← Back
Office, 20+ stories, with or without commercial
Herald Square Building
1350 BROADWAY · BIN 1080606
💬 Discuss this project
1928Year Built
24Stories
O4Building Class
C6-6Zoning
386,786 sfGross Floor Area
111Units
LL97 Covered0 Open ViolationsFISP: SWARMP
Office, 20+ stories, with or without commercial · Owner of record: 1350 BROADWAY LLC · 19,500 sf lot · 19.84 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneralOther
Permit Issued — active, not yet Signed-off
Roof4p · 2 filings · 20 docs
Floor 217p · 6 filings · 20 docs
Floor 20Under Construction17p · 4 filings · 16 docs
Floor 1921p · 5 filings · 20 docs
Floor 188p · 6 filings · 20 docs
Floor 177p · 1 filing · 6 docs
Floor 161p · 1 filing · 5 docs
Floor 151p · 1 filing · 6 docs
Floor 144p · 3 filings · 10 docs
Floor 132p · 1 filing · 3 docs
Floor 12
Floor 11
Floor 101p · 1 filing · 8 docs
Floor 98p · 3 filings · 18 docs
Floor 83p · 1 filing · 4 docs
Floor 71p · 1 filing · 10 docs
Floor 6
Floor 536p · 5 filings · 20 docs
Floor 421p · 5 filings · 17 docs
Floor 326p · 4 filings · 14 docs
Floor 237p · 13 filings · 20 docs
Floor 1107p · 14 filings · 20 docs
Mezzanine11p · 5 filings · 20 docs
CellarUnder Construction71p · 9 filings · 20 docs
Sub-Cellar2p · 1 filing · 12 docs
Basement2p · 1 filing · 8 docs
Sub-Basement1p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ESRT1109/13/2026
EMPIRE STATE REALTY TRUST35507/08/2026
BANCO SANTANDER303/22/2026
1350 BROADWAY11103/22/2026
1350 BDWY LLC103/22/2026
D.N.A. CONT LLC SUITE 801103/22/2026
GSL ENTERPRISES903/22/2026
HELMSET SPEAR INC103/22/2026
HELMSLEY SPEAL INC103/22/2026
GSL EMTERPROSES INC103/22/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RIZZO GROUP13403/21/2026
LOUIS STRIAR2403/21/2026
FRANK BUENO EXPEDITING803/21/2026
RIGGING CONSULTANTS603/21/2026
JAM CONSULTANTS, INC.403/21/2026
INDESIGN STUDIO403/21/2026
Rigid Structural Design, LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J. PHELAN CONSTRUCTION COGeneral Contractor3007/08/2026
RINNOVO CONSTRUCTION, LLCGeneral Contractor1607/08/2026
A&A PLUMBING CORPPlumbing1607/08/2026
DENKO MECHANICAL INCFire Protection1607/08/2026
J.A. JENNINGS, INCGeneral Contractor1407/08/2026
EXCEL INTERIOR CONSTRUCTIONGeneral Contractor1307/08/2026
FOLOR INCGeneral Contractor1107/08/2026
L S SIGNScaffold707/08/2026
VANGUARD CONSTRUCTION ANDGeneral Contractor707/08/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor707/08/2026
LEGACY BUILDERS/DEVELOPERS CORPGeneral Contractor707/08/2026
JRM CONSTRUCTION MGMT LLCGeneral Contractor607/08/2026
FINALY GENL CONTR CORPGeneral Contractor607/08/2026
ASHLAR MECHANICAL CORPFire Protection607/08/2026
A.G.S IMPROVEMENTS INCGeneral Contractor603/21/2026
LHOTSE CORPGeneral Contractor507/08/2026
BEVILACQUA, JOSEPHElectrical503/21/2026
TORRES, HECTORElectrical503/21/2026
PSI PARTNERS, LLCFire Protection507/08/2026
URBAN CONSTR & DESIGN LLCGeneral Contractor407/08/2026
CROSSLAND MECHANICAL INCGeneral Contractor407/08/2026
EMPIRE STATE ELEC MAINT &Electrical403/22/2026
PERRY MECHANICAL CONTRACTGeneral Contractor303/21/2026
DONNELLY MECHANICAL CORPGeneral Contractor307/08/2026
ABCO-PEERLESS SPRKLR CORPFire Protection307/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DELTA TESTING LABS687207/02/2026
PCS ENGINEERING3745311/21/2025
CODEGREEN51010411/05/2025
SAG ENGINEERING & CONSULT608508/14/2025
DOMANI INSPECTION SERVICE843111/17/2023
JOSEPH BOTTA, PE, PC1139404/10/2023
OBAID MIAN849103/22/2022
ESNYC CONSULTING INC4099107/17/2020
AKS ARCHITECTURAL & ENGIN1957205/11/2020
Building Lifecycle
All (300)Filed (69)Permit Issued (74)Signed Off (40)Facade (FISP) (3)Inspection (58)Objection (26)Special Inspection (30)
09/09/2026
Filed — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AND PLYWOOD FENCE AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01440039-P1
09/03/2026
Permit issued — Suspended Scaffold
M01221225-I1-SC
09/03/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/27/2026
Signed off — Alteration
GENERAL CONSTRUCTION TAKING PLACE ON THE 9TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01302531-I1
08/26/2026
Signed off — Alteration
MECHANICAL WORK TAKING PLACE ON THE 9TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01302601-I1
