← Back
BuildNYC
Parochial school, yeshiva
Trinity School
139 WEST 91ST STREET · BIN 1032497
💬 Discuss this project
1894Year Built
4Stories
W2Building Class
R7-2Zoning
38,264 sfGross Floor Area
1Units
LL97 Covered0 Active Violations
Parochial school, yeshiva · 12,588 sf lot · 3.04 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentLandscapeGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofTrinity School10p · 2 filings · 10 docs
Floor 34p · 2 filings · 4 docs
Floor 2
Floor 1Trinity School10p · 2 filings · 10 docs
Site & exteriorTrinity School13p · 3 filings · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Trinity Episcopal School5907/08/2026
Hse System603/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Ashraf104/26/2024
Enthink Engineers208/21/2023
Tohfaz Uddin PE405/10/2023
KZ Engineering207/13/2022
Landmark Facilities Group105/15/2020
Joshua Brandfonbrener Architect212/11/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rigid Structural Design103/21/2026
Spring Scaffolding803/21/2026
Synergy Building Consultants203/21/2026
Design 2147503/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Spring ScaffoldingScaffold1007/08/2026
Cannon Mechanicalspecialty_contractor407/08/2026
Andamio ScaffoldingScaffold407/08/2026
Topline ElectricElectrical303/21/2026
Ceprine ConstructionScaffold303/21/2026
A & M Electrical ServiceElectrical103/21/2026
Katz MichaelElectrical103/21/2026
Allstate Electrical ContElectrical103/21/2026
Allstate Electrical ContElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Future Tech Consultants O589105/15/2020
Building Lifecycle
All (47)Filed (12)Permit Issued (9)Signed Off (8)Violation (10)Objection (6)Special Inspection (2)
12/01/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/18/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-S2
11/18/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-S3
11/18/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-S1
08/08/2024
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01042360-I1
04/29/2024
Permit issued — Supported Scaffold
M01042360-I1-SF
04/26/2024
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01042360-I1
03/11/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-I1
08/28/2023
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00907075-I1
08/21/2023
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00907075-P1
07/26/2023
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00907075-I1
07/26/2023
Permit issued — Supported Scaffold
M00907075-I1-SF
05/26/2023
Signed off — Alteration
FILING HEREWITH MECHANICAL AS PER PLANS. NO CHANGE IN USE EGRESS OR OCCUPANCY.
M00340238-I1
05/23/2023
Signed off — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00752502-I1
05/12/2023
Permit issued — Supported Scaffold
M00858694-S1-SF
05/12/2023
Permit issued — Construction Fence
M00858694-S2-FN
05/10/2023
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-S2
05/10/2023
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-S3
05/10/2023
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-S1
05/10/2023
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00858694-I1
05/10/2023
Permit issued — Protection and Mechanical Methods
M00858694-S3-PMM
05/10/2023
Permit issued — Sidewalk Shed
M00858694-I1-SH
08/02/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/13/2022
Filed — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00752502-P1
06/16/2022
Permit issued — Supported Scaffold
M00752502-I1-SF
06/15/2022
Filed — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00752502-I1
05/31/2022
Permit issued — Mechanical Systems
M00340238-I1-MS
04/29/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/02/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/23/2020
Permit issued — Mechanical Systems
M00340238-I1-MS
05/18/2020
Objection raised — Inspections
05/18/2020
Objection resolved — Addressed
05/18/2020
Objection raised — Scope
05/18/2020
Objection resolved — Addressed
05/18/2020
Objection raised — Inspections
05/18/2020
Objection resolved — Addressed
05/15/2020
Filed — Alteration
FILING HEREWITH MECHANICAL AS PER PLANS. NO CHANGE IN USE EGRESS OR OCCUPANCY.
