ECB02/15/2024FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8B AND 9B REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #911935. REMEDY: FILE ACCEPTABLE REPORT.$3K due
ECB03/24/2023FAILURE TO TAKE REQUIRED MEASURES TO SECURE PUBLIC SAFETY-UNSAFE FACADE.AS PER DOCUMENTED UNSAFE FACADE NOTIFICATION#UNSAFE-911935-9B-001 ON03-07-2023,THE BUILDING HAS UNSAFE CONDTIONS AS:CRACKED/SPALLING CONCR$25K due
ECB07/28/2023FAILURE TO OBEY A VACATE ORDER FROM THE COMMISSIONER PER 28-207.4 NOTE: RESPONDENT FAILURE TO COMPLY WITH COMMISSIONER'S VACATE ORDER #S37/2023 DATED 07/11/2023, WHICH REQUIRES THE ENTIRE BACKYARD ON EXPOSURE #Nothing owed — awaiting certificate of correction
ECB12/09/2022FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 8B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#811935.AGG1 PRIOR NOV#37021784K UNDER 2Nothing owed — awaiting certificate of correction
ECB08/02/2021FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE 8B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #811935.REMEDY:SUBMIT ACCEPTABLE REQUIREDNothing owed — awaiting certificate of correction
ECB09/11/2018FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE AND APPURTENANCES. AS NOTED: 2ND FL WALKWAY HAS SPALLING CONCRETE IN SEVERAL LOCATIONS WITH EXPOSED REBAR & SPALLING CONCRETE ON FACADE IN CORNERS. REAR OF WEST WINGNothing owed — awaiting certificate of correction
ECB05/02/2017PSWO SUSPENDED SCAFFOLD. FAILED TO NOTIFY DEPT PRIOR TO INSTALLATION OF SUSPENDED SCAFFOLD. NOTE: AT TIME OF INSPECTION OUTRIGGER BEAMS INSTALLED W/I CONJUNCTION W/SUSPENDED SCAFFOLD. REMEDY: COMPLY W/CODE. DONothing owed — awaiting certificate of correction