| Owner | Filings | Most Recent |
|---|---|---|
| RISEBORO COMMUNITY PARTNERSHIP | 15 | 09/03/2026 |
| PLATINUM SERVICES NY | 10 | 07/08/2026 |
| RISEBORO TPT X HOUSING DEVELOPMENT FUND CORP. | 2 | 03/22/2026 |
| HOUSING PRESERVATION & DE | 2 | 03/22/2026 |
| HPD 806 | 3 | 03/22/2026 |
| HPD -HOUSING PRESERVATION | 1 | 03/22/2026 |
| AVANTE CONTRACTING | 3 | 03/22/2026 |
| HOUSING PRESENTATION AND | 1 | 03/22/2026 |
| RISEBORO TPT X HDFC | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NKM ENGINEERING PLLC | 1 | 08/13/2026 |
| OCV ARCHITECTS | 6 | 07/24/2024 |
| NEW YORK ENGINEERS LLC | 8 | 06/05/2024 |
| ASHRAF CORP | 3 | 10/19/2023 |
| THE H ARCHITECTS LLC | 1 | 07/24/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| OCV ARCHITECTS | 12 | 03/21/2026 |
| BMB BUILDING CONSULTING | 4 | 03/21/2026 |
| PLATINUM SERVICES NY | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AVANTE CONTRACTING CORP | General Contractor | 24 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 4 | 07/08/2026 |
| NEW CENTURY ELEC'L CONTR | Electrical | 1 | 03/22/2026 |
| VOLTAIC SOLAIRE LLC | General Contractor | 1 | 09/03/2026 |
| KATAN P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 1 | 08/13/2026 |
| VIBRANALYSIS INC., DBA VT | 6864 | 14 | 07/24/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | VOLTAIC SOLAIRE LLC | 09/02/2026 |
| DOB NOW | Mechanical Systems | Signed-off | AVANTE CONTRACTING CORP | 07/01/2024 |
| DOB NOW | General Construction | Permit Issued | AVANTE CONTRACTING CORP | 07/01/2024 |
| DOB NOW | Mechanical Systems | Signed-off | AVANTE CONTRACTING CORP | 02/13/2024 |
| DOB NOW | General Construction | Permit Issued | AVANTE CONTRACTING CORP | 02/12/2024 |
| DOB NOW | Construction Fence | Signed-off | AVANTE CONTRACTING CORP | 02/12/2024 |
| DOB NOW | Mechanical Systems | Signed-off | AVANTE CONTRACTING CORP | 11/14/2023 |
| DOB NOW | Structural | Signed-off | AVANTE CONTRACTING CORP | 11/14/2023 |
| DOB NOW | Construction Fence | Signed-off | AVANTE CONTRACTING CORP | 11/14/2023 |
| DOB NOW | General Construction | Permit Issued | AVANTE CONTRACTING CORP | 11/13/2023 |
| DOB NOW | Construction Fence | Signed-off | AVANTE CONTRACTING CORP | 07/25/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 06/16/2023 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 06/16/2023 |
| DOB NOW | Plumbing | Signed-off | KATAN P & H INC | 06/12/2023 |
| DOB NOW | General Construction | Permit Issued | AVANTE CONTRACTING CORP | 06/02/2023 |
| DOB NOW | Mechanical Systems | Signed-off | AVANTE CONTRACTING CORP | 05/26/2023 |
| DOB NOW | Structural | Signed-off | AVANTE CONTRACTING CORP | 05/26/2023 |
| DOB NOW | Mechanical Systems | Signed-off | AVANTE CONTRACTING CORP | 05/22/2023 |
| BIS | FB | ISSUED | CLASSIC FUEL OIL CORP. | 12/13/1990 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/16/2022 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | Permit Issued | BERGER QUALITY ELEC'L CON | — |
| 06/15/2023 | Complete | ILLUMINOUS ELECTRIC CORP. | General Wiring |
| 05/15/2023 | Complete | NEW CENTURY ELEC'L CONTR | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2024 | Permit Issued | AVANTE CONTRACTING CORP | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2026 | Permit Issued | VOLTAIC SOLAIRE LLC | 90 panels, 53.1 kw, 1,650 roof_area_sqft |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/07/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/16/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 07/05/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/17/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/04/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/25/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/10/2026 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 08/10/2026 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 08/10/2026 | Final | NARESH MAHANGU | progress |
| 08/10/2026 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 08/10/2026 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 07/31/2024 | Fenestration areas | JUAN GOMEZ | energy_progress |
| 07/31/2024 | Interior lighting power | JUAN GOMEZ | energy_progress |
| 07/31/2024 | Insulation placement and R values | JUAN GOMEZ | energy_progress |
| 07/31/2024 | Metering | JUAN GOMEZ | energy_progress |
| 07/31/2024 | Air barrier - visual inspection | JUAN GOMEZ | energy_progress |
| 07/31/2024 | Wall Panels, Curtain Walls, and Veneers | JUAN GOMEZ | special |
| 07/31/2024 | Structural Stability – Alterations of existing buildings | JUAN GOMEZ | special |
| 07/31/2024 | Fire-Resistant Penetrations and Joints | JUAN GOMEZ | special |
| 07/31/2024 | Exterior Insulation and Finish Systems (EIFS) | JUAN GOMEZ | special |
| 07/31/2024 | Fire-Resistance Rated Construction | JUAN GOMEZ | progress |
| 07/31/2024 | Energy Code Compliance Inspections | JUAN GOMEZ | progress |
| 07/31/2024 | Fenestration and door U-factor and product ratings | JUAN GOMEZ | energy_progress |
| 07/31/2024 | Fenestration air leakage | JUAN GOMEZ | energy_progress |
| 07/09/2024 | Air barrier - visual inspection | JUAN GOMEZ | energy_progress |
| 07/09/2024 | Fenestration areas | JUAN GOMEZ | energy_progress |
| 07/09/2024 | Interior lighting power | JUAN GOMEZ | energy_progress |
| 07/09/2024 | Metering | JUAN GOMEZ | energy_progress |
| 07/09/2024 | Exterior Insulation and Finish Systems (EIFS) | JUAN GOMEZ | special |
| 07/09/2024 | Fire-Resistant Penetrations and Joints | JUAN GOMEZ | special |
| 07/09/2024 | Structural Stability – Alterations of existing buildings | JUAN GOMEZ | special |