1915Year Built
7Stories
O3Building Class
C6-4Zoning
71,732 sfGross Floor Area
6Units
LL97 Covered10 Open Violations 5 unresolved · 5 paperwork only ▸FISP: No Report FiledFDNY Report ↗
Office only, 7-19 stories · 19,417 sf lot · 3.69 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction20p · 2 filings · 6 docs
Floor 51p · 1 filing · 5 docs
Floor 4
Floor 3
Floor 2
Floor 1
Basement2p · 1 filing · 4 docs
Sub-Basement2p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DCAS2908/29/2026
CITY OF NEW YORK NYCDDC804/09/2026
CITY OF NEW YORK703/22/2026
DCAS 8 856303/22/2026
DCAS 856303/22/2026
LAKHI GENERAL CONTRACTING103/22/2026
OWNER OF 22 READE STREET103/22/2026
DEPT OF GENERAL SERVIC856203/22/2026
DEPT OF CITYWIDE ADMIN SERVICES303/21/2026
H P D NEW YORK CITY403/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AK CONSULTING SERVICES803/21/2026
CASO ASSOCIATES203/21/2026
SUPERSTRUCTURES ENG + ARCH103/21/2026
ARISTAR GROUP203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ADMINGeneral Contractor903/21/2026
J & N CONSTRUCTION GROUPGeneral Contractor807/08/2026
MFM CONTRACTING CORPGeneral Contractor404/09/2026
ADP GROUP INCGeneral Contractor408/26/2026
CLEAN TECH MECHANICAL INCPlumbing403/22/2026
SILKAIR CORPGeneral Contractor303/21/2026
HONEY CONSTRUCTION NY INCGeneral Contractor204/09/2026
CONSTRUCTION FORCE SVCSGeneral Contractor203/21/2026
GJOKO PETROVSKIElectrical103/21/2026
CONTRACT & HOSPITALITYGeneral Contractor106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ALAN MARGOLIN & ASSOC423102/18/2026
QUALITY CONTROL LABORATOR406105/02/2024
BITOPI CONSULTANTS LLC7036204/05/2024
MSA CONSULTING GROUP LLC7616108/08/2023
TWIN PEAKS INC.317105/22/2023
Building Lifecycle
All (115)Filed (13)Permit Issued (18)Signed Off (7)Violation (60)Inspection (1)Objection (6)Special Inspection (10)
07/14/2026
Permit issued — Sidewalk Shed
M01202061-I1-SH
05/06/2026
Permit issued — General Construction
M01353807-I1-GC
04/23/2026
Permit issued — Sidewalk Shed
M01202061-I1-SH
03/26/2026
Permit issued — Supported Scaffold
M01377721-I1-SF
03/25/2026
Filed — Alteration
INSTALLATION OF +/-112 FEET HIGH X +/- 16 FEET WIDE TEMPORARY SUPPORTED SCAFFOLDING & STAIR TOWER, AS PER PLANS, FOR EXTERIOR PARTIAL ROOF REPLACEMEN / REAPIR WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01377721-I1
03/25/2026
Filed — Alteration
INSTALLATION OF APPROXIMATELY +/- 286 LF OF TEMPORARY SIDEWALK SHED, AS PER PLANS, FOR PUBLIC PROTECTION. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M01202061-P1
03/10/2026
Signed off — Alteration
Cutting access holes in masonry walls to remove debris.
M00866582-I1
02/18/2026
Filed — Alteration
M01353807-I1
10/28/2025
Signed off — Alteration
Cutting access holes in masonry walls to remove debris.
M00866582-S1
07/17/2025
Violation issued (FDNY_ORDER, closed)
07/17/2025
Violation issued (FDNY_ORDER, closed)
07/17/2025
Violation issued (FDNY_ORDER, closed)
07/17/2025
Violation issued (FDNY_ORDER, closed)
05/07/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/23/2025
Filed — Alteration
INSTALLATION OF APPROXIMATELY +/- 286 LF OF TEMPORARY SIDEWALK SHED, AS PER PLANS, FOR PUBLIC PROTECTION. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M01202061-I1
04/23/2025
Permit issued — Sidewalk Shed
M01202061-I1-SH
09/23/2024
Signed off — Alteration
M01030404-I1
09/23/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 22 READE STREET, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01047015-I1
09/23/2024
Signed off — Alteration
M01030412-I1
09/04/2024
Signed off — Alteration
Upgrade cooling for Server Rooms on both the 2nd and 3rd Floors by means of a 36000 BTU/H VRF split system, with heat pump located on the roof.
