← Back
Two family frame
138 DOWNES AVENUE
STATEN ISLAND · Annadale-Huguenot-Prince's Bay-Woodrow · BIN 5146849
💬 Discuss this project
2006Year Built
2Stories
B2Building Class
R3XZoning
—Gross Floor Area
2Units
Two family frame · 0.6 FAR built · Flood zone X
Locations of Work
Electrical
Roof1p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC104/08/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272104/08/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
08/04/2025
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01207475-I1
04/15/2025
Permit issued — Solar
S01207475-I1-SL
04/08/2025
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01207475-I1
04/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
04/08/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
04/08/2025
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
04/08/2025
Special inspection requirement — Final
Walid Abdulla
04/08/2025
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC04/15/2025
BIS—ISSUEDGLM DEVELOPMENT, CORP.03/26/2007
BIS—ISSUEDGLM DEVELOPMENT, CORP.03/24/2006
BISEQISSUEDGLM DEVELOPMENT, CORP.12/14/2005
BISPLISSUEDJ.P. COURY, INC.03/21/2005
BIS—ISSUEDGLM DEVELOPMENT, CORP.02/24/2005
BISEQISSUEDGLM DEVELOPMENT, CORP.02/18/2005
1 project · most recent 04/08/2025
FiledStatusContractorScope
04/08/2025CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/08/2025Fire-Resistant Penetrations and JointsWalid Abdullaspecial
04/08/2025Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
04/08/2025Energy Code Compliance InspectionsWalid Abdullaprogress
04/08/2025FinalWalid Abdullaprogress
04/08/2025Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026S01207475-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/26/2026S01207475-I1Open ↗
08/26/2026S01207475-I1Open ↗
08/26/2026S01207475-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026S01207475-I1Open ↗
08/26/2026S01207475-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01207475-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01207475-I1Open ↗