| Owner | Filings | Most Recent |
|---|---|---|
| 131-137 7TH AVENUE SOUTH LLC | 16 | 03/21/2026 |
| CENTENNIAL PROPERTIES NY INC. | 15 | 04/09/2026 |
| 9300 REALTY | 8 | 03/21/2026 |
| 131 7TH AVENUE SOUTH | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SY ENGINEERING PLLC | 5 | 05/08/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| HTX BUILDING CONSULTING | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DKT CONTRACTORS LLC | General Contractor | 5 | 04/09/2026 |
| ANDREW CHARNOW | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SY ENGINEERING PLLC | 5149 | 1 | 06/06/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | DKT CONTRACTORS LLC | 02/07/2025 |
| DOB NOW | General Construction | Permit Issued | DKT CONTRACTORS LLC | 01/05/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | DKT CONTRACTORS LLC | 12/01/2022 |
| BIS | FP | ISSUED | WILLIAM HIRD & CO INC | 04/21/2015 |
| BIS | PL | ISSUED | AMC PLBG, HTG & CLNG, INC | 02/17/2015 |
| BIS | PL | ISSUED | AMC PLBG, HTG & CLNG, INC | 02/17/2015 |
| BIS | OT | ISSUED | EUDA CONSTRUCTION & | 02/11/2015 |
| BIS | MH | ISSUED | EUDA CONSTRUCTION & | 02/11/2015 |
| BIS | OT | ISSUED | EUDA CONSTRUCTION & | 01/30/2015 |
| BIS | OT | ISSUED | MULBERRY LLC | 11/17/2011 |
| BIS | OT | ISSUED | MULBERRY LLC | 11/17/2011 |
| BIS | FP | ISSUED | UNIQUE FIRE SYSTEMS INC | 10/14/2011 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 08/03/2011 |
| BIS | PL | ISSUED | BRANCH PLUMBING LLC | 06/16/2011 |
| BIS | OT | ISSUED | MULBERRY GROUP CONSTR LLC | 05/13/2011 |
| BIS | OT | ISSUED | MULBERRY GROUP CONSTR LLC | 05/13/2011 |
| BIS | OT | ISSUED | CASTELLO GENERAL CONSTRUCTION | 09/03/2004 |
| BIS | MH | ISSUED | CASTELLO GENERAL CONSTRUCTION | 08/25/2004 |
| BIS | — | ISSUED | VILLAGE GRILL, INC | 07/07/2004 |
| BIS | PL | ISSUED | NEW YORK STANDARD MECH CORP | 06/04/2004 |
| BIS | — | ISSUED | CASTELLO GENE CONSTR. | 08/19/2003 |
| BIS | PL | ISSUED | THEOFORE WAGNER PLBG AND HTG | 05/23/2001 |
| BIS | OT | ISSUED | JVIRGINIA CONST MANA. | 04/06/2001 |
| BIS | FP | ISSUED | NEW YORK BUSINESS FIRE SYSTEM | 03/22/2001 |
| BIS | — | ISSUED | FRANK TORRONE & SONS | 03/15/2000 |
| BIS | PL | ISSUED | CODE MECHANICAL INC | 08/13/1999 |
| BIS | MH | ISSUED | SILVERSTEIN CONSTRUCTION | 07/20/1999 |
| BIS | EQ | ISSUED | VIRGINIA CONST. MGT | 04/23/1998 |
| BIS | PL | ISSUED | S DEMAIO PLBG & HTG | 11/19/1997 |
| BIS | — | ISSUED | VOODOO CONTRACTING COEP | 03/03/1997 |
| BIS | — | ISSUED | VOO DOO CONTRACTING | 06/25/1996 |
| BIS | EQ | ISSUED | VOO DOO CONTRACTING | 06/24/1996 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/06/2022 | Permit Issued | DKT CONTRACTORS LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2023 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2023 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/10/2023 | Permit Issued | UNITED ELEC'L CONT'G CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/08/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 05/08/2023 | Post-installed Anchors | — | special |
| 05/08/2023 | Energy Code Compliance Inspections | — | progress |
| 05/08/2023 | HVAC-R and service water heating system controls | — | energy_progress |
| 05/08/2023 | HVAC-R and service water heating equipment | — | energy_progress |
| 05/08/2023 | Maintenance information | — | energy_progress |
| 05/08/2023 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 05/08/2023 | Shutoff dampers | — | energy_progress |
| 05/08/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 05/08/2023 | Energy Code Compliance Inspections | — | progress |
| 05/08/2023 | HVAC-R and service water heating system controls | — | energy_progress |
| 05/08/2023 | Electrical motors and elevators | — | energy_progress |
| 05/08/2023 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 05/08/2023 | HVAC-R and service water heating equipment | — | energy_progress |
| 05/08/2023 | Maintenance information | — | energy_progress |
| 05/03/2023 | Mechanical Systems | — | special |
| 05/03/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 05/03/2023 | Final | — | progress |
| 05/03/2023 | Energy Code Compliance Inspections | — | progress |
| 05/03/2023 | Fire-Resistance Rated Construction | — | progress |
| 05/03/2023 | Interior lighting power | — | energy_progress |
| 05/03/2023 | Electrical motors and elevators | — | energy_progress |
| 05/03/2023 | Lighting controls | — | energy_progress |
| 06/03/2022 | HVAC-R and service water piping design and insulation | SUNGBOM YI | energy_progress |
| 06/03/2022 | Energy Code Compliance Inspections | SUNGBOM YI | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Hyun | Restaurant / Food Service | Cellar, Floors 1, 2, Mezzanine | Project M00732213 |