| Owner | Filings | Most Recent |
|---|---|---|
| 136-33 37th Ave Realty | 72 | 03/21/2026 |
| NY Commerce Properties | 15 | 03/21/2026 |
| 37th Ave Dental Care | 11 | 07/08/2026 |
| K G 33 Ave | 7 | 03/21/2026 |
| AE & LY Medical Associates | 6 | 03/21/2026 |
| Gaa Venture Investments | 5 | 03/21/2026 |
| Renaissance Tower | 4 | 03/22/2026 |
| Cheung Queens Property | 4 | 03/21/2026 |
| Caipa | 2 | 03/21/2026 |
| Pinnacle | 2 | 03/21/2026 |
| Wells Fargo | 1 | 03/21/2026 |
| 136-33 37th Avenue | 1 | 03/21/2026 |
| Eastern Star Development | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Nexus Architect | 2 | 06/17/2026 |
| City Building NY Architect | 1 | 10/30/2023 |
| CX Consulting | 9 | 03/06/2023 |
| Focal Point Architects & Associates | 1 | 12/09/2021 |
| Pinnacle | 4 | 04/22/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| G Design Drafting | 12 | 03/21/2026 |
| S Y Consulting Violations | 6 | 03/21/2026 |
| Focal Point Design & Construction | 2 | 03/21/2026 |
| Zobuilden | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Dve Construction | General Contractor | 9 | 07/08/2026 |
| Pinnacle Plumbing & Heating | Fire Protection | 4 | 08/13/2026 |
| NY Building Associates | General Contractor | 2 | 03/21/2026 |
| Efin Management | General Contractor | 2 | 07/08/2026 |
| L2 Construction | General Contractor | 2 | 03/21/2026 |
| Tri State Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| KJK Electric | Electrical | 1 | 03/22/2026 |
| Y & W NY Construction | General Contractor | 1 | 07/08/2026 |
| RRP Plumbing | Plumbing | 1 | 07/08/2026 |
| Millennium Maintenance & Electrical | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| XC Engineering | 6692 | 9 | 03/06/2023 |
| Pinnacle Engineering | 2652 | 3 | 04/22/2021 |
| New Air Solution | 8418 | 1 | 04/12/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | Pinnacle Plumbing & Heating | 08/12/2026 |
| DOB NOW | General Construction | Permit Issued | Efin Management | 06/18/2026 |
| DOB NOW | General Construction | Signed-off | Efin Management | 01/27/2026 |
| DOB NOW | General Construction | Signed-off | Y & W NY Construction | 11/27/2023 |
| DOB NOW | Sprinklers | Permit Issued | Pinnacle Plumbing & Heating | 07/25/2023 |
| DOB NOW | Sprinklers | Signed-off | Pinnacle Plumbing & Heating | 09/24/2022 |
| DOB NOW | Plumbing | Signed-off | DW Plumbing | 08/24/2022 |
| DOB NOW | Mechanical Systems | Signed-off | L2 Construction | 07/28/2022 |
| DOB NOW | General Construction | Signed-off | NY Building Associates | 01/14/2022 |
| DOB NOW | Sprinklers | Permit Issued | Pinnacle Plumbing & Heating | 10/25/2021 |
| DOB NOW | General Construction | Signed-off | Dve Construction | 08/25/2021 |
| DOB NOW | Mechanical Systems | Signed-off | Dve Construction | 06/11/2021 |
| DOB NOW | General Construction | Signed-off | Dve Construction | 06/02/2021 |
| DOB NOW | Plumbing | Signed-off | RRP Plumbing | 04/22/2021 |
| DOB NOW | Mechanical Systems | Signed-off | Dve Construction | 04/21/2021 |
| DOB NOW | General Construction | Signed-off | Dve Construction | 04/20/2021 |
| BIS | OT | ISSUED | Golden Construction NY Co | 07/21/2021 |
| BIS | OT | RE-ISSUED | Golden Construction NY Co | 07/09/2021 |
| BIS | OT | ISSUED | Golden Construction NY Co | 07/09/2021 |
| BIS | SP | ISSUED | Pinnacle Plumbing & Heating | 10/20/2020 |
| BIS | OT | ISSUED | Flushing One Construction | 08/06/2020 |
| BIS | OT | ISSUED | TGC Construction | 01/07/2020 |
| BIS | SP | ISSUED | Pinnacle Plumbing & Heating | 05/09/2019 |
| BIS | SP | ISSUED | Pinnacle Plumbing & Heating | 12/11/2018 |
| BIS | PL | ISSUED | Pinnacle Plumbing & Heating | 12/07/2018 |
| BIS | MH | ISSUED | Dve Construction | 10/31/2018 |
| BIS | OT | ISSUED | Golden Construction NY Co | 08/21/2018 |