M00880171-I1
08/29/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/07/2024
Permit issued — Structural
M00866582-S1-GC-CX
07/16/2024
Permit issued — Foundation
M00866582-S1-GC-CX
07/01/2024
Objection raised — Scope
07/01/2024
Objection resolved — Addressed
06/24/2024
Objection resolved — Addressed
05/14/2024
Objection raised — Scope
05/08/2024
Permit issued — Construction Fence
M01047015-I1-FN
05/07/2024
Filed — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 22 READE STREET, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01047015-I1
05/02/2024
Filed — Alteration
Cutting access holes in masonry walls to remove debris.
M00866582-S1
04/08/2024
Permit issued — Protection and Mechanical Methods
M01030412-I1-PMM
04/08/2024
Permit issued — Supported Scaffold
M01030419-I1-SF
04/08/2024
Permit issued — Supported Scaffold
M01030404-I1-SF
04/07/2024
Filed — Alteration
M01030412-I1
04/05/2024
Filed — Alteration
M01030404-I1
04/05/2024
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLD WITH MATERIAL HOIST AT 22 READE STREET, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01030419-I1
04/03/2024
Special inspection requirement — Post-installed Anchors
KAMRUL AHSAN
04/03/2024
Special inspection requirement — Post-installed Anchors
KAMRUL AHSAN
04/02/2024
Special inspection requirement — Footing and Foundation
SAMUEL BAUTISTA
04/02/2024
Special inspection requirement — Preliminary
SAMUEL BAUTISTA
04/02/2024
Special inspection requirement — Final
SAMUEL BAUTISTA
04/02/2024
Special inspection requirement — Concrete - Cast-In-Place
SAMUEL BAUTISTA
04/02/2024
Special inspection requirement — Masonry
SAMUEL BAUTISTA
04/02/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
SAMUEL BAUTISTA
03/01/2024
Permit issued — General Construction
M00866582-I1-GC
02/05/2024
Violation issued (FDNY_NOV, closed)
02/01/2024
Filed — Alteration
M00988763-I1
01/25/2024
Violation issued (FDNY_ORDER, closed)
09/07/2023
Signed off — Alteration
Lighting conversion to LED, power/data cabling for new and relocated furniture, painting, interior glass tinting, window shade installation, card access readers, interior door and k/d frame and hardware install/relocation.
M00715039-I1
08/22/2023
Violation issued (FDNY_NOV, closed)
08/09/2023
Permit issued — Mechanical Systems
M00880171-I1-MS
08/08/2023
Filed — Alteration
Upgrade cooling for Server Rooms on both the 2nd and 3rd Floors by means of a 36000 BTU/H VRF split system, with heat pump located on the roof.
M00880171-I1
07/03/2023
Permit issued — General Construction
M00866582-I1-GC
06/09/2023
Objection resolved — Addressed
06/08/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
MAXIM KORNGOLD
05/23/2023
Objection raised — Inspections
05/22/2023
Filed — Alteration
Cutting access holes in masonry walls to remove debris.
M00866582-I1
04/27/2023
Special inspection requirement — Final
Rohit Pradhan
04/05/2023
Violation issued (ECB, open)
Construction
12/02/2022
Violation issued (ECB, open)
Local Law
Latest 60 of 115 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedADP GROUP INC07/14/2026
DOB NOWGeneral ConstructionPermit IssuedCONTRACT & HOSPITALITY05/06/2026
DOB NOWSidewalk ShedPermit IssuedADP GROUP INC04/23/2026
DOB NOWSupported ScaffoldPermit IssuedADP GROUP INC03/26/2026
DOB NOWSidewalk ShedPermit IssuedADP GROUP INC04/23/2025
DOB NOWStructuralSigned-offMFM CONTRACTING CORP08/07/2024
DOB NOWFoundationSigned-offMFM CONTRACTING CORP07/16/2024
DOB NOWConstruction FenceSigned-offJ & N CONSTRUCTION GROUP05/08/2024
DOB NOWProtection and Mechanical MethodsSigned-offJ & N CONSTRUCTION GROUP04/08/2024
DOB NOWSupported ScaffoldPermit IssuedJ & N CONSTRUCTION GROUP04/08/2024
DOB NOWSupported ScaffoldSigned-offJ & N CONSTRUCTION GROUP04/08/2024
DOB NOWGeneral ConstructionSigned-offHONEY CONSTRUCTION NY INC03/01/2024
DOB NOWMechanical SystemsSigned-offSILKAIR CORP08/09/2023
DOB NOWGeneral ConstructionSigned-offHONEY CONSTRUCTION NY INC07/03/2023
