| Owner | Filings | Most Recent |
|---|---|---|
| BRICOLAGEDESIGNS | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/17/2019 | $960K | — | Private party → Private party | $1,039/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SELF EMPLOYED | 1 | 08/28/2024 |
| BRICOLAGE DESIGNS | 5 | 08/08/2024 |
| SIS DESIGN STUDIO | 1 | 11/19/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| BRICOLAGE DESIGNS | 6 | 03/21/2026 |
| PROPERTY ELITE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JRD BROTHERS INC | General Contractor | 9 | 07/08/2026 |
| PLUMB-IT MECHANICAL INC | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 4 | 08/28/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | JRD BROTHERS INC | 08/29/2025 |
| DOB NOW | Plumbing | Permit Issued | JVR PLBG AND HEATING INC | 05/01/2025 |
| DOB NOW | Foundation | Permit Issued | JRD BROTHERS INC | 10/04/2024 |
| DOB NOW | Foundation | Permit Issued | JRD BROTHERS INC | 06/26/2024 |
| DOB NOW | Construction Fence | Permit Issued | JRD BROTHERS INC | 06/26/2024 |
| DOB NOW | Foundation | Permit Issued | JRD BROTHERS INC | 06/26/2024 |
| BIS | — | ISSUED | MERRICOM INC | 09/08/2025 |
| BIS | — | ISSUED | MERRICOM INC | 02/19/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2025 | Permit Issued | METROPOLITAN ELEC OF NY I | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/28/2024 | Permit Issued | JRD BROTHERS INC | 1 scope_items |
| 08/08/2024 | Permit Issued | JRD BROTHERS INC | Steel, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/08/2024 | Permit Issued | JRD BROTHERS INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/21/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 10/21/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 10/21/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 09/16/2025 | Final | NAVEEN KUMAR | progress |
| 09/16/2025 | Lowest Floor Elevation | — | progress |
| 09/16/2025 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 09/16/2025 | Structural Cold-Formed Steel | Younes Abouyaala | special |
| 09/16/2025 | Exterior Insulation and Finish Systems (EIFS) | Younes Abouyaala | special |
| 09/16/2025 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Younes Abouyaala | special |
| 09/16/2025 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 09/16/2025 | Structural Steel - Details | Younes Abouyaala | special |
| 09/16/2025 | Lowest Floor Elevation | Younes Abouyaala | progress |
| 09/16/2025 | Footing and Foundation | Younes Abouyaala | progress |
| 09/03/2025 | Lowest Floor Elevation | — | progress |
| 08/27/2024 | Lowest Floor Elevation | Younes Abouyaala | progress |
| 08/27/2024 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Younes Abouyaala | special |
| 08/27/2024 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 08/27/2024 | Final | NAVEEN KUMAR | progress |
| 08/27/2024 | Footing and Foundation | Younes Abouyaala | progress |
| 08/08/2024 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 08/08/2024 | Exterior Insulation and Finish Systems (EIFS) | Younes Abouyaala | special |
| 08/08/2024 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Younes Abouyaala | special |
| 08/08/2024 | Structural Cold-Formed Steel | Younes Abouyaala | special |
| 08/08/2024 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 08/08/2024 | Structural Steel - Details | Younes Abouyaala | special |