| Owner | Filings | Most Recent |
|---|---|---|
| GARBO COMPANY | 26 | 04/09/2026 |
| J G CONSTRUCTION SRVCS | 9 | 04/09/2026 |
| EVANGELICAL CHURCH GOD | 4 | 03/22/2026 |
| OWNER OF 141 MESEROLE ST | 2 | 03/22/2026 |
| 7 RESIDENCE | 4 | 03/21/2026 |
| S4 LOFTS | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/17/2022 | $1.2M | — | Private party → MESEROLE LODGE LLC | $300/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| 360 ENGINEERING P.C. | 6 | 03/13/2025 |
| ASHRAF CORP | 3 | 08/09/2024 |
| R & O ENGINEERING | 3 | 04/08/2024 |
| ARYEH SIEGEL ARCHITECT | 1 | 03/12/2024 |
| CHOSEN MEP, CORP. | 3 | 11/28/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMG GROUP USA | 9 | 03/21/2026 |
| ELLIPSES DESIGN | 3 | 03/21/2026 |
| EZFILINGNYCORP | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ADOR BUILDERS LLC | General Contractor | 7 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 2 | 04/09/2026 |
| PLUMB-IT MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| POWER SURGE ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| DOUG'S PLBG & HTG SERV CO | Fire Protection | 1 | 07/08/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHAHRISH SHUVO ENGINEERIN | 8524 | 5 | 03/13/2025 |
| HRF SERVICES CORP | 5616 | 3 | 10/10/2024 |
| CENTURY TESTING & CONSULT | 4081 | 3 | 01/18/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | JVR PLBG AND HEATING INC | 01/17/2025 |
| DOB NOW | Sprinklers | Signed-off | DOUG'S PLBG & HTG SERV CO | 12/19/2024 |
| DOB NOW | Plumbing | Signed-off | ALL PRO PLBG & HTG INC | 11/21/2024 |
| DOB NOW | Mechanical Systems | Signed-off | ADOR BUILDERS LLC | 11/14/2024 |
| DOB NOW | Plumbing | Signed-off | JVR PLBG AND HEATING INC | 08/02/2024 |
| DOB NOW | Supported Scaffold | Signed-off | J & G CONSTRUCTION SVCS | 07/30/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | J & G CONSTRUCTION SVCS | 07/30/2024 |
| DOB NOW | Earth Work | Signed-off | ADOR BUILDERS LLC | 07/02/2024 |
| DOB NOW | Structural | Signed-off | ADOR BUILDERS LLC | 06/11/2024 |
| DOB NOW | General Construction | Permit Issued | ADOR BUILDERS LLC | 06/10/2024 |
| DOB NOW | Construction Fence | Signed-off | ADOR BUILDERS LLC | 03/27/2024 |
| DOB NOW | Structural | Signed-off | ADOR BUILDERS LLC | 03/26/2024 |
| DOB NOW | General Construction | Permit Issued | ADOR BUILDERS LLC | 03/26/2024 |
| BIS | EQ | ISSUED | HARRIS HOME REPAIR & DEVE | 10/19/2016 |
| BIS | EQ | ISSUED | JZ DEVELOPERS INC | 09/15/2016 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/13/2025 | Signed-off | ADOR BUILDERS LLC | Air Conditioning Systems, Heating Systems | Cooling Daikin DAIKIN -RXTQ36TBVJUA 34,200 BTU · Vrf Outdoor ×8 DAIKIN - RXTQ48TBVJUA 45,500 BTU · Vrf Outdoor ×1 DAIKIN -RXTQ60TBVJUA 57,000 BTU · Vrf Outdoor ×1 Heating Daikin RXSQ24TAVJU 25,800 BTU · Vrf Outdoor ×7 DAIKIN - RXTQ48TBVJUA 52,500 BTU · Vrf Outdoor ×1 DAIKIN -RXTQ36TBVJUA 37,000 BTU · Vrf Outdoor ×1 DAIKIN -RXTQ60TBVJUA 57,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2025 | Signed-off | PLUMB-IT MECHANICAL INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2025 | Complete | FRIED ELECTRIC CO. | General Wiring |
| 03/03/2025 | Complete | POWER SURGE ELECTRIC, INC | General Wiring |
| 02/22/2025 | Complete | POWER SURGE ELECTRIC, INC | — |
| 01/20/2025 | Complete | POWER SURGE ELECTRIC, INC | General Wiring |
| 07/25/2024 | Complete | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2025 | Signed-off | PLUMB-IT MECHANICAL INC | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/05/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/03/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 02/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/24/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/08/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/30/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/17/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/04/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 10/11/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/11/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/14/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/14/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/24/2025 | Lighting controls | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Air barrier - visual inspection | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Fenestration areas | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Metering | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Chimneys and vents | Shahrish Shuvo | special |
| 03/24/2025 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 03/24/2025 | Structural Stability – Alterations of existing buildings | Shahrish Shuvo | special |
| 03/24/2025 | Fire-Resistance Rated Construction | Shahrish Shuvo | progress |
| 03/24/2025 | Energy Code Compliance Inspections | Shahrish Shuvo | progress |
| 03/24/2025 | Maintenance information | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Exterior lighting power | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Protection of exposed foundation insulation | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Fenestration and door U-factor and product ratings | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Insulation placement and R values | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Lighting in dwelling units | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Fenestration air leakage | Shahrish Shuvo | energy_progress |
| 03/24/2025 | Interior lighting power | Shahrish Shuvo | energy_progress |
| 01/29/2025 | Protection of exposed foundation insulation | Shahrish Shuvo | energy_progress |
| 01/29/2025 | Chimneys and vents | Shahrish Shuvo | special |
| 01/29/2025 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 01/29/2025 | Structural Stability – Alterations of existing buildings | Shahrish Shuvo | special |
| 01/29/2025 | Energy Code Compliance Inspections | Shahrish Shuvo | progress |
| 01/29/2025 | Fire-Resistance Rated Construction | Shahrish Shuvo | progress |
| 01/29/2025 | Exterior lighting power | Shahrish Shuvo | energy_progress |
| 01/29/2025 | Lighting in dwelling units | Shahrish Shuvo | energy_progress |