| BIS | SP | ISSUED | Pinnacle Plumbing & Heating | 08/20/2018 |
| BIS | MH | ISSUED | Dve Construction | 08/08/2018 |
| BIS | OT | ISSUED | Golden Construction NY Co | 08/08/2018 |
| BIS | PL | ISSUED | RRP Plumbing | 08/07/2018 |
| BIS | OT | ISSUED | Dve Construction | 07/26/2018 |
| BIS | OT | ISSUED | Hongtai Construction | 06/13/2018 |
| BIS | OT | ISSUED | Tristar Developing | 04/11/2018 |
| BIS | SP | ISSUED | Pinnacle Plumbing & Heating | 12/11/2017 |
| BIS | — | ISSUED | Service Sign Erectors Co | 10/05/2017 |
| BIS | OT | ISSUED | Liyi Construction | 10/02/2017 |
| BIS | MH | ISSUED | Hongtai Construction | 09/22/2017 |
| BIS | SP | ISSUED | Pinnacle Plumbing & Heating | 08/03/2017 |
| BIS | PL | ISSUED | Pinnacle Plumbing & Heating | 08/03/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2021 | Permit Issued | Pinnacle Plumbing & Heating | — |
| 04/12/2021 | Signed-off | Pinnacle Plumbing & Heating | 2 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2021 | — | — | Water/Sanitary |
| 04/12/2021 | Signed-off | RRP Plumbing | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2022 | Complete | KJK Electric | General Wiring |
| 07/28/2022 | Complete | United Electrical Cont'g | General Wiring |
| 08/24/2021 | Complete | R & T Electrical | General Wiring |
| 04/19/2021 | Complete | R & T Electrical | General Wiring |
| 10/29/2018 | Complete | R & T Electrical | General Wiring |
| 08/15/2018 | Complete | United Electrical Cont'g | General Wiring |
| 07/23/2018 | Complete | R & T Electrical | General Wiring, Lighting |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/28/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/27/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/23/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/30/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/03/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/29/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/27/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/01/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/27/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/17/2026 | Final | Wilson Chao | progress |
| 06/17/2026 | Lighting controls | Wilson Chao | energy_progress |
| 06/17/2026 | Interior lighting power | Wilson Chao | energy_progress |
| 03/09/2023 | Sprinkler Systems | XIU CHEN | special |
| 03/07/2023 | Mechanical Systems | XIU CHEN | special |
| 03/07/2023 | Final | XIU CHEN | progress |
| 03/07/2023 | Fire-Resistant Penetrations and Joints | XIU CHEN | special |
| 03/06/2023 | Fire-Resistant Penetrations and Joints | XIU CHEN | special |
| 03/06/2023 | Mechanical Systems | XIU CHEN | special |
| 03/06/2023 | Final | XIU CHEN | progress |
| 03/06/2023 | Sprinkler Systems | XIU CHEN | special |
| 10/18/2022 | Energy Code Compliance Inspections | XIU CHEN | progress |
| 10/18/2022 | Fire-Resistant Penetrations and Joints | XIU CHEN | special |
| 10/17/2022 | Fire-Resistant Penetrations and Joints | XIU CHEN | special |
| 10/17/2022 | Energy Code Compliance Inspections | XIU CHEN | progress |
| 05/23/2022 | Interior lighting power | XIU CHEN | energy_progress |
| 05/23/2022 | Lighting controls | XIU CHEN | energy_progress |
| 05/23/2022 | Energy Code Compliance Inspections | XIU CHEN | progress |
| 05/23/2022 | Final | XIU CHEN | progress |
| 05/23/2022 | Maintenance information | XIU CHEN | energy_progress |
| 05/23/2022 | Mechanical Systems | XIU CHEN | special |
| 12/09/2021 | Final | Feng Zhang | progress |
| 08/19/2021 | Sprinkler Systems | XIU CHEN | special |
| 08/19/2021 | Fire-Resistant Penetrations and Joints | XIU CHEN | special |
| 05/03/2021 | Mechanical Systems | CHUN HSIUNG HUANG | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Eric Chang DDS | Medical / Healthcare | Floor 5 | Project Q00579667 Project Q00579768 |