← Back
Hospital, sanitarium, mental institution
Rose F. Kennedy Center
1410 PELHAM PARKWAY SOUTH · Morris Park · BIN 2097552
💬 Discuss this project
1965Year Built
9Stories
I1Building Class
R4Zoning
—Gross Floor Area
0Units
110 Open Violations 107 unresolved · 3 paperwork only ▸FISP: SAFE
Hospital, sanitarium, mental institution · Owner of record: ALBERT EINSTEIN COLLEGE OF MEDICINE · 2.82 FAR built · Flood zone X
Locations of Work
ArchitectureMechanical
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 2 docs
Sub-Basement8p · 2 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DEPT OF GEN SERVICES203/21/2026
VERSAI LLC109/12/2026
BILLY CONTRACTORS103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GOLDMAN COPELAND ASSOCIATES103/24/2022
ALBERT EINSTEIN COLLEGE OF MEDICINE103/14/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CAESAR BUSTAMANTE AIA403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JOHN AHRENSElectrical303/21/2026
TRANSEL ELEV. & ELEC. INCElectrical203/22/2026
CANNON MECHANICAL INCGeneral Contractor207/08/2026
VILLAFANE JOHNElectrical103/21/2026
WAYNE HAMILTONElectrical103/21/2026
WILLIAM KLEINElectrical103/21/2026
FIRST WORLD DEVELOPMENTGeneral Contractor107/08/2026
JOHN VILLAFANEElectrical103/21/2026
KLEIN WILLIAMElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GOLDMAN COPELAND ASSOCIAT2826103/24/2022
Building Lifecycle
All (91)Filed (3)Permit Issued (4)Signed Off (2)Facade (FISP) (13)Violation (60)Special Inspection (9)
09/10/2026
Permit issued — Suspended Scaffold
X01447734-I1-SC
08/19/2026
Filed — Alteration
IRA FISP INSPECTION
X01447734-I1
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Unknown
09/19/2022
Signed off — Alteration
X00695512-I1
05/31/2022
Permit issued — Mechanical Systems
X00695512-I1-MS
05/20/2022
Signed off — Alteration
Interior removals on part of the basement as indicated on the attached plans. There is no change in use, egress or occupancy.
X00695451-I1
04/11/2022
Permit issued — Mechanical Systems
X00695512-I1-MS
03/24/2022
Filed — Alteration
X00695512-I1
03/17/2022
Special inspection requirement — Maintenance information
DANIEL COLOMBINI
03/17/2022
Special inspection requirement — HVAC-R and service water heating equipment
DANIEL COLOMBINI
03/17/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
DANIEL COLOMBINI
03/17/2022
Special inspection requirement — Electrical motors and elevators
DANIEL COLOMBINI
03/17/2022
Special inspection requirement — Energy Code Compliance Inspections
DANIEL COLOMBINI
03/17/2022
Special inspection requirement — HVAC-R and service water heating system controls
DANIEL COLOMBINI
03/16/2022
Permit issued — General Construction
X00695451-I1-GC
03/14/2022
Filed — Alteration
Interior removals on part of the basement as indicated on the attached plans. There is no change in use, egress or occupancy.