DOB NOWGeneral ConstructionSigned-offCONSTRUCTION FORCE SVCS07/23/2022
DOB NOWSidewalk ShedSigned-offADMIN08/31/2019
DOB NOWSupported ScaffoldSigned-offADMIN08/31/2019
DOB NOWSupported ScaffoldSigned-offADMIN08/31/2019
BISEQISSUEDADP GROUP INC08/29/2024
BISEQISSUEDADP GROUP INC08/22/2023
BISEQISSUEDAAA WINDOWS & DOORS CORP11/04/2022
BISOTISSUEDFIVE STAR CONTRACTING COMPANIES05/17/2022
BISOTISSUEDFIVE STAR CONTRACTING COMPANIES11/08/2021
BISEQISSUEDAAA WINDOWS & DOORS CORP06/15/2020
BISEQISSUEDAAA WINDOWS & DOORS CORP06/26/2019
BISOTISSUEDCONTRACT & HOSPITALITY12/19/2018
BISEQISSUEDAAA WINDOWS & DOORS CORP06/27/2018
BISEQISSUEDAAA WINDOWS & DOORS CORP06/08/2017
BISEQISSUEDSAFWAY ATLANTIC, LLC08/24/2016
BISEQISSUEDSAFWAY ATLANTIC, LLC09/03/2015
BISEQISSUEDATLANTIC HOISTING & SCAFF09/22/2014
BISEQISSUEDTWIN & SWING SCAFFOLDING06/13/2013
BISEQISSUEDTWIN & SWING SCAFFOLDING02/05/2013
BISMHISSUEDAWL INDUSTRIES INC06/12/2012
BISMHISSUEDAWL INDUSTRIES INC06/11/2012
BISEQISSUEDTWIN & SWING SCAFFOLDING01/06/2012
BISOTISSUEDAWL INDUSTRIES INC06/20/2011
BISMHISSUEDAWL INDUSTRIES INC06/20/2011
BISMHISSUEDAWL INDUSTRIES INC06/20/2011
BISMHISSUEDAWL INDUSTRIES INC05/19/2011
+ 28 more permits on file
11 projects · most recent 03/24/2026
General Wiring HVAC Wiring Lighting
FiledStatusContractorScope
03/24/2026Permit IssuedHERTZ ELECTRIC LLC—
11/21/2024CompleteAM NY ELECTRIC CORPGeneral Wiring
03/18/2024CompleteOGC ELECTRICAL CONTRACTORHVAC Wiring
02/16/2024Permit IssuedROBERT CHIMENTI3 meters, 1 new_meters
04/06/2022CompleteP & M ELECT'L CONTR. CORPGeneral Wiring
03/09/2021CompleteE-J ELEC. INSTALLATION COGeneral Wiring
11/30/2020CompletePRECISION ELECL CONT CORPGeneral Wiring
09/21/2020CompleteSTAR ELEC'L CONTRACTORS C—
05/27/2020Permit IssuedP & M ELECT'L CONTR. CORPGeneral Wiring
03/27/2020Permit IssuedTESTFIRM2 & LLCLighting
02/11/2019Permit IssuedP & M ELECT'L CONTR. CORPGeneral Wiring
3 projects · most recent 03/25/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
03/25/2026Permit IssuedADP GROUP INCScaffold
03/25/2026Permit IssuedADP GROUP INCSidewalk Shed
04/05/2024Permit IssuedJ & N CONSTRUCTION GROUPScaffold
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
08/29/2024Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
04/03/2024Post-installed AnchorsKAMRUL AHSANspecial
04/03/2024Post-installed AnchorsKAMRUL AHSANspecial
04/02/2024Footing and FoundationSAMUEL BAUTISTAprogress
04/02/2024PreliminarySAMUEL BAUTISTAprogress
04/02/2024FinalSAMUEL BAUTISTAprogress
04/02/2024Concrete - Cast-In-PlaceSAMUEL BAUTISTAspecial
04/02/2024MasonrySAMUEL BAUTISTAspecial
04/02/2024Structural Stability – Alterations of existing buildingsSAMUEL BAUTISTAspecial
06/08/2023Structural Stability – Alterations of existing buildingsMAXIM KORNGOLDspecial
04/27/2023FinalRohit Pradhanprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Commission on Human RightsOfficeFloors 2, 3
Project M00880171 Alteration · LOC Issued · 08/08/2023
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 171 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
09/02/2026M00715039-I1Request digital key ↗
08/29/2026M00880171-I1Request digital key ↗
08/28/2026M00988763-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits39
▸BISWORK PERMIT APPLICATION22
08/29/2024140646406Open ↗
08/22/2023140646406Open ↗
11/04/2022140646406Open ↗
Showing 3 of 22 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION12
08/12/2021140997474Open ↗
04/15/2021140997474Open ↗
01/26/2021140997474Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWLPC Approval/Permit4
08/13/2026M00866582-S1Open ↗
08/13/2026M00988763-I1Open ↗
08/13/2026M00880171-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPARTIAL DEMO: 10-DAY NOTICE (FOR AL/EW-OT PERMITS)1
11/03/2021140997474Open ↗
▸Seals & Professional Certifications39
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/29/2026M00880171-I1Open ↗
08/28/2026M00988763-I1Open ↗
