| Owner | Filings | Most Recent |
|---|---|---|
| A PETER LUGER CONSTRUCTION | 10 | 07/08/2026 |
| HEERA G BUILDERS | 9 | 07/08/2026 |
| HERRA & G BUILDERS INC | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/15/2018 | $605K | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| GERALD CALIENDO ARCHITECTS | 5 | 03/17/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GERALD J. CALIENDO | Electrical | 3 | 03/21/2026 |
| HEERA & G BUILDERS INC | General Contractor | 3 | 07/08/2026 |
| KISHAN PLUMBING INC | Plumbing | 3 | 03/22/2026 |
| A PETER LUGER CONSTRUC IN | General Contractor | 2 | 03/21/2026 |
| BT'S PLUMBING AND HEATING | Plumbing | 2 | 07/08/2026 |
| GERALD J CALIENDO R A P C | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ABDUS SALAM C. ENGINEERS | 484 | 3 | 03/17/2023 |
| TRIANGLE INSPECTION & TES | 7495 | 2 | 03/17/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Permit Issued | A PETER LUGER CONSTRUC IN | 11/09/2022 |
| DOB NOW | Plumbing | Signed-off | BT'S PLUMBING AND HEATING | 03/23/2022 |
| DOB NOW | Construction Fence | Signed-off | HEERA & G BUILDERS INC | 11/09/2021 |
| DOB NOW | Plumbing | Signed-off | BT'S PLUMBING AND HEATING | 07/02/2021 |
| BIS | — | ISSUED | HEERA & G BUILDERS INC | 02/23/2021 |
| BIS | — | ISSUED | HEERA & G BUILDERS INC | 12/01/2020 |
| BIS | — | ISSUED | HEERA & G BUILDERS INC | 12/01/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2022 | Complete | AUJLA ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/01/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 01/22/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 01/19/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/19/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/17/2022 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 11/16/2022 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 10/12/2022 | Pass-Final Fence Non-Directive 14 | Pass | View ↗ |
| 11/19/2021 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 11/19/2021 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/08/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/08/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/23/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/21/2023 | Maintenance information | Rizwan Salam | energy_progress |
| 03/21/2023 | Energy Code Compliance Inspections | IDRIS SALAM | progress |
| 03/21/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 03/21/2023 | Fire-Resistant Penetrations and Joints | IDRIS SALAM | special |
| 03/14/2023 | Fire-Resistant Penetrations and Joints | IDRIS SALAM | special |
| 03/14/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 03/14/2023 | Energy Code Compliance Inspections | IDRIS SALAM | progress |
| 03/14/2023 | Maintenance information | Rizwan Salam | energy_progress |
| 01/05/2023 | Maintenance information | Rizwan Salam | energy_progress |
| 01/05/2023 | Energy Code Compliance Inspections | IDRIS SALAM | progress |
| 01/05/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | — | special |
| 01/05/2023 | Fire-Resistant Penetrations and Joints | IDRIS SALAM | special |