| Owner | Filings | Most Recent |
|---|---|---|
| Murray Hill Place | 34 | 07/08/2026 |
| National Center Foundation | 13 | 03/22/2026 |
| 954 Second Avenue | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Patti & Anthes Consulting Engineers | 8 | 03/21/2022 |
| Urbantech Consulting Engineering | 1 | 08/26/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| EA Design Group | 18 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JRM Construction Management | General Contractor | 5 | 07/08/2026 |
| A Plus Plumbing | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AK Engineering | 678 | 11 | 03/21/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | JRM Construction Management | 08/31/2021 |
| DOB NOW | Plumbing | Signed-off | A Plus Plumbing | 08/30/2021 |
| DOB NOW | Mechanical Systems | Signed-off | JRM Construction Management | 06/24/2021 |
| DOB NOW | Mechanical Systems | Signed-off | JRM Construction Management | 06/24/2021 |
| BIS | PL | ISSUED | Allcounty Plumbing & Heating | 08/05/2019 |
| BIS | PL | ISSUED | Allcounty Plumbing & Heating | 04/13/2018 |
| BIS | BL | ISSUED | Allcounty Plumbing & Heating | 04/13/2018 |
| BIS | EQ | ISSUED | Bay Restoration | 05/26/2015 |
| BIS | OT | ISSUED | Bay Restoration | 05/22/2015 |
| BIS | PL | ISSUED | Allcounty Plumbing & Heating | 06/04/2012 |
| BIS | PL | ISSUED | Hod Piping & Heating | 08/07/2009 |
| BIS | PL | ISSUED | Hod Piping & Heating | 04/20/2009 |
| BIS | — | ISSUED | Tishman Construction | 01/11/2001 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 05/08/2000 |
| BIS | SP | ISSUED | Premier Firesupression | 05/04/2000 |
| BIS | SD | ISSUED | Premir Fire Supression | 01/27/2000 |
| BIS | — | ISSUED | Tishman Construction | 01/25/2000 |
| BIS | EQ | ISSUED | Tishman Construction | 01/25/2000 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 12/30/1999 |
| BIS | EQ | ISSUED | York Scaffold Equipment | 12/15/1999 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 12/07/1999 |
| BIS | EQ | ISSUED | York Scaffold Equipment | 12/01/1999 |
| BIS | MH | ISSUED | C C Controlled Combustion | 11/19/1999 |
| BIS | PL | ISSUED | G.bassolino Plumbing | 11/19/1999 |
| BIS | FS | ISSUED | C C Controlled Combustion | 11/17/1999 |
| BIS | PL | ISSUED | Par Plumbing Co | 06/10/1999 |
| BIS | MH | ISSUED | Tishman Construction | 05/24/1999 |
| BIS | EQ | ISSUED | York Scaffold Equipment | 05/06/1999 |
| BIS | EQ | ISSUED | York Scaffold Equipment | 04/29/1999 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 04/23/1999 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 04/16/1999 |
| BIS | SP | ISSUED | Premier Firesupression | 02/17/1999 |
| BIS | — | RE-ISSUED | Tishman Construction | 01/25/1999 |
| BIS | EQ | ISSUED | Tishman Construction | 01/13/1999 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 12/18/1998 |
| BIS | SD | ISSUED | Premir Fire Supression | 12/17/1998 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 12/10/1998 |
| BIS | FP | ISSUED | B & J Fire Inc T/A. Masters | 10/08/1998 |
| BIS | — | ISSUED | Tishman Construction | 09/11/1998 |
| BIS | EQ | ISSUED | Regional Scaffold & Hoisting | 07/28/1998 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/14/2024 | Permit Issued | Patriot Electric | General Wiring |
| 10/18/2022 | Permit Issued | Patriot Electric | General Wiring |
| 10/25/2021 | Permit Issued | PJZ Maintenance | General Wiring |
| 07/05/2021 | Complete | Freedom Electl & Data | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/21/2022 | Fuel-Oil Storage and Fuel-Oil Piping Systems | Ari Kamo | special |
| 03/21/2022 | Fuel-Oil Storage and Fuel-Oil Piping Systems | Ari Kamo | special |
| 02/10/2022 | Fuel-Oil Storage and Fuel-Oil Piping Systems | Ari Kamo | special |
| 10/12/2021 | Final | Ari Kamo | progress |
| 10/12/2021 | Maintenance information | Ari Kamo | energy_progress |
| 10/12/2021 | HVAC-R and service water piping design and insulation | Ari Kamo | energy_progress |
| 10/12/2021 | HVAC-R and service water heating system controls | Ari Kamo | energy_progress |
| 10/12/2021 | HVAC-R and service water heating equipment | Ari Kamo | energy_progress |
| 10/12/2021 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 10/12/2021 | Mechanical Systems | Ari Kamo | special |
| 10/12/2021 | Energy Code Compliance Inspections | Ari Kamo | progress |
| 10/06/2021 | Maintenance information | Ari Kamo | energy_progress |
| 10/06/2021 | HVAC-R and service water piping design and insulation | Ari Kamo | energy_progress |
| 10/06/2021 | HVAC-R and service water heating equipment | Ari Kamo | energy_progress |
| 10/06/2021 | Electrical motors and elevators | Ari Kamo | energy_progress |
| 10/06/2021 | Energy Code Compliance Inspections | Ari Kamo | progress |
| 10/06/2021 | HVAC-R and service water heating system controls | Ari Kamo | energy_progress |
| 10/06/2021 | Heating Systems | Ari Kamo | special |
| 10/06/2021 | Mechanical Systems | Ari Kamo | special |
| 10/06/2021 | Chimneys and vents | Ari Kamo | special |
| 10/06/2021 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 10/06/2021 | Final | Ari Kamo | progress |
| 09/22/2021 | Mechanical Systems | Ari Kamo | special |
| 09/22/2021 | Energy Code Compliance Inspections | Ari Kamo | progress |
| 09/22/2021 | Final | Ari Kamo | progress |