08/27/2026M01030404-I1Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
07/13/2017120942542Open ↗
05/07/2010120342218Open ↗
01/11/2010120205722Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/30/2026M00866582-S1Open ↗
08/30/2026M00866582-S1Open ↗
08/30/2026M00866582-S1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/30/2026M00866582-S1Open ↗
08/30/2026M00866582-S1Open ↗
08/30/2026M00866582-S1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
01/26/2021140997474Open ↗
06/07/2017140646406Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
01/27/2021140997474Open ↗
10/09/2018140809542Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
01/10/2012120942542Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
01/10/2012120942542Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/07/2017140646406Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/07/2017140646406Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
05/07/2010120342218Open ↗
▸Safety & Tenant Protection4
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM3
11/03/2021140997474Open ↗
10/24/2021140997474Open ↗
10/14/2021140997474Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
06/07/2017140646406Open ↗
▸Environmental & Asbestos8
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
05/07/2010120342218Open ↗
11/19/2009120205722Open ↗
11/23/2009120205713Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
01/27/2021140997474Open ↗
10/09/2018140809542Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/27/2026M00866582-I1Open ↗
08/13/2026M00715039-I1Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
10/24/2021140997474Open ↗
01/27/2021140997474Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
01/27/2021140997474Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026M00715039-I1Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY5
10/24/2021140997474Open ↗
05/18/2021140997474Open ↗
01/27/2021140997474Open ↗
Showing 3 of 5 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
10/24/2021140997474Open ↗
▸Approvals, Objections & Sign-offs32
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter12
08/28/2026M00988763-I1Open ↗
08/18/2026M01202061-I1Open ↗
08/18/2026M01202061-P1Open ↗
Showing 3 of 12 on file for this type
▸BISSHED LETTER5
08/29/2024140646406Open ↗
08/22/2023140646406Open ↗
11/04/2022140646406Open ↗
Showing 3 of 5 on file for this type
▸BISLANDMARKS APPROVAL3
05/03/2021140997474Open ↗
10/09/2018140809542Open ↗
06/07/2017140646406Open ↗
▸BISADMINISTRATIVE OBJECTIONS3
01/10/2012120942542Open ↗
05/07/2010120342218Open ↗
11/19/2009120205713Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)3
08/18/2026M01202061-P1Open ↗
08/13/2026M01377721-I1Open ↗
08/13/2026M01202061-I1Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
06/27/2018140646406Open ↗
06/20/2013120942542Open ↗
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
02/12/2013120942542Open ↗
▸BISSUPERSEDING LETTER1
08/26/2016120942542Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/13/2017120942542Open ↗
▸DOB NOWLandmark Approval1
08/13/2026M01353807-I1Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT5
01/27/2021140997474Open ↗
10/09/2018140809542Open ↗
05/07/2010120342218Open ↗
Showing 3 of 5 on file for this type
▸Filing & Intake Forms16
▸BISADDITIONAL INFORMATION9
08/26/2021140997474Open ↗
08/26/2021140997474Open ↗
08/13/2021140997474Open ↗
Showing 3 of 9 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
01/26/2021140997474Open ↗
10/09/2018140809542Open ↗
06/07/2017140646406Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET3
01/10/2012120942542Open ↗
11/19/2009120205722Open ↗
11/19/2009120205713Open ↗
▸Other Documents5
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
06/26/2019140646406Open ↗
05/07/2010120342218Open ↗
11/19/2009120205722Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll1
08/13/2026M01202061-I1Open ↗
▸DOB NOWProof of Historic Building1
08/13/2026M01353807-I1Open ↗