| Firm | Filings | Most Recent |
|---|---|---|
| Stanley M. Krebushevski, R.A. | 1 | 12/05/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| K.M.D. Mechanical 1443 | specialty_contractor | 3 | 07/29/2026 |
| Bethel Building | General Contractor | 2 | 07/10/2026 |
| Bethel Building | Scaffold | 1 | 04/09/2026 |
| Quality Plumbing | Plumbing | 1 | 08/01/2026 |
| Bethel Building | specialty_contractor | 1 | 07/10/2026 |
| Husic | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P Design Consultant | 8472 | 4 | 05/13/2026 |
| SRA Planning & Expediting | 5677 | 3 | 05/05/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | K.M.D. Mechanical 1443 | 07/28/2026 |
| DOB NOW | Full Demolition | Signed-off | Husic | 03/24/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Permit Issued | Bethel Building | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Permit Issued | K.M.D. Mechanical 1443 | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Permit Issued | K.M.D. Mechanical 1443 | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Permit Issued | K.M.D. Mechanical 1443 | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/04/2025 | Permit Issued | Bethel Building | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2025 | Signed-off | Husic | Full Demolition Notification |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/13/2026 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 05/13/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 05/13/2026 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 05/13/2026 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 05/13/2026 | Ventilation and air distribution system | Stanislav Pilipenko | energy_progress |
| 02/25/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 10/08/2025 | Sprinkler Systems | Stanislav Pilipenko | special |
| 10/08/2025 | Mechanical Systems | Stanislav Pilipenko | special |
| 10/08/2025 | Final | Stanislav Pilipenko | progress |
| 07/11/2025 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 07/11/2025 | Air barrier — testing | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Fireplaces | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 07/11/2025 | Electric vehicle service equipment requirements | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Interior lighting power | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Metering | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 07/11/2025 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 07/11/2025 | Structural Steel - Welding | WILLIAM MONTAGUE | special |