| Owner | Filings | Most Recent |
|---|---|---|
| VKW DESIGN | 4 | 09/13/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| VKW DESIGN INC | 4 | 08/18/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CUBE BUILD GROUPS | General Contractor | 1 | 07/25/2026 |
| GREGG NY PLUMBING, INC | Plumbing | 1 | 07/31/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | GREGG NY PLUMBING, INC | 07/30/2026 |
| DOB NOW | General Construction | Permit Issued | CUBE BUILD GROUPS INC | 07/23/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/18/2026 | Permit Issued | CUBE BUILD GROUPS INC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Permit Issued | GREGG NY PLUMBING, INC | Gas, Water/Sanitary |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | Mechanical Systems | Yuxuan Liu | special |
| 08/19/2026 | Fire-Resistant Penetrations and Joints | Yuxuan Liu | special |
| 08/19/2026 | Final | Yuxuan Liu | progress |
| 08/19/2026 | Energy Code Compliance Inspections | Yuxuan Liu | progress |
| 08/19/2026 | Fire-Resistance Rated Construction | Yuxuan Liu | progress |
| 08/19/2026 | HVAC-R and service water piping design and insulation | Yuxuan Liu | energy_progress |
| 08/19/2026 | Interior lighting power | Yuxuan Liu | energy_progress |
| 08/19/2026 | HVAC-R and service water heating equipment | Yuxuan Liu | energy_progress |
| 08/19/2026 | HVAC-R and service water heating system controls | Yuxuan Liu | energy_progress |
| 08/17/2026 | Fire-Resistant Penetrations and Joints | Yuxuan Liu | special |
| 08/17/2026 | Energy Code Compliance Inspections | Yuxuan Liu | progress |