← Back
Elevator apt, semi-fireproof with stores
1371 MADISON AVENUE
MANHATTAN · BIN 1047435
💬 Discuss this project
1906Year Built
6Stories
D7Building Class
R10Zoning
35,998 sfGross Floor Area
26Units
LL97 CoveredRent Stabilized118 Open Violations 117 unresolved · 1 paperwork only ▸FISP: SAFE
Elevator apt, semi-fireproof with stores · Owner of record: 50 EAST 96TH STREET LLC · 8,080 sf lot · 4.46 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction4p · 4 filings · 20 docs
BulkheadUnder Construction1p · 1 filing · 3 docs
Floor 16p · 3 filings · 19 docs
Cellar1p · 1 filing · 4 docs
1 job · most recent 04/16/2025
Others
FiledStatusContractorScopeMake / Model / Capacity
04/16/2025——Others
Other
Integrity VW-60 1,500 CFM · Kitchen Exhaust ×1
1 job · most recent 06/04/2021
Water/Sanitary
FiledStatusContractorScope
06/04/2021Permit IssuedORBIT PLBG & HTG INCWater/Sanitary
6 jobs · most recent 06/20/2022
General Wiring Boiler Controls
FiledStatusContractorScope
06/20/2022CompleteBOROWIDE ELECT'L CONTR'S—
06/09/2021CompleteJANON ELECTRIC CORPGeneral Wiring
02/07/2020Complete247 ELECTRICAL CORP—
07/25/2019CompleteV. VASS ELECTRIC CORP—
07/18/2019Permit IssuedITKIN ELECTRIC CORP.Boiler Controls
08/28/2018CompleteANTHONY G FERRY INC—
1 job · most recent 08/17/2026
Scaffold
FiledStatusContractorScope
08/17/2026Permit IssuedRAJPUT RESTORATION INCScaffold
2 jobs · most recent 08/19/2026
Suspended Scaffold
FiledStatusContractorScope
08/19/2026Permit IssuedRAJPUT RESTORATION INCSuspended Scaffold
12/22/2025Permit IssuedSTRUCTURAL PRESERVATION SSuspended Scaffold
2 jobs · most recent 08/19/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
08/19/2026Permit IssuedRAJPUT RESTORATION INCSuspended Scaffold (SC)
12/22/2025Permit IssuedSTRUCTURAL PRESERVATION S—
Building Lifecycle
All (158)Filed (18)Permit Issued (20)Signed Off (11)Facade (FISP) (6)Violation (60)Inspection (13)Special Inspection (30)
09/08/2026
Permit issued — Suspended Scaffold
M01446552-I1-SC
08/19/2026
Filed — Alteration
SUSPENDED SCAFFOLD OUTRIGGER SYSTEM AT 50 EAST 96TH STREET, MANHATTAN, FOR FACADE RESTORATION WORK.
M01446552-I1
08/18/2026
Permit issued — Supported Scaffold
M01446535-I1-SF
08/17/2026
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLD AT 50 EAST 96TH STREET, MANHATTAN, AS PER PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01446535-I1
08/17/2026
Permit issued — General Construction
M01121866-I1-GC
08/16/2026
Special inspection requirement — Post-installed Anchors
Md Rashid
07/10/2026
Signed off — Alteration
FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola
M01326788-I1
12/29/2025
Permit issued — Suspended Scaffold
M01326788-I1-SC
12/22/2025
Filed — Alteration
FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola
M01326788-I1
07/15/2025
Signed off — Alteration
Register laundry equipment in the cellar.
M00603684-I1
06/04/2025
Violation issued (HPD, closed)
A
04/16/2025
Filed — Alteration
MECHANICAL WORK TYPE IN FILED TO PROPOSE COMMERCIAL COOKING HOOD SYSTEM, AS PER PLAN SUBMITTED.
