1920Year Built
2Stories
B1Building Class
R5Zoning
—Gross Floor Area
2Units
0 Open Violations
Two family brick · Owner of record: PELHAM BUILDERS LLC · 1.11 FAR built · Flood zone X
Locations of Work
StructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
Floor 2Under Construction5p · 1 filing · 20 docs
Floor 1Under Construction6p · 1 filing · 20 docs
BasementUnder Construction7p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
UNITED 24411304/09/2026
PELHAM BUILDERS303/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SIDERIS KEFALAS ENGINEERS PC108/21/2025
GERALD CALIENDO ARCHITECTS307/07/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J CALIENDO ARCHITECT P C603/21/2026
Mdl consulting services103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
IVAN ROSA LLCGeneral Contractor307/08/2026
GO PRO FIRE PROTECTION CFire Protection107/08/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616308/21/2025
Building Lifecycle
All (73)Filed (5)Permit Issued (5)Signed Off (1)Violation (5)Inspection (9)Objection (18)Special Inspection (30)
05/19/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
04/30/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/06/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
03/23/2026
Violation issued (ECB, closed)
Construction
03/20/2026
Permit issued — Sprinklers
X01183527-S2-EW-SP
12/19/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
12/09/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
12/09/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
12/09/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/09/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/26/2025
Permit issued — Plumbing
X01183527-S1-PL
11/12/2025
Permit issued — Foundation
X01183527-I1-GC-CX
10/15/2025
Permit issued — Mechanical Systems
X01183527-I1-GC-CX
10/06/2025
Signed off — Full Demolition
Hand demolition of 2 story detached house .See attached survey
X01132172-I1
08/25/2025
Permit issued — Full Demolition
X01132172-I1-FD
08/21/2025
Filed — New Building
INSTALLATION OF SPRINKLER SYSTEM THROUGH-OUT NEW BUILDING, FILED IN CONJUCTION WITH NB #X01183527-I1.
X01183527-S2
08/11/2025
Special inspection requirement — HVAC-R and service water heating system controls
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Metering
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Duct leakage testing, insulation and design
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Ventilation and air distribution system
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Structural Steel - Details
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Concrete - Cast-In-Place
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Heating Systems
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Subgrade Inspections
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Mechanical Systems
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Footing and Foundation
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Lighting controls
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Permanent certificate
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Air barrier — testing
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
08/11/2025
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
07/24/2025
Special inspection requirement — Sprinkler Systems
SHAHRIAR QUAYYUM
07/14/2025
Objection resolved — Addressed
07/10/2025
Objection raised — Other
07/07/2025
Filed — New Building
INSTALLATION OF SPRINKLER SYSTEM THROUGH-OUT NEW BUILDING, FILED IN CONJUCTION WITH NB #X01183527-I1.
X01183527-P1
06/16/2025
Objection resolved — Addressed
05/14/2025
Objection resolved — Addressed
04/30/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
04/30/2025
Special inspection requirement — Permanent certificate
SHAHRIAR QUAYYUM
04/30/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SHAHRIAR QUAYYUM
04/23/2025
Objection resolved — Addressed
04/10/2025
Objection resolved — Addressed
04/10/2025
Objection resolved — Addressed
04/10/2025
Objection resolved — Addressed
04/10/2025
Objection resolved — Addressed
04/03/2025
Objection resolved — Addressed
03/13/2025
Objection raised — Admin
03/10/2025
Objection raised — Plumbing
Latest 60 of 73 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedGO PRO FIRE PROTECTION C03/20/2026
DOB NOWPlumbingPermit IssuedINFINITI ESC PLUMBING COR11/26/2025
DOB NOWFoundationPermit IssuedIVAN ROSA LLC11/12/2025
DOB NOWMechanical SystemsPermit IssuedIVAN ROSA LLC10/15/2025
DOB NOWFull DemolitionSigned-offIVAN ROSA LLC08/25/2025
BISPLISSUEDMEJ PLUMBING LLC11/12/1998
BIS—ISSUEDNONE01/23/1998
1 project · most recent 08/21/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/21/2025Permit IssuedIVAN ROSA LLCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Lg LMU480HV 48,000 BTU · Vrf Outdoor ×6
Ventilation
Continental Fan ECO-FLO plus 35 CFM · Erv ×24
1 project · most recent 08/21/2025
Sprinkler System
FiledStatusContractorScope
08/21/2025Permit IssuedGO PRO FIRE PROTECTION CSprinkler System
1 project · most recent 08/21/2025
Storm Water/Sanitary
FiledStatusContractorScope
08/21/2025Permit IssuedINFINITI ESC PLUMBING CORStorm, Water/Sanitary
1 project · most recent 12/11/2025
General Wiring
FiledStatusContractorScope
12/11/2025Permit IssuedRONEY ELECTRIC INCGeneral Wiring
1 project · most recent 08/21/2025
Steel
FiledStatusContractorScope
