← Back
Two family frame
141-11 185 STREET
💬 Discuss this project
1945Year Built
1.67Stories
B2Building Class
R3AZoning
1,837 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 3,768 sf lot · 0.49 FAR built · Flood zone X
Locations of Work
Electrical
Roof3p · 1 filing · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC201/21/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036201/21/2026
Building Lifecycle
All (13)Filed (2)Permit Issued (1)Signed Off (1)Violation (1)Special Inspection (8)
04/20/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01173846-I1
04/17/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
04/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
04/17/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
04/17/2026
Special inspection requirement — Final
Ayracon Almaraz
01/21/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01173846-P1
01/21/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
01/21/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
01/21/2026
Special inspection requirement — Final
Ayracon Almaraz
01/21/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
12/02/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/07/2025
Permit issued — Solar
Q01173846-I1-SL
02/04/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01173846-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC02/07/2025
1 project · most recent 04/24/2025
FiledStatusContractorScope
04/24/2025CompleteREDLINE ELECTRIC INC—
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
04/17/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
04/17/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
04/17/2026Energy Code Compliance InspectionsAyracon Almarazprogress
04/17/2026FinalAyracon Almarazprogress
01/21/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
01/21/2026Energy Code Compliance InspectionsAyracon Almarazprogress
01/21/2026FinalAyracon Almarazprogress
01/21/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q01173846-P1Request digital key ↗
08/17/2026Q01173846-I1Request digital key ↗
▸Seals & Professional Certifications10
▸DOB NOWProgress Inspector Seal & Signature6
08/26/2026Q01173846-I1Open ↗
08/26/2026Q01173846-I1Open ↗
08/26/2026Q01173846-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q01173846-I1Open ↗
08/13/2026Q01173846-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026Q01173846-I1Open ↗
08/26/2026Q01173846-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q01173846-I1Open ↗
08/13/2026Q01173846-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026Q01173846-I1Open ↗