M01181352-I1
04/09/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
04/09/2025
Special inspection requirement — Energy Code Compliance Inspections
04/09/2025
Special inspection requirement — Tenant Protection Plan Compliance
02/13/2025
Special inspection requirement — Final
02/13/2025
Special inspection requirement — Mechanical Systems
11/07/2024
Filed — Alteration
M01121866-I1
11/07/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Addesso
11/07/2024
Special inspection requirement — Air barrier - visual inspection
Anthony Addesso
11/07/2024
Special inspection requirement — Energy Code Compliance Inspections
Anthony Addesso
11/07/2024
Special inspection requirement — Masonry
Anthony Addesso
11/07/2024
Special inspection requirement — Post-installed Anchors
Anthony Addesso
11/06/2024
Special inspection requirement — Tenant Protection Plan Compliance
Md Rashid
10/03/2024
Special inspection requirement — Final
Anthony Addesso
09/11/2024
Violation issued (HPD, closed)
C
09/11/2024
Violation issued (HPD, closed)
B
09/11/2024
Violation issued (HPD, closed)
B
09/11/2024
Violation issued (HPD, closed)
B
07/23/2024
Signed off — Alteration
M00754821-I1
02/14/2024
Violation issued (HPD, open)
C
02/14/2024
Violation issued (HPD, open)
C
01/02/2024
Signed off — Alteration
HEREBY FILING FOR RENOVATION OF COMMERCIAL SPACE FOR "CHIP CITY" (INSTALLATION OF PLUMBING FIXTURES). NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00810093-I1
01/02/2024
Signed off — Alteration
HEREBY FILING FOR RENOVATION OF COMMERCIAL SPACE FOR "CHIP CITY". NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00810091-I1
11/15/2023
Violation issued (HPD, closed)
I
08/22/2023
Permit issued — Sidewalk Shed
M00754821-I1-SH
07/12/2023
Signed off — Alteration
Propose to install non-illuminated, non-flashing accessory business sign. Wording: CHiP CiTY.
M00895324-I1
07/11/2023
Inspection — Pass-Final Sign Permit Inspection
Pass
View inspection ↗
06/30/2023
Permit issued — Sign
M00895324-I1-SG
06/29/2023
Filed — Alteration
Propose to install non-illuminated, non-flashing accessory business sign. Wording: CHiP CiTY.
M00895324-I1
06/23/2023
Special inspection requirement — Final
JUSTIN KIM
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/01/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/07/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/15/2023
Violation issued (HPD, closed)
A
03/10/2023
Permit issued — Plumbing
M00810093-I1-PL
03/08/2023
Permit issued — Mechanical Systems
M00810091-I1-GC-CX
02/14/2023
Filed — Alteration
HEREBY FILING FOR RENOVATION OF COMMERCIAL SPACE FOR "CHIP CITY" (INSTALLATION OF PLUMBING FIXTURES). NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00810093-I1
02/14/2023
Filed — Alteration
HEREBY FILING FOR RENOVATION OF COMMERCIAL SPACE FOR "CHIP CITY". NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00810091-I1
02/14/2023
Special inspection requirement — Energy Code Compliance Inspections
NICHOLAS MOSHOPOULOS
02/14/2023
Special inspection requirement — Fire-Resistance Rated Construction
NICHOLAS MOSHOPOULOS
01/10/2023
Special inspection requirement — Tenant Protection Plan Compliance
NICHOLAS MOSHOPOULOS
01/10/2023
Special inspection requirement — Tenant Protection Plan Compliance
NICHOLAS MOSHOPOULOS
01/09/2023
Special inspection requirement — Final
NICHOLAS MOSHOPOULOS
01/09/2023
Special inspection requirement — Mechanical Systems
NICHOLAS MOSHOPOULOS
11/03/2022
Violation issued (HPD, closed)
I
08/30/2022
Permit issued — Sidewalk Shed
M00754821-I1-SH
08/29/2022
Filed — Alteration
M00754821-I1
03/21/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
Latest 60 of 158 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CEPRINE CONSTRUCTION807/08/2026