X00695451-I1
03/10/2022
Special inspection requirement — Mechanical Systems
DANIEL COLOMBINI
03/10/2022
Special inspection requirement — Final
DANIEL COLOMBINI
03/10/2022
Special inspection requirement — Final
VINCENT MARQUARDT
01/28/2021
Cycle 9 facade report submitted
01/26/2021
Cycle 9 facade report signed — SAFE
01/07/2021
Cycle 9 facade inspection completed
12/01/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/18/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/18/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/18/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/05/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/05/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/05/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
01/23/2017
Cycle 8 facade report submitted
01/03/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/03/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/30/2016
Cycle 8 facade report signed — SAFE
12/01/2016
Cycle 8 facade inspection completed
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/14/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/14/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Latest 60 of 91 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSUPERSTARS CONTRACTING IN09/10/2026
DOB NOWMechanical SystemsSigned-offCANNON MECHANICAL INC05/31/2022
DOB NOWMechanical SystemsSigned-offCANNON MECHANICAL INC04/11/2022
DOB NOWGeneral ConstructionSigned-offFIRST WORLD DEVELOPMENT03/16/2022
BIS—ISSUEDALBERT EINSTEIN COLLEGE OF MED.01/06/2020
BISOTISSUEDPINNACLE ENVIRONMENTAL CO12/05/2017
BISOTISSUEDHERBERT ROSE INC10/04/2016
BISMHISSUEDCANNON MECHANICAL INC06/07/2016
BISMHISSUEDCANNON MECHANICAL INC06/07/2016
BISOTISSUEDCANNON MECHANICAL INC06/07/2016
BISMHISSUED2260 MAG CORP04/22/2016
BISPLISSUEDACCURATE MECHANICAL INC03/16/2016
BISMHISSUEDCANNON MECHANICAL INC03/15/2016
BISOTISSUEDCANNON MECHANICAL INC03/10/2016
BISOTISSUEDALLIED CONTRACTING II COR05/29/2012
BISOTISSUEDDURR MECHANICAL CONSTRUCTION INC01/08/2008
BISOTISSUEDHERBERT ROSE INC05/08/2007
BISEQISSUEDHERBERT ROSE INC05/02/2007
BISOTISSUEDHERBERT ROSE INC03/28/2007
BISEQISSUEDHERBERT ROSE INC02/26/2007
BISSPISSUEDFRED J. DRIEHM, INC04/20/2004
BISPLISSUEDFRED J. RIEHM INC02/04/2004
BISPLISSUEDPERFECT PLUMBING & HEATING CORP09/30/2003
BISOTISSUEDPHONEIX BUILDING CORPORATION09/17/2003
BISPLISSUEDGEORGE WENK PLUMBING10/01/1992
6 projects · most recent 08/05/2026
General Wiring
FiledStatusContractorScope
08/05/2026Permit IssuedLIPPOLIS ELECTRIC, INC.General Wiring
06/26/2025CompleteTRANSEL ELEV. & ELEC. INCGeneral Wiring
04/12/2022CompleteRNW ELECTRIC CORPGeneral Wiring
10/04/2019CompleteLIPPOLIS ELECTRIC, INC.General Wiring
06/23/2019CompleteTUXEDO ELEC'L CONTR'G INC—
01/30/2019CancelledAPPROVED ELEC CONT'G INCGeneral Wiring
1 project · most recent 08/19/2026
FiledStatusContractorScope
08/19/2026Permit IssuedSUPERSTARS CONTRACTING IN—
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
03/17/2022Maintenance informationDANIEL COLOMBINIenergy_progress
03/17/2022HVAC-R and service water heating equipmentDANIEL COLOMBINIenergy_progress
03/17/2022HVAC-R and service water piping design and insulationDANIEL COLOMBINIenergy_progress
03/17/2022Electrical motors and elevatorsDANIEL COLOMBINIenergy_progress
03/17/2022Energy Code Compliance InspectionsDANIEL COLOMBINIprogress
03/17/2022HVAC-R and service water heating system controlsDANIEL COLOMBINIenergy_progress
03/10/2022Mechanical SystemsDANIEL COLOMBINIspecial
03/10/2022FinalDANIEL COLOMBINIprogress
03/10/2022FinalVINCENT MARQUARDTprogress
▾Documents — 186 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/24/2026X00695451-I1Request digital key ↗
08/24/2026X00695512-I1Request digital key ↗
08/20/2026X01447734-I1Request digital key ↗
▸Applications & Permits31
▸BISPLAN / WORK APPROVAL APPLICATION17
11/15/2021220660407Open ↗
11/12/2019220660407Open ↗
12/24/2018220660407Open ↗
Showing 3 of 17 on file for this type
▸BISWORK PERMIT APPLICATION11
01/06/2020220660407Open ↗
12/05/2017240201820Open ↗
10/04/2016220541242Open ↗
