DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
DOB06/22/2018VIOLATION ISSUED FOR FAILURE TO FILE 2016 ANNUAL HIGH PRESSURE BOILER INSPECTION
DOB06/23/2017VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION
DOB05/15/2014VIOLATION ISSUED FOR FAILURE TO FILE 2012 ANNUAL HIGH PRESSURE BOILER INSPECTION
ECB11/07/200848B.50A.50B.50C.50A COMBUSTION LEAK ATLOWER HAND HOLE ALLOWING SPILLAGE OF COMBUSTABLE PRODUCTS IN BOILER RM 50B GAUGE GLASS DRAIN NOT PIPED TO A SAFE LOCATION 50C FLU PIPE NOT PROPERLY SUPPORTED STRUCTUALLYNothing owed — awaiting certificate of correction
ECB12/20/2006NONHAZARDOUS.B4A,50A,50B,50C.50A-FLU PIPE NOT PROPERLY CONNECTED AT SECTIONS.50B-REVERSE BLOW DOWN VALVE TO HAVE SLOW OPENING VALVE TERMINATE LAST.50C-POOR LIGHTING IN BOILER ROOM.Nothing owed — awaiting certificate of correction