08/20/2026
Permit issued — Construction Fence
M01440039-I1-SH
08/20/2026
Permit issued — Construction Fence
M01440039-I1-FN
08/19/2026
Filed — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AND PLYWOOD FENCE AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01440039-I1
08/14/2026
Signed off — Alteration
M01167476-I1
07/30/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/22/2026
Permit issued — Sign
M01260958-I1-SG
07/22/2026
Permit issued — Sign
M01260957-I1-SG
07/22/2026
Permit issued — Sign
M01260959-I1-SG
07/15/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/08/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/06/2026
Permit issued — Structural
M01179566-I1-ST
07/06/2026
Permit issued — General Construction
M01179534-I1-GC
07/02/2026
Filed — Alteration
Installation and use of sidewalk shed as per plans filed herewith. This application is filed in conjunction with DOB M01179534-I1-GC.
M01401834-I1
07/02/2026
Filed — Alteration
Installation and use of plywood enclosure as per plans filed herewith. This application is filed in conjunction with DOB# M01179534-I1-GC
M01401911-I1
07/02/2026
Permit issued — Mechanical Systems
M01179539-I1-MS
07/02/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/13/2026
Special inspection requirement — Post-installed Anchors
RICHARD GREENWALD
05/06/2026
Signed off — Alteration
M01213965-I1
05/04/2026
Signed off — Alteration
SPRINKLER MODIFICATIONS TO THE 2ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01145996-I1
04/27/2026
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01217480-I1
04/27/2026
Permit issued — Sidewalk Shed
M01213965-I1-SH
04/27/2026
Permit issued — Supported Scaffold
M01217480-I1-SF
04/23/2026
Signed off — Alteration
M01158392-I1
03/23/2026
Signed off — Alteration
M01295998-I1
03/20/2026
Signed off — Alteration
PLUMBING WORK ON THE 2ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01145965-I1
03/16/2026
Permit issued — Protection and Mechanical Methods
M01295998-I1-PMM
01/19/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/08/2025
Inspection — Fail-Final Boiler Equipment Inspection
Fail
View inspection ↗
11/21/2025
Filed — Alteration
Suspended Scaffolding For facade restoration as shown on plans| PAA1 Additional Drop Locations
M01221225-P2
11/13/2025
Permit issued — General Construction
M01302531-I1-GC
11/13/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
11/13/2025
Special inspection requirement — Post-installed Anchors
Michael Walsh
11/12/2025
Signed off — Alteration
PLUMBING WORK ON THE 1ST AND 2ND FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01116541-I1
11/12/2025
Permit issued — Mechanical Systems
M01302601-I1-MS
11/10/2025
Permit issued — Sprinklers
M01302607-I1-EW-SP
11/10/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/05/2025
Filed — Alteration
GENERAL CONSTRUCTION TAKING PLACE ON THE 9TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01302531-I1
11/05/2025
Filed — Alteration
MECHANICAL WORK TAKING PLACE ON THE 9TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01302601-I1
11/05/2025
Filed — Alteration
SPRINKLER WORK TAKING PLACE ON THE 9TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01302607-I1
11/05/2025
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
10/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
HATIM ELSAID
10/29/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/27/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/24/2025
Filed — Alteration
Suspended Scaffolding For facade restoration as shown on plans| PAA1 Additional Drop Locations
M01221225-P1
10/23/2025
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
10/22/2025
Filed — Alteration
M01295998-I1
10/22/2025
Permit issued — Protection and Mechanical Methods
M01295998-I1-PMM
10/22/2025
Special inspection requirement — Duct leakage testing, insulation and design
HATIM ELSAID
10/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
HATIM ELSAID
10/22/2025
Special inspection requirement — Lighting controls
HATIM ELSAID
10/22/2025
Special inspection requirement — Ventilation and air distribution system
HATIM ELSAID
10/22/2025
Special inspection requirement — Interior lighting power
