| Owner | Filings | Most Recent |
|---|---|---|
| RP GENERAL CONSTRUCTION | 23 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/13/2021 | $835K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ARCHITECTURAL CONCEPT | 6 | 10/13/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARCHITECTUAL CONCEPT | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RP GENERAL CONST CORP | General Contractor | 8 | 07/08/2026 |
| FOSTER ELEC'L SVC., INC. | Electrical | 1 | 03/22/2026 |
| "I AM" CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| DOUG'S PLBG & HTG SERV CO | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ARCHITECTURAL CONCEPT | 3642 | 4 | 10/13/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | "I AM" CONSTRUCTION INC | 08/30/2023 |
| DOB NOW | Construction Fence | Signed-off | RP GENERAL CONST CORP | 11/03/2022 |
| DOB NOW | General Construction | Permit Issued | RP GENERAL CONST CORP | 11/03/2022 |
| DOB NOW | Plumbing | Signed-off | DOUG'S PLBG & HTG SERV CO | 10/21/2022 |
| DOB NOW | Structural | Permit Issued | RP GENERAL CONST CORP | 08/26/2022 |
| DOB NOW | Construction Fence | Signed-off | RP GENERAL CONST CORP | 03/15/2022 |
| BIS | — | ISSUED | RP GENERAL CONST CORP | 06/17/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/13/2023 | Permit Issued | RP GENERAL CONST CORP | Air Conditioning Systems, Heating Systems, Ventilation Systems | Cooling Goodman ASPT 39C14 5 tons · Ahu ×2 Heating A.O. Smith GPVX 75L 75,000 BTU · Water Heater ×1 Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/21/2023 | Complete | FOSTER ELEC'L SVC., INC. | General Wiring |
| 09/01/2023 | Complete | FOSTER ELEC'L SVC., INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2023 | Permit Issued | RP GENERAL CONST CORP | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/02/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/07/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/23/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 06/07/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/13/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/04/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/07/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 01/13/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/03/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/05/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/25/2023 | Protection of exposed foundation insulation | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Fire-Resistant Penetrations and Joints | MUZAFFAR JAMAL | special |
| 10/25/2023 | Excavations - Sheeting, Shoring, and Bracing | MUZAFFAR JAMAL | special |
| 10/25/2023 | Concrete - Cast-In-Place | MUZAFFAR JAMAL | special |
| 10/25/2023 | Subgrade Inspections | MUZAFFAR JAMAL | special |
| 10/25/2023 | Structural Steel - Details | MUZAFFAR JAMAL | special |
| 10/25/2023 | Wood – Metal-Plate-Connected Trusses | MUZAFFAR JAMAL | special |
| 10/25/2023 | Mechanical Systems | MUZAFFAR JAMAL | special |
| 10/25/2023 | Masonry | MUZAFFAR JAMAL | special |
| 10/25/2023 | Energy Code Compliance Inspections | MUZAFFAR JAMAL | progress |
| 10/25/2023 | Footing and Foundation | MUZAFFAR JAMAL | progress |
| 10/25/2023 | Fire-Resistance Rated Construction | MUZAFFAR JAMAL | progress |
| 10/25/2023 | Final | TARIQ SIDDIQUI | progress |
| 10/25/2023 | Fenestration areas | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Air barrier - visual inspection | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Air barrier — testing | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Fireplaces | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Duct leakage testing, insulation and design | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Metering | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Fenestration air leakage | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | HVAC-R and service water heating equipment | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Interior lighting power | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Insulation placement and R values | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | HVAC-R and service water piping design and insulation | MUZAFFAR JAMAL | energy_progress |
| 10/25/2023 | Electric vehicle service equipment requirements | MUZAFFAR JAMAL | energy_progress |