| Owner | Filings | Most Recent |
|---|---|---|
| FOREST CITY PIERREPONT ASSOC | 507 | 09/18/2026 |
| BROOKFIELD PROPERTIES | 77 | 07/08/2026 |
| OWNERS REP | 3 | 03/22/2026 |
| FOREST CITY PIERREPONT ASSOCS | 14 | 03/22/2026 |
| CONCEPT CONSTRUCTION SERV | 1 | 03/22/2026 |
| SAINT ANNS SCHOOL | 1 | 03/22/2026 |
| FORREST CITY PIERREPONT ASSOCIAT | 6 | 03/21/2026 |
| FIRST NEW YORK MANAGEMENT | 7 | 03/21/2026 |
| ONE PIERREPONT PLAZA | 4 | 03/21/2026 |
| METROTECH | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| R.G. VANDERWEIL ENGINEERS, PC | 12 | 06/11/2026 |
| JOEL PHAGOO P.E. PLLC | 3 | 05/06/2026 |
| AMA CONSULTING ENGINEERS, PC | 37 | 04/16/2026 |
| CASEWORKS ARCHITECT, PLLC | 1 | 10/24/2025 |
| ERIC FOSTER | 1 | 08/22/2025 |
| HIGHLAND ASSOCIATES | 1 | 08/05/2025 |
| STRATFORD ENGINEERING | 1 | 05/01/2025 |
| ARIANNA BRAUN ARCHITECTS, PLLC | 5 | 04/29/2025 |
| LEON SKVIRSKY PE | 1 | 11/02/2023 |
| TPG ARCHITECTURE, LLP | 12 | 10/13/2023 |
| LEA ARCHITECTURE PLLC | 3 | 05/05/2023 |
| TOHFAZ UDDIN PE PC | 1 | 05/03/2023 |
| MSP ENGINEERING INC. P.C. | 7 | 01/31/2023 |
| BALA CONSULTING ENGINEERS | 25 | 07/05/2022 |
| MICHELLE DROLLETTE ARCHITECT LLC | 1 | 06/30/2022 |
| F.P.VILLANO CONSULTING ENGINEER LLC | 1 | 04/08/2021 |
| PATUXENT ENGINEERING LLC | 1 | 01/18/2021 |
| MG ENGINEERING D.P.C. | 2 | 06/17/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 207 | 03/21/2026 |
| LOUIS STRIAR | 2 | 03/21/2026 |
| PATUXENT ENGINEERING | 2 | 03/21/2026 |
| BUILDING BROTHERS | 2 | 03/21/2026 |
| CAESAR BUSTAMANTE, AIA | 1 | 03/21/2026 |
| INTEGRATED C O MILROSE CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STRUCTURE TONE, LLC | General Contractor | 16 | 07/08/2026 |
| JRM CONSTRUCTION MGMT LLC | General Contractor | 16 | 07/08/2026 |
| MED-TEK CONTRACTING INC | General Contractor | 10 | 07/08/2026 |
| VIKING RESTORATION SVCE | General Contractor | 9 | 03/21/2026 |
| GBL MECHANICAL INC | Plumbing | 7 | 07/08/2026 |
| AMA DESIGN BUILD LLC | General Contractor | 6 | 03/21/2026 |
| CONCEPT CONSTRUCTION SERV | General Contractor | 6 | 03/21/2026 |
| DAVID SPOTO | Electrical | 5 | 03/21/2026 |
| YORKE CONSTRUCTION CORP | General Contractor | 5 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 5 | 09/18/2026 |
| SPOTO DAVID | Electrical | 5 | 03/21/2026 |
| SIGNATURE CONSTRUCTION GROUP | General Contractor | 4 | 07/08/2026 |
| TALISEN CONSTRUCTION CORP | General Contractor | 4 | 03/21/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 3 | 03/21/2026 |
| PREFERRED MECHANICAL INC | Plumbing | 3 | 09/12/2026 |
| BEDROCK PLBG. & HTG., INC | Plumbing | 3 | 07/08/2026 |
| PREFERRED SPKLR AND MECH | Fire Protection | 3 | 07/08/2026 |
| SKH MECHANICAL CORP | Fire Protection | 3 | 07/08/2026 |
| Z-CAR-D | Scaffold | 2 | 07/08/2026 |
| RALPH OCCHIPINTI | Electrical | 2 | 03/21/2026 |
| CAPITOL FIRE SPRINKLER CO | Fire Protection | 2 | 07/08/2026 |
| DEVO FIRE PROTECTION INC | Fire Protection | 2 | 07/08/2026 |
| MACCARONE PLUMBING INC | Fire Protection | 2 | 07/08/2026 |
| WHITE HILL RESTORATION INC | General Contractor | 2 | 07/22/2026 |
| MAC FELDER INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CATALPA SPECIAL INSPECTIO | 2004 | 49 | 06/11/2026 |
| MEP INSPECTIONS, INC | 1102 | 31 | 06/11/2026 |
| JOEL PHAGOO ,PE, PLLC | 2416 | 3 | 05/06/2026 |
| METRIC CONSULTING AND INS | 1803 | 5 | 10/24/2025 |
| AUTOGRAPHIC CO | 1579 | 8 | 05/01/2025 |
| AMARACON TESTING & INSPEC | 5842 | 4 | 07/17/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Protection and Mechanical Methods | Permit Issued | ANDAMIO SCAFFOLDING LLC | 09/17/2026 |
| DOB NOW | Plumbing | Permit Issued | PREFERRED MECHANICAL INC | 09/10/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 08/21/2026 |
| DOB NOW | General Construction | Permit Issued | WHITE HILL RESTORATION INC | 07/20/2026 |
