| Owner | Filings | Most Recent |
|---|---|---|
| MDG DESIGN + CONSTRUCTION | 6 | 03/22/2026 |
| NYC HOUSING AUTHORITY | 12 | 03/22/2026 |
| NYCHA | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NEWMAN DESIGN ARCHITECTS PLLC | 5 | 08/30/2024 |
| CITYSCAPE ENGINEERING, PLLC | 2 | 07/27/2023 |
| DIBARI ENGINEERING, P.C. | 7 | 04/12/2023 |
| JOEL PHAGOO P.E. PLLC | 1 | 12/07/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| CHARIS CONSULTING | 6 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 14 | 03/21/2026 |
| EVELYN NEGRON | 1 | 03/21/2026 |
| DVA Advisors | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MDG DESIGN & CONSTR LLC | General Contractor | 7 | 07/08/2026 |
| YARKS NYC INC | General Contractor | 4 | 07/08/2026 |
| SNS ORGNIZATION LTD | General Contractor | 3 | 03/21/2026 |
| TRADELINE PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| JOHN DELUCA | Electrical | 2 | 03/21/2026 |
| DELCO ELECTRICAL CORP 002448 | General Contractor | 2 | 03/22/2026 |
| ZONE PLUMBING & HEATING C | Plumbing | 1 | 07/08/2026 |
| COLE, VINCENT | Electrical | 1 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| SUTTON, ALEX | Electrical | 1 | 03/21/2026 |
| A1 EXPEDITING SERVICE COR | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOMANI INSPECTION SERVICE | 843 | 4 | 07/27/2023 |
| LORJAN AGALLIU ARCHITECT | 6104 | 9 | 04/12/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | MDG DESIGN & CONSTR LLC | 10/11/2023 |
| DOB NOW | Plumbing | Signed-off | TRADELINE PLUMBING INC | 03/17/2023 |
| DOB NOW | Mechanical Systems | Signed-off | SNS ORGNIZATION LTD | 01/04/2023 |
| DOB NOW | Structural | Signed-off | MDG DESIGN & CONSTR LLC | 12/26/2022 |
| DOB NOW | Boiler Equipment | Signed-off | STUART N SCHWARTZ | 12/13/2022 |
| DOB NOW | Plumbing | Signed-off | ZONE PLUMBING & HEATING C | 10/14/2022 |
| DOB NOW | General Construction | Signed-off | MDG DESIGN & CONSTR LLC | 08/26/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | YARKS NYC INC | 02/23/2022 |
| DOB NOW | Boiler Equipment | Signed-off | STUART N SCHWARTZ | 01/19/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | YARKS NYC INC | 12/08/2021 |
| BIS | PL | ISSUED | RAYTONE PL SPEC INC | 03/02/2006 |
| BIS | FB | ISSUED | DOUGLAS SIMMONS | 10/21/2005 |
| BIS | BL | ISSUED | DOUGLAS SIMMONS | 02/15/2005 |
| BIS | PL | ISSUED | NY PLUMBING & SPRINKLER CORP | 02/15/2005 |
| BIS | FB | ISSUED | MARIC PLBG & HTG INC | 05/03/2002 |
| BIS | FS | ISSUED | STEPHEN BRAUN | 07/09/2001 |
| BIS | FS | ISSUED | JACK PICCINNI INC | 03/28/2001 |
| BIS | BL | ISSUED | DOUGLAS SIMMONS | 05/04/1999 |
| BIS | PL | ISSUED | NY PLUMBING & SPRINKLER CORP | 04/20/1999 |
| BIS | EQ | ISSUED | PERIMETER BRIDGE & SCAFFOLD CO | 02/11/1999 |
| BIS | PL | ISSUED | B.G. NATIONAL PLUMBING & HEATING | 02/28/1995 |
| BIS | FB | ISSUED | B.G. NATIONAL PLUMBING & HEATING | 02/28/1995 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/18/2025 | Complete | KTB ELECTRIC INC. | General Wiring |
| 07/16/2025 | Complete | DELCO ELECTRICAL CORP. | General Wiring |
| 07/16/2025 | Complete | DELCO ELECTRICAL CORP. | General Wiring |
| 12/07/2021 | Complete | RICHARD NEU | — |
| 10/09/2020 | Complete | JEMCO ELECT. CONTRS INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/10/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 11/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/27/2023 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 04/25/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/07/2023 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 04/04/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/22/2023 | No Access-Final Boiler Equipment Inspection | No Access | View ↗ |
| 11/23/2022 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 11/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/18/2024 | Fire-Resistance Rated Construction | lorjan agalliu | progress |
| 08/28/2023 | Concrete - Cast-In-Place | JOHN MCMONAGLE | special |
| 08/28/2023 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 08/28/2023 | Subsurface Investigations (Borings/Test Pits) | Hadiprawira Djohan | special |
| 08/28/2023 | Subsurface Conditions – Fill Placement & In-Place Density | JOHN MCMONAGLE | special |
| 08/28/2023 | Structural Stability – Alterations of existing buildings | JOHN MCMONAGLE | special |
| 08/28/2023 | Subgrade Inspections | JOHN MCMONAGLE | special |
| 08/28/2023 | Final | JOHN MCMONAGLE | progress |
| 08/28/2023 | Footing and Foundation | JOHN MCMONAGLE | progress |
| 04/26/2023 | HVAC-R and service water heating equipment | lorjan agalliu | energy_progress |
| 04/26/2023 | Heating Systems | LORJAN AGALLIU | special |
| 04/26/2023 | Maintenance information | lorjan agalliu | energy_progress |
| 04/26/2023 | HVAC-R and service water heating system controls | lorjan agalliu | energy_progress |
| 04/10/2023 | Maintenance information | lorjan agalliu | energy_progress |
| 04/10/2023 | Heating Systems | LORJAN AGALLIU | special |
| 04/10/2023 | HVAC-R and service water heating system controls | lorjan agalliu | energy_progress |
| 04/10/2023 | HVAC-R and service water heating equipment | lorjan agalliu | energy_progress |
| 03/03/2023 | Fire-Resistant Penetrations and Joints | lorjan agalliu | special |
| 12/28/2022 | Lighting in dwelling units | lorjan agalliu | energy_progress |
| 12/28/2022 | Masonry | lorjan agalliu | special |
| 12/28/2022 | Energy Code Compliance Inspections | lorjan agalliu | progress |
| 12/28/2022 | Fire-Resistance Rated Construction | lorjan agalliu | progress |
| 12/28/2022 | Final | lorjan agalliu | progress |
| 12/28/2022 | Fenestration and door U-factor and product ratings | lorjan agalliu | energy_progress |
| 12/28/2022 | Exterior lighting power | lorjan agalliu | energy_progress |