HATIM ELSAID
10/22/2025
Special inspection requirement — Energy Code Compliance Inspections
HATIM ELSAID
10/16/2025
Special inspection requirement — Post-installed Anchors
Michael Walsh
10/16/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offLHOTSE CORP09/03/2026
DOB NOWConstruction FencePermit IssuedMC SUPERSTRUCTURE INC08/20/2026
DOB NOWConstruction FencePermit IssuedMC SUPERSTRUCTURE INC08/20/2026
DOB NOWSignSigned-offULTIMATE SIGNS&DESIGNS CO07/22/2026
DOB NOWSignPermit IssuedULTIMATE SIGNS&DESIGNS CO07/22/2026
DOB NOWSignSigned-offULTIMATE SIGNS&DESIGNS CO07/22/2026
DOB NOWStructuralPermit IssuedVANGUARD CONSTRUCTION AND07/06/2026
DOB NOWGeneral ConstructionPermit IssuedVANGUARD CONSTRUCTION AND07/06/2026
DOB NOWMechanical SystemsPermit IssuedVANGUARD CONSTRUCTION AND07/02/2026
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC04/27/2026
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC04/27/2026
DOB NOWProtection and Mechanical MethodsSigned-offDYNAMIC HOISTING SCAFF IN03/16/2026
DOB NOWGeneral ConstructionSigned-offWHALEN CONSTRUCTION, INC11/13/2025
DOB NOWMechanical SystemsSigned-offWHALEN CONSTRUCTION, INC11/12/2025
DOB NOWSprinklersSigned-offFIVE BOROUGH NYC LLC11/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offDYNAMIC HOISTING SCAFF IN10/22/2025
DOB NOWSignPermit IssuedCAPITOL DESIGN & MAINT IN09/17/2025
DOB NOWSignSigned-offCAPITOL DESIGN & MAINT IN09/17/2025
DOB NOWSignSigned-offCAPITOL DESIGN & MAINT IN09/17/2025
DOB NOWStructuralSigned-offJ PHELAN CONSTRUCTION08/13/2025
DOB NOWGeneral ConstructionPermit IssuedJ PHELAN CONSTRUCTION07/28/2025
DOB NOWSprinklersPermit IssuedABCO-PEERLESS SPRKLR CORP07/25/2025
DOB NOWMechanical SystemsPermit IssuedJ PHELAN CONSTRUCTION07/25/2025
DOB NOWSprinklersSigned-offMORA FIRE PROTECTION LLC07/08/2025
DOB NOWGeneral ConstructionPermit IssuedLHOTSE CORP06/13/2025
DOB NOWGeneral ConstructionPermit IssuedLHOTSE CORP06/13/2025
DOB NOWSignPermit IssuedWEINFELD, ELLIOT06/11/2025
DOB NOWSignPermit IssuedWEINFELD, ELLIOT06/11/2025
DOB NOWSignPermit IssuedWEINFELD, ELLIOT06/11/2025
DOB NOWSignPermit IssuedWEINFELD, ELLIOT06/11/2025
DOB NOWSignPermit IssuedWEINFELD, ELLIOT06/11/2025
DOB NOWSignPermit IssuedWEINFELD, ELLIOT06/11/2025
DOB NOWSignPermit IssuedWEINFELD, ELLIOT06/11/2025
DOB NOWSuspended ScaffoldSigned-offLHOTSE CORP06/06/2025
DOB NOWGeneral ConstructionPermit IssuedJ PHELAN CONSTRUCTION06/03/2025
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC05/01/2025
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC05/01/2025
DOB NOWStructuralPermit IssuedVANGUARD CONSTRUCTION AND04/17/2025
DOB NOWSprinklersPermit IssuedABCO-PEERLESS SPRKLR CORP04/09/2025
DOB NOWPlumbingSigned-offWILLIAM C. GERAKARIS P&H04/09/2025
+ 60 more permits on file
4 projects · most recent 07/14/2025
Air Conditioning Systems Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/14/2025Permit IssuedJ. PHELAN CONSTRUCTION COHeating and Air Conditioning Systems
Heat / Cool
Sigma CSC VERTICAL AIR COOLED SDSV-D.1-240 251,000 BTU · Wshp ×4
01/16/2025Permit IssuedRINNOVO CONSTRUCTION, LLCAir Conditioning Systems, Ventilation Systems
Cooling
Aaon V3-ERB-8-0-26FA-12F 232,200 BTU · Fan Coil Indoor ×2
V3-DRB-8-0-26FC-12H 163,600 BTU · Fan Coil Indoor ×1
06/14/2023Permit IssuedEXCEL INTERIOR CONSTRUCTIAir Conditioning Systems
Cooling
Aaon V3-CRB-8-0-24HC-000 84,400 BTU · Fan Coil Indoor ×1
02/27/2020Permit IssuedJ.A. JENNINGS, INCAir Conditioning Systems
Cooling
Aaon V3-CRB-8-8 84,480 BTU ×1
8 projects · most recent 11/05/2025
FiledStatusContractorScope
11/05/2025Signed-offFIVE BOROUGH NYC LLC4 heads
07/29/2025Permit IssuedPSI PARTNERS, LLC135 heads
07/17/2025Permit IssuedABCO-PEERLESS SPRKLR CORP4 heads
04/01/2025Permit IssuedABCO-PEERLESS SPRKLR CORP34 heads
09/25/2023———
09/21/2023Permit IssuedDENKO MECHANICAL INC—
05/31/2022Permit IssuedA + SPRINKLER CORP140 heads
05/11/2020——3 heads
3 projects · most recent 11/05/2025
Water/Sanitary
FiledStatusContractorScope
11/05/2025———
07/17/2025———
05/11/2020——Water/Sanitary
25 projects · most recent 09/10/2026
General Wiring Lighting
FiledStatusContractorScope
09/10/2026Permit IssuedBDS ELECTRIC CORP.General Wiring