| DOB NOW | Mechanical Systems | Signed-off | STRUCTURE TONE, LLC | 04/20/2026 |
| DOB NOW | General Construction | Permit Issued | WHITE HILL RESTORATION IN | 03/13/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | WHITE HILL RESTOR. INC | 02/23/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | WHITE HILL RESTOR. INC | 09/04/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 08/25/2025 |
| DOB NOW | General Construction | Signed-off | SAVCON CONSTRUCTION LLC | 08/21/2025 |
| DOB NOW | Structural | Signed-off | MED-TEK CONTRACTING INC | 07/10/2025 |
| DOB NOW | Sprinklers | Permit Issued | DEVO FIRE PROTECTION INC | 07/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MED-TEK CONTRACTING INC | 06/30/2025 |
| DOB NOW | General Construction | Signed-off | MED-TEK CONTRACTING INC | 06/18/2025 |
| DOB NOW | Plumbing | Signed-off | LIQUID TECH PLBG&HTG,INC | 05/15/2025 |
| DOB NOW | General Construction | Signed-off | MED-TEK CONTRACTING INC | 05/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MED-TEK CONTRACTING INC | 05/06/2025 |
| DOB NOW | Sprinklers | Signed-off | DEVO FIRE PROTECTION INC | 08/30/2024 |
| DOB NOW | Mechanical Systems | Signed-off | MED-TEK CONTRACTING INC | 07/22/2024 |
| DOB NOW | General Construction | Signed-off | MED-TEK CONTRACTING INC | 07/18/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TALISEN CONSTRUCTION CORP | 07/12/2024 |
| DOB NOW | General Construction | Signed-off | TALISEN CONSTRUCTION CORP | 07/12/2024 |
| DOB NOW | Sprinklers | Signed-off | FIVE BOROUGH NYC LLC | 07/12/2024 |
| DOB NOW | General Construction | Signed-off | MED-TEK CONTRACTING INC | 04/19/2024 |
| DOB NOW | Mechanical Systems | Signed-off | MED-TEK CONTRACTING INC | 04/19/2024 |
| DOB NOW | General Construction | Signed-off | YORKE CONSTRUCTION CORP | 03/13/2024 |
| DOB NOW | Standpipe | Signed-off | PREFERRED SPKLR AND MECH | 01/29/2024 |
| DOB NOW | General Construction | Signed-off | STRUCTURE TONE, LLC | 12/26/2023 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 12/04/2023 |
| DOB NOW | Sprinklers | Permit Issued | UNITED PLBG MECHANICAL INC | 08/03/2023 |
| DOB NOW | Plumbing | Signed-off | CITY/SUBURBAN PLBG CORP | 06/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | YORKE CONSTRUCTION CORP | 06/07/2023 |
| DOB NOW | General Construction | Signed-off | YORKE CONSTRUCTION CORP | 05/11/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | KING HOIST & SCAFFOLDING | 05/04/2023 |
| DOB NOW | General Construction | Signed-off | YORKE CONSTRUCTION CORP | 03/30/2023 |
| DOB NOW | Sprinklers | Signed-off | PREFERRED SPKLR AND MECH | 03/29/2023 |
| DOB NOW | Sprinklers | Signed-off | PREFERRED SPKLR AND MECH | 03/27/2023 |
| DOB NOW | Plumbing | Signed-off | PREFERRED MECHANICAL INC | 03/27/2023 |
| DOB NOW | Plumbing | Signed-off | PREFERRED MECHANICAL INC | 03/27/2023 |
| DOB NOW | Structural | Signed-off | STRUCTURE TONE, LLC | 02/04/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/16/2026 | Signed-off | STRUCTURE TONE, LLC | Heating Systems | Heating Iec IEC VEY12 1,200 CFM · Fan Coil Indoor ×1 |
| 05/01/2025 | Signed-off | MED-TEK CONTRACTING INC | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2026 | Permit Issued | DEVO FIRE PROTECTION INC | 147 heads |
| 05/16/2024 | Signed-off | FIVE BOROUGH NYC LLC | — |
| 05/10/2023 | Permit Issued | UNITED PLBG MECHANICAL IN | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2025 | Signed-off | LIQUID TECH PLBG&HTG,INC | Water/Sanitary |
| 12/05/2022 | Permit Issued | PREFERRED MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2025 | Permit Issued | BOROWIDE ELECT'L CONTR'S | — |
| 07/17/2025 | Complete | CROSSWIRE ELECTRICAL INC | General Wiring |
| 04/11/2025 | Permit Issued | ASSOCIATED ELEC CONT OF N | General Wiring |
| 03/17/2025 | Complete | UNITY ELECTRIC CO. INC | General Wiring |
| 02/27/2025 | Complete | UNITY ELECTRIC CO. INC | General Wiring |
