ECB06/11/2026RESPONDING TO AN INCIDENT WHERE A WORKER FELL APPROX. 25' FROM A MAN LIFT BASKET WHILE RELOCATING IT WITH THE PLATFORM ELEVATED AND OVEREXTENDED. THE OPERATOR WASN'T WEARING A SAFETY HARNESS AND WASN'T TIED OFFHearing held — result not yet published$2K proposed
ECB02/25/2025FAILURE TO MAINTAIN BUILDING WALLS AND APPURTENANCES. NOTE: QEWI FILEDAMENDED SAFE #TR6-909211-9B-A1. AT TIME OF INSPECTION, I OBSERVED BROKEN GLASS(X2) AT EXPOSURE(1) SOUTH ELEVATION, AND INADEQUATE AC UNITS SNothing owed — awaiting certificate of correction
ECB01/12/2023NO DOB APPROVED SET(EN DRAWING,COM/CHECK, ARCHITECTURAL DRAWING) PROVIDED ON JOB SITE AT THE TIME OF INSPECTION, PROVIDE APPROVED /ACCEPTED CONSTRUCTION DOCUMENTS; PLEASE GO TO HTTPS://WWW1.NYC.GOV/SITE/BUILDINNothing owed — awaiting certificate of correction
ECB06/07/2022IN RESPONSE TO ABOVE COMPLAINT OBSERVED CHAIN LINK FENCE AROUND THE SITE WITH SEE-THROUGH FABRIC AROUND CONTRARY TO BC3307.7.4 #4 THAT SPECIFIES THAT THERE SHALL BE OPAQUE STURDY CLOTH "WINDSCREEN" FABRIC AT ALNothing owed — awaiting certificate of correction
ECB04/11/202228-110.2 PHASE SHIFTING SITE SAFETY PLAN.AT TIME OF INSPECTION ON AN 1STORY TOPPED OFF NB UNDER PERMIT#322066367,IT WAS OBSERVED ONGOING CONSTRUCTION OPERATION.UPON REVIEW OF THE SITE SAFETY PLAN,IT WAS OBSERVENothing owed — awaiting certificate of correction
ECB09/28/2020PROTECTION OF PEDESTRIANS(WARNING SIGNS,PERSONNEL & BARRIERS). AT THE TIME OF MY INSPECTION,I OBSERVED AN APPROX 3" DIAMETER WATER HOSE EXTENDING FROM ACROSS THE STREET & TRAVERSING THE PEDESTRIAN SIDEWALK AT ENothing owed — awaiting certificate of correction
ECB09/28/2020WORK CONTRARY TO CONSTRUCTION DOCUMENTS(SUPPORT OF EXCAVATION). AT THE TIME OF MY INSPECTION,I OBSERVED THAT THE SUPPORT OF EXCAVATION(SOE)FOR THE UTILITY LINES AT EXP#3 WAS INSTALLED CONTRARY TO THE DRAWINGSNothing owed — awaiting certificate of correction
ECB09/28/2020DOCUMENTS TO BE KEPT ON SITE(DEP PERMIT). AT THE TIME OF MY INSPECTION,I OBSERVED AN APPROX 3" DIAMETER WATER HOSE EXTENDING FROM A FIRE HYDRANT ACROSS THE STREET INTO THE JOBSITE FORTHE USE FO THE INSTALLATIONNothing owed — awaiting certificate of correction
ECB08/17/2020@TIME OF INSPECTION, OBSERVED ON GOING CONSTRUCTION ACTIVITIES CONTRARY TO MAYOR'S EMERGENCY EXECUTIVE ARDEX 120 & SUBSEQUENT ORDERS INCORPORATING REQUIREMENTS OF GOVERNOR'S EXECUTIVE ORDER 202.34. AND SUBSEQUENothing owed — awaiting certificate of correction