09/04/2026CompleteOFF SHORE ELECTRIC CORPGeneral Wiring
08/19/2026Permit IssuedULTIMATE SIGNS & ELEC COR—
08/19/2026Permit IssuedULTIMATE SIGNS & ELEC COR—
08/03/2026Permit IssuedNASH ELECTRIC SERVICES IN—
05/08/2026Permit IssuedBIGMAN BROS., INC.—
03/23/2026CompleteRONAN ELECTRICAL LLCGeneral Wiring
10/15/2025CompleteHUNTER ELECTRIC, INC.—
04/23/2025CompleteBOROWIDE ELECT'L CONTR'S—
01/28/2025CompleteDENMAR ELECTRIC CORPGeneral Wiring
10/07/2024CompleteHUNTER ELECTRIC, INC.—
08/23/2024CompleteOFF SHORE ELECTRIC CORPGeneral Wiring
08/09/2024CompleteOFF SHORE ELECTRIC CORPGeneral Wiring
02/02/2024CompleteOFF SHORE ELECTRIC CORPGeneral Wiring
02/02/2024CompleteOFF SHORE ELECTRIC CORPGeneral Wiring
2 projects · most recent 08/14/2025
Steel
FiledStatusContractorScope
08/14/2025Permit IssuedVANGUARD CONSTRUCTION ANDSteel
07/12/2022Permit IssuedJRM CONSTRUCTION MGMT LLC1 scope_items
4 projects · most recent 09/09/2026
Fence Sidewalk Shed Scaffold
FiledStatusContractorScope
09/09/2026Permit IssuedMC SUPERSTRUCTURE INCFence, Sidewalk Shed
07/02/2026——Sidewalk Shed
09/23/2025Signed-offANDAMIO SCAFFOLDING LLCScaffold
08/15/2025Permit IssuedVANGUARD CONSTRUCTION ANDFence
1 project · most recent 11/21/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
11/21/2025Signed-offLHOTSE CORPSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 94
DateTypeResultReport
09/03/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/30/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/15/2026Pass-Final CND-Occupancy InspectionPassView ↗
07/08/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/02/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/19/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/08/2025Fail-Final Boiler Equipment InspectionFailView ↗
11/10/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/05/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
10/29/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/27/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/23/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
09/22/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/22/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/10/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/09/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/02/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/02/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/19/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/13/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/11/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/23/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/23/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/14/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
07/14/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
Latest 25 of 94.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
05/13/2026Post-installed AnchorsRICHARD GREENWALDspecial
11/13/2025Alternative Materials - OTCR Buildings Bulletin NumberMichael Walshspecial
11/13/2025Post-installed AnchorsMichael Walshspecial
10/30/2025Fire-Resistant Penetrations and JointsHATIM ELSAIDspecial
10/22/2025Duct leakage testing, insulation and designHATIM ELSAIDenergy_progress
10/22/2025Interior lighting powerHATIM ELSAIDenergy_progress
10/22/2025Lighting controlsHATIM ELSAIDenergy_progress
10/22/2025Ventilation and air distribution systemHATIM ELSAIDenergy_progress
10/22/2025Energy Code Compliance InspectionsHATIM ELSAIDprogress
10/22/2025Fire-Resistant Penetrations and JointsHATIM ELSAIDspecial
10/16/2025Alternative Materials - OTCR Buildings Bulletin NumberMichael Walshspecial
10/16/2025Post-installed AnchorsMichael Walshspecial
10/14/2025FinalHATIM ELSAIDprogress
10/14/2025Mechanical SystemsHATIM ELSAIDspecial
10/14/2025Sprinkler SystemsHATIM ELSAIDspecial
10/14/2025FinalHATIM ELSAIDprogress
09/03/2025FinalRyan Hungprogress
09/03/2025FinalRyan Hungprogress
09/03/2025FinalRyan Hungprogress
08/18/2025Post-installed AnchorsChester Kowalskispecial
08/18/2025Energy Code Compliance InspectionsChester Kowalskiprogress
08/18/2025Structural Steel - DetailsChester Kowalskispecial
08/18/2025Sprayed fire-resistant materialsChester Kowalskispecial