Showing 3 of 11 on file for this type
▸BISPLACE OF ASSEMBLY2
11/04/2020220654085Open ↗
06/13/2018220654085Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
03/09/2020220660407Open ↗
▸Seals & Professional Certifications45
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION22
12/24/2018220660407Open ↗
06/13/2018220654085Open ↗
01/10/2018240201820Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/01/2026X00695512-I1Open ↗
09/01/2026X00695512-I1Open ↗
09/01/2026X00695512-I1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
10/11/2017240201820Open ↗
04/22/2016220528169Open ↗
03/15/2016220520817Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
04/22/2016220528169Open ↗
03/15/2016220520817Open ↗
12/19/2007210028129Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
10/11/2017240201820Open ↗
03/09/2016240134911Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
10/11/2017240201820Open ↗
03/09/2016240134911Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/24/2026X00695451-I1Open ↗
08/24/2026X00695512-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
12/19/2007210028129Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026X00695512-I1Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
05/05/2016240134911Open ↗
04/20/2016240134911Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
09/11/2017220525590Open ↗
▸BISSCHEDULE B - PLUMBING1
03/09/2016240134911Open ↗
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST2
12/24/2018220660407Open ↗
03/09/2016240134911Open ↗
▸BISTenant Protection Plan and Notes1
07/13/2016220541242Open ↗
▸BISSTREET TREE SIGNOFF1
05/09/2025220660407Open ↗
▸Environmental & Asbestos11
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
07/13/2016220541242Open ↗
04/22/2016220528169Open ↗
04/08/2016220525590Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)3
01/10/2018240201820Open ↗
01/10/2018240201820Open ↗
10/11/2017240201820Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/24/2026X00695451-I1Open ↗
08/24/2026X00695512-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
12/19/2007210028129Open ↗
▸Energy Compliance19
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS11
12/24/2018220660407Open ↗
04/21/2017220528169Open ↗
03/21/2017220528169Open ↗
Showing 3 of 11 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
01/10/2018240201820Open ↗
03/21/2017220528169Open ↗
01/05/2017220541242Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
10/11/2017240201820Open ↗
03/09/2016240134911Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026X00695512-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
10/11/2017240201820Open ↗
03/09/2016240134911Open ↗
▸Approvals, Objections & Sign-offs29
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST19
01/10/2018240201820Open ↗
10/20/2017220525590Open ↗
09/15/2017220525590Open ↗
Showing 3 of 19 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
06/13/2018220654085Open ↗
04/08/2016220525590Open ↗
06/07/2012220149649Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE3
11/15/2021220660407Open ↗
11/12/2019220660407Open ↗
12/24/2018220660407Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
11/14/2011220149649Open ↗
12/19/2007210028129Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
08/13/2026X00695451-I1Open ↗
08/13/2026X00695512-I1Open ↗
▸Cost, Insurance & Ownership18
▸BISCOST AFFIDAVIT18
12/24/2018220660407Open ↗
01/10/2018240201820Open ↗
10/20/2017220525590Open ↗
Showing 3 of 18 on file for this type
▸Filing & Intake Forms17
▸BISEFILING COVER SHEET6
12/24/2018220660407Open ↗
07/13/2016220541242Open ↗
04/22/2016220528169Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION5
01/06/2020220660407Open ↗
08/12/2016220520817Open ↗
05/05/2016240134911Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM4
03/09/2020220660407Open ↗
01/10/2018240201820Open ↗
10/20/2017220525590Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
10/11/2017240201820Open ↗
03/09/2016240134911Open ↗
▸Other Documents3
▸BISPLOT DIAGRAM2
01/06/2020220660407Open ↗
12/24/2018220660407Open ↗
▸DOB NOWIRA Certification1
08/20/2026X01447734-I1Open ↗