| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/04/2026 | Permit Issued | DAJ EMR LLC | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | Permit Issued | DAJ EMR LLC | Fence |
| Firm | Filings | Most Recent |
|---|---|---|
| AG ENGINEERING PLLC | 5 | 05/04/2026 |
| ADNAN ENGINEERING, P.C. | 3 | 04/27/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DAJ EMR LLC | General Contractor | 2 | 09/19/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 7 | 05/04/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | DAJ EMR LLC | 09/18/2026 |
| DOB NOW | Structural | Permit Issued | DAJ EMR LLC | 09/18/2026 |
| DOB NOW | Earth Work | Permit Issued | M&A PROJECTS RESTORATION* | 08/25/2026 |
| DOB NOW | Support of Excavation | Permit Issued | D'APRILE INC | 08/19/2026 |
| DOB NOW | Construction Fence | Permit Issued | DAJ EMR LLC | 10/03/2025 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/29/2026 | HVAC-R and service water piping design and insulation | SHAHRIAR QUAYYUM | energy_progress |
| 04/29/2026 | HVAC-R and service water heating equipment | SHAHRIAR QUAYYUM | energy_progress |
| 04/29/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SHAHRIAR QUAYYUM | special |
| 04/29/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 04/29/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 04/29/2026 | HVAC-R and service water heating system controls | SHAHRIAR QUAYYUM | energy_progress |
| 04/28/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 04/28/2026 | Post-installed Anchors | SHAHRIAR QUAYYUM | special |
| 04/27/2026 | Post-installed Anchors | SHAHRIAR QUAYYUM | special |
| 04/27/2026 | Structural Cold-Formed Steel | SHAHRIAR QUAYYUM | special |
| 04/27/2026 | Structural Steel - Welding | SHAHRIAR QUAYYUM | special |
| 04/27/2026 | Structural Steel - Details | SHAHRIAR QUAYYUM | special |
| 04/27/2026 | Subgrade Inspections | SHAHRIAR QUAYYUM | special |
| 04/27/2026 | Concrete - Cast-In-Place | SHAHRIAR QUAYYUM | special |
| 03/11/2026 | HVAC-R and service water heating system controls | SHAHRIAR QUAYYUM | energy_progress |
| 03/11/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 03/11/2026 | Post-installed Anchors | SHAHRIAR QUAYYUM | special |
| 03/11/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 03/11/2026 | HVAC-R and service water heating equipment | SHAHRIAR QUAYYUM | energy_progress |
| 03/11/2026 | Duct leakage testing, insulation and design | SHAHRIAR QUAYYUM | energy_progress |
| 03/11/2026 | HVAC-R and service water piping design and insulation | SHAHRIAR QUAYYUM | energy_progress |
| 03/11/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 03/11/2026 | Shutoff dampers | SHAHRIAR QUAYYUM | energy_progress |
| 03/11/2026 | Sprinkler Systems | SHAHRIAR QUAYYUM | special |
| 03/10/2026 | Final | SHAHRIAR QUAYYUM | progress |