1967Year Built
1Stories
E1Building Class
M1-1Zoning
10,250 sfGross Floor Area
1Units
0 Open Violations
General warehouse · Owner of record: THE CHRISTIAN FELLOWSHIP MINISTRY INC. · 10,264 sf lot · 1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
Roof3p · 2 filings · 20 docs
Floor 2Under Construction4p · 1 filing · 17 docs
Floor 1Under Construction5p · 2 filings · 20 docs
MezzanineUnder Construction11p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FRATERNIDAD CRISTIANA, CORP103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/27/2022$3.8M—ABE V SYSTEMS, INC → THE CHRISTIAN FELLOWSHIP MINISTRY INC.$371/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MASTROGIACOMO ENGINEERING PC801/08/2025
HC ARCHITECT, PC103/08/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ALBA CONSULTANTS1603/21/2026
CH CORNERSTONE DESIGN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
QUINTEROS CONSTRUCTION OFGeneral Contractor707/08/2026
ARCO PLBG AND HTG INCFire Protection207/08/2026
BENCHMARK DESIGN BUILDERSGeneral Contractor204/09/2026
HORBRIDGE PLUMBING & HEATINGPlumbing207/08/2026
C.Q. ELECTR'L CONTRG CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MASTROGIACOMO ENGINEERING4237701/08/2025
BEYOND ARCH LLC3600103/08/2023
Building Lifecycle
All (80)Filed (9)Permit Issued (10)Signed Off (3)Violation (1)Inspection (16)Objection (26)Special Inspection (15)
07/28/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/07/2026
Inspection — Pass-Final SP Permit Withdrawal
Pass
View inspection ↗
03/26/2026
Signed off — Alteration
INTERIOR RENOVATION OF EXISTING BUILDING. NO CHANGE IN USE, EGRESS OR OCCUPANCY
X00688365-I1
03/09/2026
Signed off — Alteration
HEATING AND COOLING HVAC SPLIT UNITS ON THE GROUNG AND MEZZANINE FLOOR, NO CHANGE IN USE OR OCCUPANCY
X00858641-I1
07/14/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/23/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
06/02/2025
Signed off — Alteration
plumbing fixtures on ground and mezzanine floor work and sprinkler heads on ground floor and mezzanine floor. no change in use or occupancy. AMEND PLANS PAGHE P-200.02.
X00858600-I1
05/22/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/22/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/20/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/18/2025
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
03/03/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/27/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/07/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/04/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/09/2025
Special inspection requirement — Sprinkler Systems
MICHAEL MASTROGIACOMO
01/08/2025
Filed — Alteration
plumbing fixtures on ground and mezzanine floor work and sprinkler heads on ground floor and mezzanine floor. no change in use or occupancy. AMEND PLANS PAGHE P-200.02.
X00858600-P3
12/11/2024
Permit issued — General Construction
X00727361-I1-GC
07/26/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/22/2024
Permit issued — Sprinklers
X00858600-I1-EW-SP
07/22/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/09/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/26/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/21/2024
Permit issued — Sprinklers
X00858600-I1-PL
01/30/2024
Filed — Alteration
plumbing fixtures on ground and mezzanine floor work and sprinkler heads on ground floor and mezzanine floor. no change in use or occupancy. AMEND PLANS PAGHE P-200.02.
X00858600-P2
12/27/2023
Special inspection requirement — Sprinkler Systems
MICHAEL MASTROGIACOMO
12/22/2023
Permit issued — General Construction
X00727361-I1-GC
12/18/2023
Special inspection requirement — Final
MICHAEL MASTROGIACOMO
12/18/2023
Special inspection requirement — Mechanical Systems
MICHAEL MASTROGIACOMO
12/13/2023
Filed — Alteration
HEATING AND COOLING HVAC SPLIT UNITS ON THE GROUNG AND MEZZANINE FLOOR, NO CHANGE IN USE OR OCCUPANCY
X00858641-P1
12/13/2023
Filed — Alteration
plumbing fixtures on ground and mezzanine floor work and sprinkler heads on ground floor and mezzanine floor. no change in use or occupancy. AMEND PLANS PAGHE P-200.02.
X00858600-P1
12/13/2023
Special inspection requirement — Sprinkler Systems
MICHAEL MASTROGIACOMO
06/16/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/30/2023
Permit issued — Sprinklers
X00858600-I1-EW-SP
04/20/2023
Permit issued — Plumbing
X00858600-I1-PL
04/19/2023
Permit issued — Mechanical Systems
X00858641-I1-MS
04/12/2023
Filed — Alteration
HEATING AND COOLING HVAC SPLIT UNITS ON THE GROUNG AND MEZZANINE FLOOR, NO CHANGE IN USE OR OCCUPANCY
X00858641-I1
04/12/2023
Filed — Alteration
plumbing fixtures on ground and mezzanine floor work and sprinkler heads on ground floor and mezzanine floor. no change in use or occupancy. AMEND PLANS PAGHE P-200.02.