08/18/2025Structural Steel - WeldingChester Kowalskispecial
08/18/2025Structural Steel - High Strength BoltingChester Kowalskispecial
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Skip HopRetail—
Project M01208756 Alteration · Permit Entire · 06/05/2025
Project M01208757 Alteration · Permit Entire · 06/05/2025
Project M01208752 Alteration · Permit Entire · 06/04/2025
Project M01208753 Alteration · Permit Entire · 06/04/2025
Project M01208754 Alteration · Permit Entire · 06/04/2025
Project M01208755 Alteration · Permit Entire · 06/04/2025
Project M01208758 Alteration · Permit Entire · 06/04/2025
WF BranchRetailCellar, Floor 1
Project M01179539 Alteration · Permit Entire · 04/01/2025
Project M01179556 Alteration · Permit Entire · 04/01/2025
Carter'sOfficeFloor 2
Project M01167476 Alteration · LOC Issued · 01/17/2025
Project M01158392 Alteration · LOC Issued · 01/15/2025
NutanixOfficeFloor 10
Project M00215129 Alteration · LOC Issued · 10/03/2019
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 5,966 on file (BIS + DOB NOW)
▸Plans & Drawings166
▸DOB NOWPlans/Sketch133
09/03/2026M00503988-I1Request digital key ↗
09/03/2026M00523253-I1Request digital key ↗
09/03/2026M00590216-I1Request digital key ↗
Showing 3 of 133 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler15
09/05/2026M00207480-I1Request digital key ↗
09/05/2026M00254683-I1Request digital key ↗
09/05/2026M00285918-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems10
09/05/2026M00254623-I1Request digital key ↗
09/05/2026M00285866-I1Request digital key ↗
09/05/2026M00321525-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Plumbing8
09/05/2026M00254642-I1Request digital key ↗
09/05/2026M00285907-I1Request digital key ↗
09/05/2026M00321546-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits994
▸BISPLAN / WORK APPROVAL APPLICATION565
02/11/2026122494112Open ↗
02/10/2026122404040Open ↗
12/03/2025122494112Open ↗
Showing 3 of 565 on file for this type
▸BISWORK PERMIT APPLICATION413
06/23/2025122494112Open ↗
10/06/2021123780346Open ↗
12/08/2020140971278Open ↗
Showing 3 of 413 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISApplication Withdrawal/Address Change Form OP-1131
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Zoning, Tax Lot & Property Records3
▸BISZRD1-Zoning Resolution Determination2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications1,670
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION885
03/13/2020123867271Open ↗
03/13/2020123867271Open ↗
Showing 2 of 885 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature168
09/15/2026M01440039-P1Open ↗
09/05/2026M00207480-I1Open ↗
09/05/2026M00254642-I1Open ↗
Showing 3 of 168 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST152
03/13/2020123867271Open ↗
Showing 1 of 152 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM137
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 137 on file for this type
▸DOB NOWProgress Inspector Seal & Signature117
09/26/2026M00503988-I1Open ↗
09/04/2026M01302601-I1Open ↗
09/04/2026M01302601-I1Open ↗
Showing 3 of 117 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature106
09/23/2026M01302607-I1Open ↗
09/23/2026M01242122-I1Open ↗
09/23/2026M00766027-I1Open ↗
Showing 3 of 106 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT85
11/19/2020140971278Open ↗
08/31/2020140944389Open ↗
07/13/2020140922759Open ↗
Showing 3 of 85 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
11/19/2020140971278Open ↗
10/07/2020140957917Open ↗
08/31/2020140944389Open ↗
Showing 3 of 6 on file for this type
▸BISPC FULL REPORT6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
11/19/2020140971278Open ↗
08/31/2020140944389Open ↗
07/13/2020140922759Open ↗
Showing 3 of 5 on file for this type
▸BISAPPLICANT OWNER SIGNATURE3
10/07/2020140957917Open ↗
05/29/2020140900345Open ↗
05/13/2020140900345Open ↗
▸Trade Schedules & Equipment656
▸BISSELF-CERT PLUMBING NOTICE158
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 158 on file for this type
▸BISSCHEDULE B - PLUMBING113
12/03/2025122494112Open ↗
12/01/2025122494112Open ↗
Showing 2 of 113 on file for this type
▸BISEQUIPMENT USE PERMITS106
