← Back
Two family converted from one family
142-30 249 STREET
QUEENS · BIN 4288575
💬 Discuss this project
1925Year Built
2Stories
B3Building Class
R3XZoning
2,994 sfGross Floor Area
2Units
Two family converted from one family · 5,000 sf lot · 0.6 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/23/2019$959K—— → —$320/sf building
02/02/2018$424K—Private party → ADRIAN GROUP LLC$142/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ROYAL ENGINEERING, P.C102/13/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PREPARER103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOMAL HOME IMPROVEMENTS.IGeneral Contractor507/08/2026
Building Lifecycle
All (5)Filed (1)Permit Issued (3)Signed Off (1)
01/07/2019
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Q00017762-I1
12/31/2018
Permit issued — Construction Fence
Q00017762-I1-FN
04/19/2018
Permit issued — Construction Fence
Q00017762-I1-FN
02/13/2018
Filed — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Q00017762-I1
02/13/2018
Permit issued — Construction Fence
Q00017762-I1-FN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offSOMAL HOME IMPROVEMENTS.I12/31/2018
DOB NOWConstruction FenceSigned-offSOMAL HOME IMPROVEMENTS.I04/19/2018
DOB NOWConstruction FenceSigned-offSOMAL HOME IMPROVEMENTS.I02/13/2018
BISOTISSUEDAMERGY SOLAR INC10/04/2019
BISPLISSUEDCROWN PLUMBING INC09/27/2018
BISPLISSUEDTOP DOG PLBG & HTG CORP05/14/2018
BIS—ISSUEDSOMAL HOME IMPROVEMENTS.I04/25/2018
BIS—ISSUEDSOMAL HOME IMPROVEMENTS.I04/25/2018
2 projects · most recent 10/10/2019
General Wiring
FiledStatusContractorScope
10/10/2019CompleteACE ELEC'L CONSTRUCTION—
07/17/2018CompleteMETROPOLITAN ELEC OF NY IGeneral Wiring
Nothing on file for this building.
▾Documents — 60 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/29/2026Q00017762-I1Request digital key ↗
▸Applications & Permits8
▸BISWORK PERMIT APPLICATION4
10/03/2019440568360Open ↗
10/29/2018421606667Open ↗
05/16/2018421606667Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION3
10/03/2019440568360Open ↗
01/23/2019421606667Open ↗
11/03/2018421606667Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
11/29/2018421606667Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISZONING DIAGRAM1
04/09/2018421606667Open ↗
▸Seals & Professional Certifications9
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
01/19/2019421606667Open ↗
01/16/2019421606667Open ↗
05/02/2018421606667Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/03/2019440568360Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/03/2019440568360Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/03/2019440568360Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/29/2026Q00017762-I1Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
11/10/2018421606667Open ↗
04/05/2018421606667Open ↗
▸Safety & Tenant Protection3
▸BISTENANT PROTECTION PLAN AND NOTES2
10/03/2019440568360Open ↗
03/20/2018421606667Open ↗
▸BISSTREET TREE CHECKLIST1
03/20/2018421606667Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
10/03/2019440568360Open ↗
04/09/2018421606667Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
01/19/2019421606667Open ↗
01/16/2019421606667Open ↗
05/02/2018421606667Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
04/07/2020440568360Open ↗
01/23/2019421606667Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
04/07/2020440568360Open ↗
10/03/2019440568360Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/03/2019440568360Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
10/03/2019440568360Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
04/07/2020440568360Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY2
04/07/2020440568360Open ↗
10/03/2019440568360Open ↗
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION2
01/23/2019421606667Open ↗
01/23/2019421606667Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
04/09/2018421606667Open ↗
▸Approvals, Objections & Sign-offs5
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
04/07/2020440568360Open ↗
01/23/2019421606667Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
04/09/2018421606667Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
04/07/2020440568360Open ↗
▸BISSUPERSEDING LETTER1
10/29/2018421606667Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT4
04/07/2020440568360Open ↗
10/03/2019440568360Open ↗
01/23/2019421606667Open ↗
Showing 3 of 4 on file for this type
▸BISDEPT OF FINANCE VERIFICATION1
01/23/2019421606667Open ↗
▸Filing & Intake Forms8
▸BISADDITIONAL INFORMATION4
03/12/2020440568360Open ↗
01/23/2019421606667Open ↗
04/09/2018421606667Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM2
01/23/2019421606667Open ↗
11/29/2018421606667Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/03/2019440568360Open ↗
▸BISEFILING COVER SHEET1
03/20/2018421606667Open ↗
▸Other Documents1
▸BISPLOT DIAGRAM1
01/23/2019421606667Open ↗