| Owner | Filings | Most Recent |
|---|---|---|
| Capstone Equities | 41 | 07/08/2026 |
| NO | 39 | 10/20/2026 |
| Nightingale Properties | 28 | 07/08/2026 |
| 14 53rd Street Owner | 25 | 03/22/2026 |
| SL Whale Realty LLC Brickwell | 11 | 03/21/2026 |
| Ang Contracting | 10 | 07/08/2026 |
| Madison Realty Capital | 10 | 03/21/2026 |
| 15 53rd St Property Owner | 4 | 03/21/2026 |
| Greenline Building Consultants | 3 | 03/22/2026 |
| NYC Department of Housing Preservation and Development | 2 | 03/21/2026 |
| 14 53 Owner | 1 | 03/22/2026 |
| Chashama | 1 | 03/22/2026 |
| Metro | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/25/2020 | $84.1M | — | — → — | $220/sf building |
| 08/10/2015 | $82.5M | — | — → — | $216/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Gene Kaufman Architect | 24 | 09/24/2026 |
| Rigid Structural Design | 6 | 09/23/2026 |
| Eoc-NY | 3 | 07/29/2026 |
| Backforty Architecture | 10 | 03/31/2026 |
| Jack Green Associates | 7 | 03/13/2026 |
| Zachary Gidich Architecture and Des | 1 | 03/06/2026 |
| John F. Giuseffi, Architect | 1 | 12/27/2023 |
| Leslie M. Good Architects | 1 | 06/14/2023 |
| MW Wellet Engineering | 6 | 05/10/2023 |
| Basic Groups | 4 | 10/27/2022 |
| RSC Architects | 2 | 10/13/2022 |
| Project Tactical Solutions | 1 | 09/28/2022 |
| Bala Consulting Engineers | 2 | 01/24/2022 |
| Robert Derector Associates | 4 | 01/18/2022 |
| Studios Architecture | 2 | 01/14/2022 |
| Enthink Engineers | 1 | 09/24/2021 |
| Patuxent Engineering | 1 | 03/28/2019 |
| Pace Engineering | 2 | 11/07/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM Zoning | 26 | 03/21/2026 |
| Rigid Structural Design | 8 | 03/21/2026 |
| Gene Kaufman Architect | 17 | 03/21/2026 |
| DVA Advisors | 6 | 03/21/2026 |
| Direct Access Expediting | 2 | 03/21/2026 |
| Basic Groups | 8 | 03/21/2026 |
| Patuxent Engineering | 2 | 03/21/2026 |
| Eurocelt Expediting | 4 | 03/21/2026 |
| EA Design Group | 6 | 03/21/2026 |
| Municipal Building Consultants | 9 | 03/21/2026 |
| MMSR Consulting Group | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Andamio Scaffolding | Scaffold | 8 | 10/20/2026 |
| Consolidated Scaffolding | Scaffold | 7 | 07/08/2026 |
| Niche Waterproofing | specialty_contractor | 4 | 06/28/2026 |
| Nyeg | General Contractor | 4 | 07/08/2026 |
| Ang Contracting | General Contractor | 4 | 07/08/2026 |
| Ocgp | General Contractor | 4 | 07/08/2026 |
| L&T Consultants | General Contractor | 3 | 03/21/2026 |
| Ashlar Mechanical | Fire Protection | 3 | 07/08/2026 |
| Holt Construction | General Contractor | 3 | 07/08/2026 |
| Parkview P&H | Plumbing | 2 | 07/08/2026 |
| Arthur Klansky | Electrical | 2 | 03/21/2026 |
| Sal Builders | General Contractor | 2 | 07/08/2026 |
| Miller Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| New Era Mechanical Services | Plumbing | 1 | 07/08/2026 |
| Maor Electr'l Service | Electrical | 1 | 03/21/2026 |
| AAA Total Plumbing | Fire Protection | 1 | 07/08/2026 |
| Arco Plumbing and Heating | Fire Protection | 1 | 07/17/2026 |
| Joseph Weinstein Electric | Electrical | 1 | 03/22/2026 |
| Brook Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Expert Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| AL-Lectric Elect'l Contracting | Electrical | 1 | 03/22/2026 |
| Miller Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| MJ General Mechanical | Plumbing | 1 | 07/08/2026 |
| Good-Will Mechanical | specialty_contractor | 1 | 07/08/2026 |
| Platinum Builders | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| City-Wide Testing | 416 | 5 | 09/24/2026 |
| Eoc-NY | 6548 | 3 | 07/29/2026 |
| Jack Green Associates | 422 | 9 | 03/13/2026 |
| CNS Inspection Services | 7566 | 1 | 06/27/2024 |
| Acv Design | 3864 | 1 | 06/14/2023 |
| Project Tactical Solution | 5859 | 6 | 05/10/2023 |
| Andrew Goodrich, P.E., PL | 965 | 4 | 10/27/2022 |
| Big Apple Group NY A Rma | 9168 | 2 | 01/24/2022 |
| Domani Inspection Service | 843 | 6 | 01/18/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | Andamio Scaffolding | 10/19/2026 |
| DOB NOW | Sprinklers | Permit Issued | Arco Plumbing and Heating | 07/16/2026 |
| DOB NOW | General Construction | Permit Issued | Niche Waterproofing | 06/22/2026 |
| DOB NOW | General Construction | Permit Issued | Niche Waterproofing | 06/22/2026 |
| DOB NOW | Structural | Permit Issued | Niche Waterproofing | 06/16/2026 |
| DOB NOW | Sprinklers | Permit Issued | Ashlar Mechanical | 05/13/2026 |