M00340238-I1
05/02/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/06/2020
Special inspection requirement — Mechanical Systems
Stephen Marchese
04/06/2020
Special inspection requirement — Final
Stephen Marchese
12/11/2019
Filed — No Work
M00270706-I1
05/03/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/11/2018
Filed — No Work
M00108193-I1
09/23/2015
Violation issued (ECB, closed)
Construction
01/19/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/29/1995
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding04/29/2024
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding07/26/2023
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding05/12/2023
DOB NOWConstruction FenceSigned-offSpring Scaffolding05/12/2023
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding05/10/2023
DOB NOWSidewalk ShedSigned-offSpring Scaffolding05/10/2023
DOB NOWSupported ScaffoldSigned-offCeprine Construction06/16/2022
DOB NOWMechanical SystemsSigned-offCannon Mechanical05/31/2022
DOB NOWMechanical SystemsSigned-offCannon Mechanical06/23/2020
BISOTISSUEDArchstone Builders07/07/2020
BISOTISSUEDArchstone Builders06/04/2020
BISPLISSUEDPar Plumbing Co07/27/2017
BIS—ISSUEDTishman Construction07/21/2017
BISOTISSUEDA.W. & S. Construction Co07/14/2017
BISEQISSUEDYork Scaffold Equipment07/12/2017
BISEQISSUEDSafway Atlantic03/03/2017
BISOTISSUEDTishman Construction10/13/2016
BISOTISSUEDTishman Construction10/12/2016
BISSPISSUEDPreferred Sprinkler and Mechanical09/27/2016
BISEQISSUEDHse System08/23/2016
BISEQISSUEDHse System08/23/2016
BISEQISSUEDSafway Atlantic07/22/2016
BISEQISSUEDHse System07/15/2016
BISEQISSUEDSafway Atlantic03/14/2016
BISEQISSUEDSafway Atlantic03/14/2016
BISOTISSUEDA.W. & S. Construction Co10/21/2015
BISOTISSUEDA.W. & S. Construction Co10/21/2015
BISOTISSUEDTishman Construction10/06/2015
BISOTISSUEDTishman Construction10/06/2015
BISEQISSUEDHse System09/23/2015
BISEQISSUEDHse System09/23/2015
BISEQISSUEDHse System08/07/2015
BISEQISSUEDColgate Enterprise07/02/2015
BISEQISSUEDEverest Scaffolding06/23/2015
BISEQISSUEDEverest Scaffolding06/19/2015
BISOTISSUEDTishman Construction04/29/2015
BISOTISSUEDTishman Interiors03/30/2015
BISOTISSUEDTishman Construction03/16/2015
BISPLISSUEDMac Felder08/01/2012
BISOTISSUEDA.W. & S. Construction Co07/27/2012
+ 6 more permits on file
9 projects · most recent 10/04/2023
General Wiring Lighting
FiledStatusContractorScope
10/04/2023CompleteTopline ElectricGeneral Wiring
10/04/2023CompleteTopline ElectricGeneral Wiring
10/04/2023CompleteTopline ElectricGeneral Wiring
06/20/2023Permit IssuedAllstate Electrical Cont—
06/16/2020CompleteAllstate Electrical ContGeneral Wiring
06/08/2020Permit IssuedAllstate Electrical ContGeneral Wiring
05/01/2020CompleteAllstate Electrical ContGeneral Wiring
07/29/2019CancelledLippolis ElectricLighting
04/16/2019CompleteTop Shelf Electric—
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
04/06/2020Mechanical SystemsStephen Marchesespecial
04/06/2020FinalStephen Marcheseprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Trinity SchoolEducationEntire building
Project M01042360 Alteration · LOC Issued · 04/26/2024
Project M00907075 Alteration · LOC Issued · 07/26/2023
Project M00858694 Alteration · LOC Issued · 05/10/2023
Project M00752502 Alteration · LOC Issued · 06/15/2022
Project M00340238 Alteration · LOC Issued · 05/15/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 536 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch9
09/02/2026M00752502-P1Request digital key ↗
09/02/2026M00752502-I1Request digital key ↗
08/31/2026M00858694-S1Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly2
09/06/2026M00108193-I1Request digital key ↗
09/05/2026M00270706-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/15/2026M00340238-I1Request digital key ↗
▸Applications & Permits78
▸BISPLAN / WORK APPROVAL APPLICATION41
08/12/2024121191771Open ↗
01/23/2024123100134Open ↗
10/25/2023123100134Open ↗
Showing 3 of 41 on file for this type
▸BISWORK PERMIT APPLICATION34
07/07/2020140910575Open ↗
07/07/2020140910575Open ↗
06/04/2020140893326Open ↗
Showing 3 of 34 on file for this type
▸BISPLACE OF ASSEMBLY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWLPC Approval/Permit1
08/13/2026M00340238-I1Open ↗
▸Seals & Professional Certifications115
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION56
06/15/2018140666447Open ↗
05/03/2018122337444Open ↗
05/03/2018122337676Open ↗
Showing 3 of 56 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST15
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 15 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT15
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 15 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