| 02/27/2025 | Complete | UNITY ELECTRIC CO. INC | — |
| 07/30/2024 | Complete | TRANSFORM ELECTL CONTRS I | General Wiring |
| 08/04/2023 | Complete | DIFAZIO ELECTRIC NY, INC | General Wiring |
| 04/20/2023 | Complete | PHOENIX ELECTRIC NY LLC | General Wiring |
| 04/10/2023 | Complete | FREEDOM ELECTRIC & DATA | General Wiring |
| 08/22/2022 | Permit Issued | H. & L. ELECTRIC INC | General Wiring |
| 01/27/2021 | Complete | DAL ELECTRICAL CORP. | — |
| 01/27/2021 | Complete | DAL ELECTRICAL CORP. | General Wiring |
| 10/14/2020 | Complete | LIVE WIRE ELECTRIC 1 LLC | — |
| 10/14/2020 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/01/2025 | Signed-off | MED-TEK CONTRACTING INC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/03/2023 | Permit Issued | KING HOIST & SCAFFOLDING | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/06/2026 | Permit Issued | WHITE HILL RESTOR. INC | Suspended Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/06/2026 | Permit Issued | WHITE HILL RESTOR. INC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/17/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/02/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/24/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/18/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/12/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/09/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 01/31/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 11/01/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/24/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/23/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/17/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/17/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/31/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/31/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/28/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/21/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/18/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/17/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/11/2026 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 06/11/2026 | Sprinkler Systems | Nicolas Crosetto | special |
| 06/11/2026 | Post-installed Anchors | Nicolas Crosetto | special |
| 05/18/2026 | Post-installed Anchors | JOEL PHAGOO | special |
| 05/06/2026 | Post-installed Anchors | JOEL PHAGOO | special |
| 03/30/2026 | Duct leakage testing, insulation and design | ERIC BERLENT | energy_progress |
| 03/30/2026 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 03/30/2026 | Post-installed Anchors | ERIC BERLENT | special |
| 03/30/2026 | HVAC-R and service water heating system controls | ERIC BERLENT | energy_progress |
| 03/30/2026 | Maintenance information | ERIC BERLENT | energy_progress |
| 03/30/2026 | HVAC-R and service water piping design and insulation | ERIC BERLENT | energy_progress |
| 03/30/2026 | HVAC-R and service water heating equipment | ERIC BERLENT | energy_progress |
| 01/23/2026 | Mechanical Systems | ERIC BERLENT | special |
| 01/23/2026 | Final | ERIC BERLENT | progress |
| 01/22/2026 | Sprinkler Systems | Nicolas Crosetto | special |
| 01/22/2026 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 01/22/2026 | Post-installed Anchors | Nicolas Crosetto | special |
| 08/13/2025 | Structural Stability – Alterations of existing buildings | SAMI HAJJAR P.E | special |
| 08/13/2025 | Masonry | SAMI HAJJAR P.E | special |
| 08/13/2025 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 07/17/2025 | Final | Glenn Leitch | progress |
| 07/16/2025 | Final | SAMI HAJJAR P.E | progress |
| 04/09/2025 | Lighting controls | ERIC BERLENT | energy_progress |
| 04/09/2025 | Interior lighting power | ERIC BERLENT | energy_progress |
| 04/09/2025 | Maintenance information | ERIC BERLENT | energy_progress |