| DOB NOW | Plumbing | Signed-off | Expert Plumbing & Heating | 05/05/2026 |
| DOB NOW | Plumbing | Permit Issued | Parkview P&H | 04/30/2026 |
| DOB NOW | General Construction | Permit Issued | Platinum Builders | 04/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Holt Construction | 04/10/2026 |
| DOB NOW | Structural | Permit Issued | Holt Construction | 04/10/2026 |
| DOB NOW | Foundation | Permit Issued | Holt Construction | 03/12/2026 |
| DOB NOW | General Construction | Permit Issued | Niche Waterproofing | 01/20/2026 |
| DOB NOW | Standpipe | Permit Issued | Ashlar Mechanical | 11/28/2025 |
| DOB NOW | Plumbing | Permit Issued | Parkview P&H | 11/26/2025 |
| DOB NOW | Sprinklers | Permit Issued | Ashlar Mechanical | 11/26/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | Andamio Scaffolding | 10/24/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | Andamio Scaffolding | 10/21/2025 |
| DOB NOW | Plumbing | Permit Issued | MJ General Mechanical | 02/10/2025 |
| DOB NOW | Plumbing | Permit Issued | Miller Plumbing & Heating | 07/26/2024 |
| DOB NOW | Sprinklers | Permit Issued | Miller Plumbing & Heating | 01/22/2024 |
| DOB NOW | General Construction | Permit Issued | Sal Builders | 12/29/2023 |
| DOB NOW | Plumbing | Permit Issued | Miller Plumbing & Heating | 12/29/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | Sal Builders | 12/29/2023 |
| DOB NOW | Plumbing | Signed-off | New Era Mechanical Services | 12/14/2023 |
| DOB NOW | General Construction | Permit Issued | L&T Consultants | 06/17/2023 |
| DOB NOW | Structural | Signed-off | Ang Contracting | 12/27/2022 |
| DOB NOW | Sprinklers | Permit Issued | AAA Total Plumbing | 09/19/2022 |
| DOB NOW | Plumbing | Permit Issued | Brook Plumbing & Heating | 08/04/2022 |
| DOB NOW | Mechanical Systems | Signed-off | Goodwill Mechanical | 07/27/2022 |
| DOB NOW | General Construction | Signed-off | Ang Contracting | 07/12/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | Nyeg | 05/12/2022 |
| DOB NOW | General Construction | Permit Issued | Nyeg | 05/12/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | Ocgp | 03/30/2022 |
| DOB NOW | General Construction | Permit Issued | Ocgp | 03/30/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Andamio Scaffolding | 09/24/2021 |
| DOB NOW | Supported Scaffold | Permit Issued | Consolidated Scaffolding | 06/26/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | Consolidated Scaffolding | 06/26/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | Consolidated Scaffolding | 11/08/2018 |
| DOB NOW | Supported Scaffold | Permit Issued | Consolidated Scaffolding | 10/31/2018 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/13/2026 | Permit Issued | Platinum Builders | Air Conditioning Systems | Cooling Lg ARNU543B8A4 54,000 BTU · Vrf Indoor ×3 ARNU153TQD4 15,400 BTU · Vrf Indoor ×1 ARNU243MAA4 24,200 BTU · Vrf Indoor ×1 ARNU423B8A4 42,000 BTU · Vrf Indoor ×1 ARNU423M2A4 42,000 BTU · Vrf Indoor ×1 ARUM241BTE5 240,000 BTU · Vrf Outdoor ×1 ARUMO72BSS5 72,000 BTU · Vrf Outdoor ×1 |
| 12/27/2023 | Permit Issued | Sal Builders | Heating and Air Conditioning Systems | Heat / Cool Lg ARNU483M3A4 48,100 BTU · Vrf Indoor ×3 ARNU243M1A4 24,200 BTU · Vrf Indoor ×1 ARNU763B8A4 76,400 BTU · Vrf Indoor ×1 ARNU963B8A4 95,900 BTU · Vrf Indoor ×1 ARUM072BTE5 72,000 BTU · Vrf Outdoor ×1 ARUM096BTE5 96,000 BTU · Vrf Outdoor ×1 ARUM144BTE5 144,000 BTU · Vrf Outdoor ×1 ARUN060GSS4 24,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2025 | Permit Issued | Ashlar Mechanical | 3 heads, 1 outlets |
| 06/27/2024 | — | — | — |
| 06/27/2024 | — | — | — |
| 06/27/2024 | — | — | 12 heads |
| 06/27/2024 | — | — | — |
| 12/27/2023 | Permit Issued | Miller Plumbing & Heating | — |
| 10/27/2022 | Permit Issued | AAA Total Plumbing | 55 heads |
| 01/18/2022 | — | — | 291 heads, 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Signed-off | Expert Plumbing & Heating | Water/Sanitary |
| 09/10/2025 | Permit Issued | Parkview P&H | Storm, Water/Sanitary |
| 09/04/2024 | Permit Issued | Centa Plumbing & Heating | Water/Sanitary |
| 08/29/2024 | Permit Issued | Rockefeller Plumbing & Heating I | Water/Sanitary |
| 12/27/2023 | Permit Issued | Rockefeller Plumbing & Heating I | Water/Sanitary |
| 12/14/2023 | Signed-off | New Era Mechanical Services | Water/Sanitary |