50 EAST 96TH STREET3103/22/2026
50 EAST 96 STREET LLC503/22/2026
50 E 96 ST LLCY PO BOX 56103/22/2026
50 E 96TH ST LLC103/22/2026
PAYSON ESTATES203/22/2026
PAYSON ESTATES INC PO BOX103/22/2026
COLGATE ENTERPRISE203/21/2026
RUTH SONS REAL ESTATES603/21/2026
WALTPAYSON ESTATES103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEPRINE CONSTRUCTION INCGeneral Contractor907/08/2026
YM PRO CORPGeneral Contractor603/21/2026
THE MANLYN DEVELOPMENT GROUPGeneral Contractor407/08/2026
ANGELO ANDREW INCPlumbing207/08/2026
RAJPUT RESTORATION INCGeneral Contractor208/20/2026
T.N.T. PLBG & HTG, INCPlumbing107/08/2026
ITKIN ELECTRIC CORP.Electrical103/22/2026
UNITECH DESIGNScaffold107/08/2026
JOSEF BOSROKElectrical103/21/2026
YOUNG CHOEElectrical103/21/2026
P3 CONSTRUCTION, LLCGeneral Contractor107/08/2026
ORBIT PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
EMPIRE DESIGN CORP5474208/17/2026
PARADIGM ARCHITECTURE5931111/07/2024
NKO ARCHITECT PC6811202/14/2023
GREGORY V. PEROTTO, P.E.947302/03/2022
AK ENGINEERING PC678207/20/2021
STRATFORD ENGINEERING997105/27/2021
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedRAJPUT RESTORATION INC09/08/2026
DOB NOWSupported ScaffoldPermit IssuedRAJPUT RESTORATION INC08/18/2026
DOB NOWGeneral ConstructionPermit IssuedRAJPUT RESTORATION INC08/17/2026
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTURAL PRESERVATION S12/29/2025
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC08/22/2023
DOB NOWSignSigned-offUNITECH DESIGN INC06/30/2023
DOB NOWPlumbingSigned-offT.N.T. PLBG & HTG, INC03/10/2023
DOB NOWMechanical SystemsSigned-offP3 CONSTRUCTION, LLC03/08/2023
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC08/30/2022
DOB NOWPlumbingSigned-offANGELO ANDREW INC01/17/2022
DOB NOWPlumbingSigned-offANGELO ANDREW INC11/18/2021
DOB NOWPlumbingPermit IssuedORBIT PLBG & HTG INC08/17/2021
DOB NOWGeneral ConstructionSigned-offYM PRO CORP08/06/2021
DOB NOWMechanical SystemsSigned-offTHE MANLYN DEVELOPMENT GR08/06/2021
DOB NOWGeneral ConstructionSigned-offYM PRO CORP06/30/2021
DOB NOWStructuralSigned-offTHE MANLYN DEVELOPMENT GR06/09/2021
DOB NOWGeneral ConstructionSigned-offTHE MANLYN DEVELOPMENT GR06/09/2021
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC09/24/2020
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC09/14/2020
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC09/13/2019
BISOTISSUEDYOUN DESIGN CORP10/24/2019
BISBLISSUEDBRYAN A. ENNIST05/28/2019
BISFSISSUEDBRYAN A. ENNIST04/05/2019
BISBLISSUEDBRYAN A. ENNIST03/28/2019
BISOTISSUEDAPPLE RESTORATION & WATERPROOF03/22/2019
BISEQISSUEDROCKLEDGE SCAFFOLD CORP03/14/2019
BISPLISSUEDCASA MECHANICAL CO. INC03/14/2019
BISOTISSUEDAPPLE RESTORATION & WATERPROOF06/06/2018
BISEQISSUEDROCKLEDGE SCAFFOLD CORP04/03/2018
BISOTISSUEDAPPLE RESTORATION & WATERPROOF10/16/2017
BISEQISSUEDROCKLEDGE SCAFFOLD CORP04/21/2017
BISEQISSUEDCOLGATE ENTERPRISE CORP08/03/2016
BISEQISSUEDLIU JIN INTERIOR CONTRACT01/12/2012
BISOTISSUEDLIU JIN INTERIOR CONTRACT01/12/2012
BISEQISSUEDJ & G GNRL CONTRACT CORP12/09/2011
BISFPISSUEDNY FIRE LLC11/09/2011
BISPLISSUEDCATMAN PLUMBING INC09/26/2011
BISMHISSUEDLIU JIN INTERIOR CONTRACT09/20/2011
BISOTISSUEDNICE INTERIOR OF NY03/12/2007
BISEQISSUEDNICE INTERIOR OF NY03/12/2007
+ 6 more permits on file
▾Field Inspections (DOB CAP) — 13
DateTypeResultReport
07/11/2023Pass-Final Sign Permit InspectionPassView ↗
06/01/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/07/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/21/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/17/2022Certified Sprinkler (PL)-SP-Fixtures (PL)-FinishCertifiedView ↗
03/01/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/21/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/18/2022Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
