |
| HPL ENGINEERING PC | General Contractor | 2 | 03/22/2026 |
| FULL CIRCLE PLUMBING CORP. | Plumbing | 2 | 07/08/2026 |
| SUNLIGHT CONSTRUCTION AA | General Contractor | 2 | 03/21/2026 |
| DYNAMIC PLBNG & SPRKR COR | Fire Protection | 2 | 07/08/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 1 | 07/08/2026 |
| JONG HYUN KIM | Electrical | 1 | 03/22/2026 |
| RIGHTWAY ELECTRICAL INC 004046 | General Contractor | 1 | 03/22/2026 |
| A.C. MORGAN ELECTRIC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HPL ENGINEERING PC | 5613 | 23 | 07/10/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | CONSTRUCTION MNGT. AA,LLC | 08/23/2024 |
| DOB NOW | Sprinklers | Signed-off | CITYWIDE PLBG, HTG &SPRKL | 09/12/2023 |
| DOB NOW | Plumbing | Signed-off | FULL CIRCLE PLUMBING CORP | 09/11/2023 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 06/22/2023 |
| DOB NOW | Mechanical Systems | Signed-off | JRL SKYLINE | 04/20/2023 |
| DOB NOW | General Construction | Permit Issued | JRL SKYLINE | 04/18/2023 |
| DOB NOW | General Construction | Permit Issued | JRL SKYLINE | 04/18/2023 |
| DOB NOW | Construction Fence | Signed-off | JRL SKYLINE | 04/18/2023 |
| DOB NOW | General Construction | Permit Issued | BUILDERS CONSTRUCTION NYC | 03/24/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BUILDERS CONSTRUCTION NYC | 12/14/2022 |
| DOB NOW | General Construction | Permit Issued | BUILDERS CONSTRUCTION NYC | 12/02/2022 |
| DOB NOW | Sprinklers | Signed-off | CITYWIDE PLBG, HTG &SPRKL | 08/16/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 06/09/2022 |
| DOB NOW | General Construction | Permit Issued | BUILDERS CONSTRUCTION NYC | 06/04/2022 |
| DOB NOW | General Construction | Signed-off | BUILDERS CONSTRUCTION NYC | 06/02/2022 |
| DOB NOW | Structural | Signed-off | BUILDERS CONSTRUCTION NYC | 06/01/2022 |
| DOB NOW | Construction Fence | Signed-off | BUILDERS CONSTRUCTION NYC | 06/01/2022 |
| DOB NOW | General Construction | Permit Issued | BUILDERS CONSTRUCTION NYC | 06/01/2022 |
| DOB NOW | General Construction | Permit Issued | H&Z BUILDING CONSULTING I | 05/13/2022 |
| DOB NOW | Plumbing | Signed-off | FULL CIRCLE PLUMBING CORP | 04/15/2022 |
| DOB NOW | Foundation | Signed-off | H&Z BUILDING CONSULTING I | 03/11/2022 |
| DOB NOW | General Construction | Permit Issued | H&Z BUILDING CONSULTING I | 03/01/2022 |
| DOB NOW | General Construction | Signed-off | H&Z BUILDING CONSULTING I | 01/24/2022 |
| DOB NOW | Construction Fence | Signed-off | H&Z BUILDING CONSULTING I | 01/05/2022 |
| DOB NOW | General Construction | Permit Issued | H&Z BUILDING CONSULTING I | 01/04/2022 |
| DOB NOW | General Construction | Permit Issued | SUNLIGHT CONSTRUCTION AA | 07/14/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/28/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/14/2024 | Pass-Final Construction Permit Withdrawal | Pass | View ↗ |
| 04/22/2024 | Fail-Final Construction Permit Withdrawal | Fail | View ↗ |
| 02/16/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/02/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/19/2023 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 09/19/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/14/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/14/2023 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 09/12/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/05/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/29/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/09/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/10/2026 | Chimneys and vents | Fran Huang | special |
| 07/10/2026 | Fenestration and door U-factor and product ratings | Fran Huang | energy_progress |
| 07/10/2026 | Vestibules | Fran Huang | energy_progress |
| 07/10/2026 | Exterior lighting power | Fran Huang | energy_progress |
| 07/10/2026 | Metering | Fran Huang | energy_progress |
| 07/10/2026 | Fenestration areas | Fran Huang | energy_progress |
| 07/10/2026 | Fenestration air leakage | Fran Huang | energy_progress |
| 07/10/2026 | Concrete - Cast-In-Place | Fran Huang | special |
| 07/10/2026 | Excavations - Sheeting, Shoring, and Bracing | Fran Huang | special |
| 07/10/2026 | Fire-Resistant Penetrations and Joints | Fran Huang | special |
| 07/10/2026 | Masonry | Fran Huang | special |
| 07/10/2026 | Structural Stability – Alterations of existing buildings | Fran Huang | special |
| 07/10/2026 | Subgrade Inspections | Fran Huang | special |
| 07/10/2026 | Subsurface Investigations (Borings/Test Pits) | Fran Huang | special |
| 07/10/2026 | Underpinning | Fran Huang | special |
| 07/10/2026 | Wall Panels, Curtain Walls, and Veneers | Fran Huang | special |
| 07/10/2026 | Energy Code Compliance Inspections | Fran Huang | progress |
| 07/10/2026 | Fire-Resistance Rated Construction | Fran Huang | progress |
| 07/10/2026 | Air barrier - visual inspection | Fran Huang | energy_progress |
| 07/10/2026 | Air barrier — testing | Fran Huang | energy_progress |
| 07/10/2026 | Electrical motors and elevators | Fran Huang | energy_progress |
| 07/10/2026 | Maintenance information | Fran Huang | energy_progress |
| 07/10/2026 | Lighting controls | Fran Huang | energy_progress |
| 07/10/2026 | Interior lighting power | Fran Huang | energy_progress |
| 07/10/2026 | Insulation placement and R values | Fran Huang | energy_progress |