09/06/2026M00108193-I1Open ↗
09/02/2026M00752502-I1Open ↗
09/02/2026M00752502-P1Open ↗
Showing 3 of 12 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
06/23/2020140910575Open ↗
04/22/2020140893326Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/29/2026M00340238-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/29/2026M00340238-I1Open ↗
▸Trade Schedules & Equipment19
▸BISEQUIPMENT USE PERMITS5
08/16/2024121191771Open ↗
03/06/2024121191771Open ↗
Showing 2 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT4
08/16/2024121191771Open ↗
Showing 1 of 4 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
07/31/2019122823445Open ↗
Showing 1 of 2 on file for this type
▸BISSCHEDULE B - PLUMBING2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
10/13/2017121191771Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos21
▸BISASBESTOS: CERTIFICATION (DEP ACP5)10
06/23/2020140910575Open ↗
05/26/2020140893326Open ↗
Showing 2 of 10 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)6
11/07/2022122823445Open ↗
Showing 1 of 6 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
07/07/2020140910575Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026M00340238-I1Open ↗
▸Energy Compliance33
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY13
12/18/2023123100134Open ↗
08/15/2022123100134Open ↗
08/15/2022123100134Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS10
12/11/2017121191771Open ↗
11/29/2017121191771Open ↗
Showing 2 of 10 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)3
09/19/2023122550523Open ↗
02/09/2023140910575Open ↗
11/10/2021140893326Open ↗
▸BISAS-BUILT ENERGY ANALYSIS3
12/11/2017121191771Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
06/23/2020140910575Open ↗
▸BISINTERIOR LIGHTING POWER1
01/09/2023123100134Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISENERGY CODE ANALYSIS INCOMPLETE1
12/11/2017121191771Open ↗
▸Inspections & Test Reports40
▸BISTECHNICAL REPORT: RESPONSIBILITY30
09/19/2023122550523Open ↗
12/22/2021140893326Open ↗
12/22/2021140893326Open ↗
Showing 3 of 30 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
09/29/2017121191771Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: PILE DRIVING2
05/03/2018122337444Open ↗
03/12/2018122337676Open ↗
▸BISPOST-INSTALLED ANCHORS1
04/18/2022140910575Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTRUCTURAL STEEL - DETAILS1
04/18/2022140910575Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
09/19/2023122550523Open ↗
▸BISMASONRY1
09/19/2023122550523Open ↗
▸Approvals, Objections & Sign-offs92
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST43
10/11/2023122550523Open ↗
02/17/2023140910575Open ↗
11/07/2022122823445Open ↗
Showing 3 of 43 on file for this type
▸BISLANDMARKS APPROVAL14
06/23/2020140910575Open ↗
05/15/2020140893326Open ↗
Showing 2 of 14 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION11
08/20/2024121191771Open ↗
10/11/2023122550523Open ↗
10/13/2017121191771Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
09/06/2026M00108193-I1Open ↗
09/02/2026M00752502-I1Open ↗
09/02/2026M00752502-P1Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS SIGNOFF6
03/09/2023121191771Open ↗
01/09/2023122550523Open ↗
01/09/2023123100134Open ↗
Showing 3 of 6 on file for this type
▸BISFINAL4
09/19/2023122550523Open ↗
08/04/2023123100134Open ↗
01/25/2022140910575Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE1
08/12/2024121191771Open ↗
▸Cost, Insurance & Ownership29
▸BISCOST AFFIDAVIT23
06/23/2020140910575Open ↗
04/22/2020140893326Open ↗
07/18/2018110207473Open ↗
Showing 3 of 23 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW36
03/10/2023121191771Open ↗
02/21/2023122550523Open ↗
02/21/2023123100134Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms71
▸BISBOROUGH INTAKE FORM25
02/12/2020121191771Open ↗
10/11/2019121191771Open ↗
10/04/2019121191771Open ↗
Showing 3 of 25 on file for this type
▸BISEFILING COVER SHEET21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISADDITIONAL INFORMATION18
02/10/2023140910575Open ↗
12/21/2021140893326Open ↗
12/21/2021140893326Open ↗
Showing 3 of 18 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET7
06/23/2020140910575Open ↗
04/22/2020140893326Open ↗
Showing 2 of 7 on file for this type
▸Other Documents16
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION10
10/17/2023102906759Open ↗
Showing 1 of 10 on file for this type
▸BISSupporting Document: Fee Deferment3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFEE EXEMPTION DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPRIOR TO NEXT RENEWAL UPLOAD A COPY OFTHE CERTIFICATE OF COMPLIANCE FOR SERVICE EQUIPMENT.1
06/06/2024121191771Open ↗