08/21/2025Permit IssuedGO PRO FIRE PROTECTION CSteel
1 project · most recent 08/21/2025
Earthwork
FiledStatusContractorScope
08/21/2025Permit IssuedGO PRO FIRE PROTECTION CEarthwork
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
05/19/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
04/30/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/24/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/06/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
12/19/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
12/09/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
12/09/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/09/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/09/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 33
DateRequirementInspectorRole
08/11/2025HVAC-R and service water heating system controlsSHAHRIAR QUAYYUMenergy_progress
08/11/2025HVAC-R and service water piping design and insulationSHAHRIAR QUAYYUMenergy_progress
08/11/2025MeteringSHAHRIAR QUAYYUMenergy_progress
08/11/2025Duct leakage testing, insulation and designSHAHRIAR QUAYYUMenergy_progress
08/11/2025Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
08/11/2025Ventilation and air distribution systemSHAHRIAR QUAYYUMenergy_progress
08/11/2025Structural Steel - DetailsSHAHRIAR QUAYYUMspecial
08/11/2025Concrete - Cast-In-PlaceSHAHRIAR QUAYYUMspecial
08/11/2025Heating SystemsSHAHRIAR QUAYYUMspecial
08/11/2025Subgrade InspectionsSHAHRIAR QUAYYUMspecial
08/11/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
08/11/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationSHAHRIAR QUAYYUMspecial
08/11/2025Mechanical SystemsSHAHRIAR QUAYYUMspecial
08/11/2025Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
08/11/2025Footing and FoundationSHAHRIAR QUAYYUMprogress
08/11/2025FinalSHAHRIAR QUAYYUMprogress
08/11/2025HVAC-R and service water heating equipmentSHAHRIAR QUAYYUMenergy_progress
08/11/2025Lighting controlsSHAHRIAR QUAYYUMenergy_progress
08/11/2025Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
08/11/2025Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
08/11/2025Fenestration areasSHAHRIAR QUAYYUMenergy_progress
08/11/2025Maintenance informationSHAHRIAR QUAYYUMenergy_progress
08/11/2025Permanent certificateSHAHRIAR QUAYYUMenergy_progress
08/11/2025Air barrier — testing SHAHRIAR QUAYYUMenergy_progress
08/11/2025Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
Latest 25 of 33.
▾Documents — 56 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/20/2026X01132172-I1Request digital key ↗
08/20/2026X01183527-S1Request digital key ↗
08/20/2026X01183527-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
03/21/2025240361880Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
03/21/2025240361880Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026X01183527-P1Open ↗
08/13/2026X01183527-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026X01183527-P1Open ↗
08/13/2026X01183527-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026X01183527-I1Open ↗
08/13/2026X01183527-P1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/20/2026X01183527-S1Open ↗
08/20/2026X01183527-I1Open ↗
08/20/2026X01183527-S2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/23/2026X01183527-S2Open ↗
08/23/2026X01183527-I1Open ↗
08/22/2026X01183527-S1Open ↗
▸DOB NOWProgress Inspector Seal & Signature3
08/23/2026X01183527-I1Open ↗
08/23/2026X01183527-I1Open ↗
08/22/2026X01183527-S1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/21/2025240361880Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
03/21/2025240361880Open ↗
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026X01183527-I1Open ↗
08/13/2026X01183527-P1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026X01132172-I1Open ↗
▸DOB NOWElectric Cut-Off1
08/13/2026X01132172-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026X01132172-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026X01132172-I1Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST2
11/12/2025240361880Open ↗
03/21/2025240361880Open ↗
▸DOB NOWStreet Tree Checklist2
08/13/2026X01183527-I1Open ↗
08/13/2026X01183527-P1Open ↗
▸BISBPP: STREET TREES SITE PLAN1
11/12/2025240361880Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X01183527-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026X01183527-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWRodent Control1
08/13/2026X01132172-I1Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X01132172-I1Open ↗
▸Filing & Intake Forms2
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
03/21/2025240361880Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
03/21/2025240361880Open ↗
▸Other Documents14
▸BISBPP - SUPPORTING DOCUMENTATION3
11/12/2025240361880Open ↗
11/12/2025240361880Open ↗
03/21/2025240361880Open ↗
▸DOB NOWProperty Ownership Certification3
08/20/2026X01183527-I1Open ↗
08/20/2026X01183527-P1Open ↗
08/13/2026X01132172-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026X01183527-P1Open ↗
08/13/2026X01183527-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026X01183527-I1Open ↗
08/13/2026X01183527-P1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026X01132172-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026X01132172-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026X01183527-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026X01132172-I1Open ↗