← Back
BuildNYC
Two stories - detached, small or mid-size
137-27 220 PLACE
QUEENS · Laurelton · BIN 4281956
💬 Discuss this project
1930Year Built
2Stories
A1Building Class
R3XZoning
854 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,500 sf lot · 0.34 FAR built · Flood zone X
Locations of Work
Electrical
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofBuilding mounted photovoltaic solar electric array installat1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Momentum Solar203/26/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV Sia9281203/26/2026
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (8)
04/01/2026
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 8 Panels, 3.28 kW
Q01035860-I1
03/26/2026
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 8 Panels, 3.28 kW
Q01035860-P1
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
03/26/2026
Special inspection requirement — Final
Mina Makar
03/26/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
03/26/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
05/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
05/27/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
05/27/2025
Special inspection requirement — Final
Mina Makar
05/27/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
05/17/2024
Permit issued — Solar
Q01035860-I1-SL
05/13/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 8 Panels, 3.28 kW
Q01035860-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMomentum Solar05/17/2024
1 project · most recent 05/13/2024
FiledStatusContractorScope
05/13/2024CompleteIsland Electric—
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
03/26/2026Fire-Resistant Penetrations and JointsMina Makarspecial
03/26/2026FinalMina Makarprogress
03/26/2026Energy Code Compliance InspectionsMina Makarprogress
03/26/2026Air barrier - visual inspectionMina Makarenergy_progress
05/27/2025Fire-Resistant Penetrations and JointsMina Makarspecial
05/27/2025Energy Code Compliance InspectionsMina Makarprogress
05/27/2025FinalMina Makarprogress
05/27/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/22/2026Q01035860-P1Request digital key ↗
08/22/2026Q01035860-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
08/25/2026Q01035860-I1Open ↗
08/25/2026Q01035860-I1Open ↗
08/23/2026Q01035860-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/22/2026Q01035860-I1Open ↗
08/13/2026Q01035860-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/25/2026Q01035860-I1Open ↗
08/23/2026Q01035860-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/22/2026Q01035860-I1Open ↗
08/13/2026Q01035860-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01035860-I1Open ↗