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 106 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA91
06/08/2021123403058Open ↗
Showing 1 of 91 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE80
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 80 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT61
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 61 on file for this type
▸BISSPRINKLER INSP REPORT : FP-8528
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸BISSIGN HANGER CERTIFICATE18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISSTANDPIPE SYSTEMS1
10/22/2020122494112Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos497
▸DOB NOWDEP ACP-5: Asbestos Assessment Report153
09/05/2026M00207480-I1Open ↗
09/05/2026M00254642-I1Open ↗
09/05/2026M00285918-I1Open ↗
Showing 3 of 153 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)150
11/19/2020140971278Open ↗
10/07/2020140957917Open ↗
08/31/2020140944389Open ↗
Showing 3 of 150 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'148
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 148 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER42
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 42 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance267
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS146
03/13/2020123867271Open ↗
03/13/2020123867271Open ↗
Showing 2 of 146 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS64
06/23/2021140957917Open ↗
04/06/2021140971278Open ↗
03/30/2021123867253Open ↗
Showing 3 of 64 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY20
10/06/2021123780346Open ↗
04/06/2021140971278Open ↗
03/30/2021123867253Open ↗
Showing 3 of 20 on file for this type
▸BISTECHNICAL REPORT: ENERGY14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISTR8: Energy Code Progress Inspections9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸DOB NOWEN2: As Built Energy Analysis7
09/02/2026M00590120-I1Open ↗
Showing 1 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS5
11/19/2020140971278Open ↗
10/07/2020140957917Open ↗
08/31/2020140944389Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Inspections & Test Reports52
▸BISTECHNICAL REPORT: RESPONSIBILITY45
12/01/2025122494112Open ↗
10/06/2021123780346Open ↗
10/06/2021123780346Open ↗
Showing 3 of 45 on file for this type
▸BISTECHNICAL REPORT: PILE DRIVING3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISHYDRO FLOW TEST LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs524
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST285
06/23/2021140957917Open ↗
06/11/2021123403058Open ↗
04/06/2021140971278Open ↗
Showing 3 of 285 on file for this type
▸BISADMINISTRATIVE OBJECTIONS174
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 174 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION46
02/17/2026122494112Open ↗
11/23/2020140957917Open ↗
Showing 2 of 46 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSUPERSEDING LETTER6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸Cost, Insurance & Ownership673
▸BISCOST AFFIDAVIT673
06/23/2021140957917Open ↗
06/11/2021123403058Open ↗
04/06/2021140971278Open ↗
Showing 3 of 673 on file for this type
▸Filing & Intake Forms411
▸BISEFILING COVER SHEET241
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 241 on file for this type
▸BISADDITIONAL INFORMATION81
02/26/2026122494112Open ↗
11/10/2020140957917Open ↗
07/24/2020123867235Open ↗
Showing 3 of 81 on file for this type
▸BISBOROUGH INTAKE FORM72
03/25/2020123490043Open ↗
Showing 1 of 72 on file for this type
▸BISeFiling Job Application Cover Sheet17
11/19/2020140971278Open ↗
10/07/2020140957917Open ↗
08/31/2020140944389Open ↗
Showing 3 of 17 on file for this type
▸Other Documents40
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION29
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 29 on file for this type
▸BISSupporting Document: Fee Exempt3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWManufacturer's Specifications3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWCalculations3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWProperty Ownership Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type