← Back
BuildNYC
One story - permanent living quarter
142-40 222 STREET
QUEENS · Laurelton · BIN 4280905
💬 Discuss this project
1950Year Built
1.5Stories
A2Building Class
R3XZoning
1,010 sfGross Floor Area
1Units
One story - permanent living quarter · 5,172 sf lot · 0.2 FAR built · Flood zone X
Locations of Work
Electrical
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofProposed PV solar system on dwelling1 filing · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Trinity Solar206/30/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Aca Associates103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Trinity SolarGeneral Contractor107/03/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Bitopi Consultants7036206/30/2026
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (8)
07/09/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01306571-I1
07/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
07/01/2026
Special inspection requirement — Final
Ayracon Almaraz
07/01/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
07/01/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
06/30/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01306571-P1
06/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
06/30/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
06/30/2026
Special inspection requirement — Final
Ayracon Almaraz
06/30/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
10/24/2025
Permit issued — Solar
Q01306571-I1-SL
10/22/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01306571-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTrinity Solar10/24/2025
2 projects · most recent 01/12/2026
General Wiring
FiledStatusContractorScope
01/12/2026CompleteRedline Electric—
09/11/2025Permit IssuedEmpire Lic Electrical ContractorsGeneral Wiring
1 project · most recent 06/30/2026
FiledStatusContractorScope
06/30/2026Signed-offTrinity Solar31 panels, 12.71 kw, 1,034 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
07/01/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
07/01/2026FinalAyracon Almarazprogress
07/01/2026Energy Code Compliance InspectionsAyracon Almarazprogress
07/01/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
06/30/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
06/30/2026Energy Code Compliance InspectionsAyracon Almarazprogress
06/30/2026FinalAyracon Almarazprogress
06/30/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026Q01306571-I1Request digital key ↗
08/18/2026Q01306571-P1Request digital key ↗
▸Seals & Professional Certifications10
▸DOB NOWProgress Inspector Seal & Signature6
10/09/2026Q01306571-I1Open ↗
10/09/2026Q01306571-I1Open ↗
10/09/2026Q01306571-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/18/2026Q01306571-I1Open ↗
08/18/2026Q01306571-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
10/09/2026Q01306571-I1Open ↗
08/23/2026Q01306571-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/18/2026Q01306571-P1Open ↗
08/18/2026Q01306571-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/18/2026Q01306571-I1Open ↗