10/15/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/15/2021Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
10/15/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/15/2021Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/25/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
08/16/2026Post-installed AnchorsMd Rashidspecial
04/09/2025HVAC-R and service water piping design and insulation—energy_progress
04/09/2025Energy Code Compliance Inspections—progress
04/09/2025Tenant Protection Plan Compliance—special
02/13/2025Final—progress
02/13/2025Mechanical Systems—special
11/07/2024Structural Stability – Alterations of existing buildingsAnthony Addessospecial
11/07/2024Air barrier - visual inspectionAnthony Addessoenergy_progress
11/07/2024Energy Code Compliance InspectionsAnthony Addessoprogress
11/07/2024MasonryAnthony Addessospecial
11/07/2024Post-installed AnchorsAnthony Addessospecial
11/06/2024Tenant Protection Plan ComplianceMd Rashidspecial
10/03/2024FinalAnthony Addessoprogress
06/23/2023FinalJUSTIN KIMprogress
02/14/2023Energy Code Compliance InspectionsNICHOLAS MOSHOPOULOSprogress
02/14/2023Fire-Resistance Rated ConstructionNICHOLAS MOSHOPOULOSprogress
01/10/2023Tenant Protection Plan ComplianceNICHOLAS MOSHOPOULOSspecial
01/10/2023Tenant Protection Plan ComplianceNICHOLAS MOSHOPOULOSspecial
01/09/2023FinalNICHOLAS MOSHOPOULOSprogress
01/09/2023Mechanical SystemsNICHOLAS MOSHOPOULOSspecial
02/04/2022Energy Code Compliance InspectionsGregory Perottoprogress
02/04/2022Fire-Resistant Penetrations and JointsGregory Perottospecial
01/25/2022Fire-Resistant Penetrations and JointsGregory Perottospecial
01/25/2022Energy Code Compliance InspectionsGregory Perottoprogress
06/04/2021HVAC-R and service water piping design and insulationSERDAR CEYLANenergy_progress
Latest 25 of 34.
▾Documents — 243 on file (BIS + DOB NOW)
▸Plans & Drawings18
▸DOB NOWPlans/Sketch17
09/03/2026M00521670-I1Request digital key ↗
09/03/2026M00521717-I1Request digital key ↗
09/03/2026M00524378-I1Request digital key ↗
Showing 3 of 17 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00225009-I1Request digital key ↗
▸Applications & Permits49
▸BISWORK PERMIT APPLICATION19
10/23/2019140874604Open ↗
03/25/2019140705850Open ↗
03/14/2019140632304Open ↗
Showing 3 of 19 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION17
05/10/2021140705850Open ↗
10/23/2019140874604Open ↗
10/22/2019140836594Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWLPC Approval/Permit13
09/02/2026M00603684-I1Open ↗
09/02/2026M00603684-P1Open ↗
08/13/2026M01181352-I1Open ↗
Showing 3 of 13 on file for this type
▸Seals & Professional Certifications71
▸DOB NOWDPL-1: Design Professional Seal & Signature16
09/03/2026M00521717-I1Open ↗
09/03/2026M00524383-I1Open ↗
09/02/2026M00603684-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/23/2026M00524383-I1Open ↗
09/23/2026M00524383-I1Open ↗
09/01/2026M00225009-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
08/31/2026M00603684-P2Open ↗
08/28/2026M01446535-I1Open ↗
08/27/2026M00603684-I1Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
03/13/2020140836594Open ↗
09/27/2017140530094Open ↗
01/12/2012120946744Open ↗
Showing 3 of 6 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
10/11/2017140705850Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
10/11/2017140705850Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY5
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
10/11/2017140705850Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
01/12/2012120946744Open ↗
12/09/2011120919097Open ↗
11/30/2011120829595Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