| 11/09/2022 | Permit Issued | Brook Plumbing & Heating | Gas, Water/Sanitary |
| 01/18/2022 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/08/2026 | Permit Issued | Ennell Group Electric | — |
| 10/07/2026 | Permit Issued | Ennell Group Electric | General Wiring |
| 04/22/2026 | Cancelled | L&B Electrical International | General Wiring |
| 02/18/2026 | Permit Issued | Borowide Elect'l Contractors | — |
| 01/27/2025 | Complete | Ket Electric | General Wiring |
| 01/23/2025 | Permit Issued | Madison Electric | General Wiring |
| 01/04/2024 | Permit Issued | AL-Lectric Elect'l Contracting | General Wiring |
| 10/26/2022 | Complete | Warren Ostroff Electric | 1 meters |
| 08/01/2022 | Complete | Warren Ostroff Electric | General Wiring, HVAC Wiring |
| 07/29/2022 | Complete | Warren Ostroff Electric | — |
| 09/24/2021 | Permit Issued | Joseph Weinstein Electric | General Wiring |
| 03/20/2019 | Permit Issued | V. Vass Electric | — |
| 12/04/2018 | Permit Issued | Dennison Electric | General Wiring |
| 11/21/2018 | Complete | Demand Electric | — |
| 07/02/2018 | Permit Issued | Elite Electrical & Wiring | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2026 | Permit Issued | Ashlar Mechanical | Steel, Concrete |
| 06/02/2026 | Permit Issued | Niche Waterproofing | 1 scope_items |
| 08/29/2024 | Permit Issued | Rockefeller Plumbing & Heating I | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/23/2026 | Permit Issued | Andamio Scaffolding | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/17/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/14/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/31/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/05/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/29/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/25/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/04/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/02/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/27/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/27/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/07/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/07/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/01/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/24/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/21/2026 | HVAC-R and service water heating system controls | ELIAS RASABI | energy_progress |
| 09/21/2026 | HVAC-R and service water heating equipment | ELIAS RASABI | energy_progress |
| 09/21/2026 | Shutoff dampers | ELIAS RASABI | energy_progress |
| 09/21/2026 | HVAC-R and service water piping design and insulation | ELIAS RASABI | energy_progress |
| 09/21/2026 | Final | ELIAS RASABI | progress |
| 09/21/2026 | Mechanical Systems | ELIAS RASABI | special |
| 09/21/2026 | Heating Systems | ELIAS RASABI | special |
| 07/30/2026 | Concrete - Cast-In-Place | David Merabyan | special |
| 07/30/2026 | Structural Stability – Alterations of existing buildings | David Merabyan | special |
| 07/30/2026 | Post-installed Anchors | David Merabyan | special |
| 07/30/2026 | Final | David Merabyan | progress |
| 07/30/2026 | Mastic and Intumescent Fire-resistant Coatings | David Merabyan | special |
| 06/30/2026 | Structural Stability – Alterations of existing buildings | David Merabyan | special |
| 06/30/2026 | Final | David Merabyan | progress |
| 06/30/2026 | Concrete - Cast-In-Place | David Merabyan | special |
| 06/30/2026 | Mastic and Intumescent Fire-resistant Coatings | David Merabyan | special |
| 06/30/2026 | Post-installed Anchors | David Merabyan | special |
| 06/02/2026 | Masonry | David Merabyan | special |
| 05/08/2026 | Final | David Merabyan | progress |
| 05/08/2026 | Structural Stability – Alterations of existing buildings | David Merabyan | special |
| 05/08/2026 | Post-installed Anchors | David Merabyan | special |
| 03/06/2026 | Fire-Resistant Penetrations and Joints | LAWRENCE GREEN | special |
| 03/06/2026 | Energy Code Compliance Inspections | LAWRENCE GREEN | progress |
| 03/03/2026 | Duct leakage testing, insulation and design | LAWRENCE GREEN | energy_progress |
| 03/03/2026 | Fire-Resistant Penetrations and Joints | LAWRENCE GREEN | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| The Whale | Office | Floors 2, 4, 5 | Project B01065553 Project B01069490 Project B01041007 Project B01045624 |
| Vista Hermosa Products | Other | Floor 1, Roof | Project B00754545 |