Issued Permit Scope
General Construction · Mechanical Systems · Structural · Supported Scaffold
DIRECT REPLACEMENT OF EXISITNG SPLIT SYSTEM HVAC UNITS ON ROOF CURBS AND AT CEILING OF FIRST FLOOR TENANT SPACE. NEW DUCTWORK FOR FRESH AIR THROUGH MEZZ. NO CHANGE TO USE, EGRESS, OR OCCUCPANCY.
On file for this project
6 documents · 1 drawing sheet
Roof repairs as per plans. No change to use, egress or occupancy.
On file for this project
3 documents · 4 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Latest 3 of 8 filings on this floor.
Bulkhead1p · 1 filing · 3 docs
Structural
Installation of construction fence per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
3 documents · 1 drawing sheet
Floor 617p · 3 filings · 10 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
Floor 531p · 5 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 433p · 5 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 333p · 5 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 233p · 5 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 175p · 11 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers · Structural · Supported Scaffold
DIRECT REPLACEMENT OF EXISITNG SPLIT SYSTEM HVAC UNITS ON ROOF CURBS AND AT CEILING OF FIRST FLOOR TENANT SPACE. NEW DUCTWORK FOR FRESH AIR THROUGH MEZZ. NO CHANGE TO USE, EGRESS, OR OCCUCPANCY.
On file for this project
6 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
SNIPES-- INSTALLATION OF PLUMBING FIXTURES FOR RETAIL RENOVATION.
On file for this project
3 documents
Latest 3 of 11 filings on this floor.
Mezzanine26p · 3 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
DIRECT REPLACEMENT OF EXISITNG SPLIT SYSTEM HVAC UNITS ON ROOF CURBS AND AT CEILING OF FIRST FLOOR TENANT SPACE. NEW DUCTWORK FOR FRESH AIR THROUGH MEZZ. NO CHANGE TO USE, EGRESS, OR OCCUCPANCY.
On file for this project
6 documents · 1 drawing sheet
JIMMY JAZZ- INTERIOR RENOVATIONS TO JIMMY JAZZ RETAIL SPACE AND RENOVATIONS TO BUILDING STOREFRONT AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 2 drawing sheets
STRUCTURAL WORK FOR STOREFRONT MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents
Site & exterior33p · 8 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · General Construction · Sidewalk Shed · Supported Scaffold
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
On file for this project
2 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 10 drawing sheets
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
4 documents · 4 drawing sheets
Latest 3 of 8 filings on this floor.
Filed — no permit issued1 filing · 3 docs
Plumbing
JIMMY JAZZ- INSTALL PLUMBING FIXTURES FOR NEW ADA BATHROOM AS PER PLANS FILED HEREWITH.