01/12/2012120946744Open ↗
12/09/2011120919097Open ↗
09/30/2011120829595Open ↗
▸Trade Schedules & Equipment11
▸BISSELF-CERT PLUMBING NOTICE5
02/15/2012120829595Open ↗
01/25/2012120829595Open ↗
12/20/2011120829595Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING3
03/13/2019140836594Open ↗
11/30/2011120829595Open ↗
09/30/2011120829595Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
10/22/2019140836594Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
01/25/2012120829595Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
03/13/2019140836594Open ↗
▸Safety & Tenant Protection6
▸BISTENANT PROTECTION PLAN AND NOTES5
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
10/11/2017140705850Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWTenant Protection Plan1
08/13/2026M00225009-I1Open ↗
▸Environmental & Asbestos19
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
09/03/2026M00521717-I1Open ↗
09/03/2026M00524383-I1Open ↗
09/02/2026M00603684-I1Open ↗
Showing 3 of 13 on file for this type
▸BISTHIS IS NOT AN ASBESTOS PROJECT4
12/09/2011120919097Open ↗
10/26/2011120871155Open ↗
10/26/2011120871155Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
03/13/2019140836594Open ↗
10/11/2017140705850Open ↗
▸Energy Compliance13
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
▸BISTECHNICAL REPORT: ENERGY2
01/12/2012120946744Open ↗
09/30/2011120829595Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00521712-I1Open ↗
08/13/2026M00524378-I1Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
04/20/2017140632304Open ↗
▸BISNYCECC EXEMPTION1
10/11/2017140705850Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
03/13/2020140836594Open ↗
▸BISTR8: Energy Code Progress Inspections1
10/08/2013120829595Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
03/13/2020140836594Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY6
09/03/2020140632304Open ↗
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
Showing 3 of 6 on file for this type
▸BISMASONRY1
04/02/2021140705850Open ↗
▸Approvals, Objections & Sign-offs17
▸BISLANDMARKS APPROVAL6
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
10/11/2017140705850Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
01/12/2012120946744Open ↗
12/09/2011120919097Open ↗
10/26/2011120871155Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
05/14/2021140705850Open ↗
09/03/2020140632304Open ↗
03/13/2020140836594Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION2
03/13/2020140836594Open ↗
09/27/2017140530094Open ↗
▸BISFINAL1
05/14/2021140705850Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT7
03/13/2020140836594Open ↗
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
Showing 3 of 7 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
05/11/2021140705850Open ↗
▸Filing & Intake Forms16
▸BISEFILING JOB APPLICATION COVER SHEET5
10/23/2019140874604Open ↗
03/13/2019140836594Open ↗
10/11/2017140705850Open ↗
Showing 3 of 5 on file for this type
▸BISADDITIONAL INFORMATION4
10/22/2019140836594Open ↗
11/20/2013120829595Open ↗
10/08/2013120829595Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET4
01/12/2012120946744Open ↗
12/09/2011120919097Open ↗
10/26/2011120871155Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
03/13/2020140836594Open ↗
10/18/2019140836594Open ↗
09/27/2017140530094Open ↗
▸Other Documents8
▸BISBPP - SUPPORTING DOCUMENTATION2
05/14/2021140705850Open ↗
05/14/2021140705850Open ↗
▸DOB NOWProof of Historic Building2
08/13/2026M00810093-I1Open ↗
08/13/2026M00810091-I1Open ↗
▸DOB NOWIRA Certification1
08/13/2026M01326788-I1Open ↗
▸DOB NOWDHCR Document1
08/13/2026M00225009-I1Open ↗
▸DOB NOWCalculations1
08/20/2026M01446552-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/20/2026M01446552-I1Open ↗