X00858600-I1
03/08/2023
Filed — Alteration CO
CHANGE CERTIFCATE OF OCCUPANCY FROM WAREHOUSE TO CHURCH U.G. 4A. ADDITONAL OF SECOND FLOOR ON EXISTING BULK FOR ACCESSORY TO CHURCH BELOW. PROVIDE NEW STOREFRONT. WORK INCLUDES NEW PARTITION WALLS, CEILING, FLOORING AND FINISHES , AMENDING PLANS
X00727361-P1
03/08/2023
Special inspection requirement — Fenestration air leakage
Hackjong Choi
03/08/2023
Special inspection requirement — Air barrier - visual inspection
Hackjong Choi
03/08/2023
Special inspection requirement — Interior lighting power
Hackjong Choi
03/08/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Hackjong Choi
03/08/2023
Special inspection requirement — Lighting controls
Hackjong Choi
03/08/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Hackjong Choi
03/08/2023
Special inspection requirement — Fenestration areas
Hackjong Choi
03/08/2023
Special inspection requirement — Fire-Resistance Rated Construction
Hackjong Choi
03/08/2023
Special inspection requirement — Energy Code Compliance Inspections
Hackjong Choi
10/31/2022
Permit issued — General Construction
X00727361-I1-GC
10/19/2022
Permit issued — General Construction
X00727361-I1-GC
07/28/2022
Objection raised — Admin
07/28/2022
Objection resolved — Addressed
05/09/2022
Objection raised — Mechanical
05/09/2022
Objection resolved — Addressed
05/06/2022
Objection raised — Mechanical
05/06/2022
Objection resolved — Addressed
05/06/2022
Objection raised — Inspections
05/06/2022
Objection resolved — Addressed
05/06/2022
Objection raised — Structural
05/06/2022
Objection resolved — Addressed
Latest 60 of 80 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedQUINTEROS CONSTRUCTION OF12/11/2024
DOB NOWSprinklersSigned-offARCO PLBG AND HTG INC07/22/2024
DOB NOWSprinklersSigned-offHORBRIDGE PLUMBING & HEAT02/21/2024
DOB NOWGeneral ConstructionPermit IssuedQUINTEROS CONSTRUCTION OF12/22/2023
DOB NOWSprinklersSigned-offARCO PLBG AND HTG INC05/30/2023
DOB NOWPlumbingSigned-offHORBRIDGE PLUMBING & HEAT04/20/2023
DOB NOWMechanical SystemsSigned-offQUINTEROS CONSTRUCTION OF04/19/2023
DOB NOWGeneral ConstructionPermit IssuedQUINTEROS CONSTRUCTION OF10/31/2022
DOB NOWGeneral ConstructionPermit IssuedBENCHMARK DESIGN BUILDERS10/19/2022
DOB NOWGeneral ConstructionSigned-offBENCHMARK DESIGN BUILDERS03/09/2022
1 project · most recent 01/13/2025
FiledStatusContractorScope
01/13/2025CompleteC.Q. ELECTR'L CONTRG CORP1 meters, 1 new_meters
▾Field Inspections (DOB CAP) — 16
DateTypeResultReport
07/28/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/07/2026Pass-Final SP Permit WithdrawalPassView ↗
07/14/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/23/2025Fail-Final CND-Occupancy InspectionFailView ↗
05/22/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/22/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/20/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/18/2025Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
03/03/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/27/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/07/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/04/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/26/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/22/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/26/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/16/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
01/09/2025Sprinkler SystemsMICHAEL MASTROGIACOMOspecial
12/27/2023Sprinkler SystemsMICHAEL MASTROGIACOMOspecial
12/18/2023FinalMICHAEL MASTROGIACOMOprogress
12/18/2023Mechanical SystemsMICHAEL MASTROGIACOMOspecial
12/13/2023Sprinkler SystemsMICHAEL MASTROGIACOMOspecial
03/08/2023Fenestration air leakageHackjong Choienergy_progress
03/08/2023Air barrier - visual inspectionHackjong Choienergy_progress
03/08/2023Interior lighting powerHackjong Choienergy_progress
03/08/2023Fenestration and door U-factor and product ratingsHackjong Choienergy_progress
03/08/2023Lighting controlsHackjong Choienergy_progress
03/08/2023Fire-Resistant Penetrations and JointsHackjong Choispecial
03/08/2023Fenestration areasHackjong Choienergy_progress
03/08/2023Fire-Resistance Rated ConstructionHackjong Choiprogress
03/08/2023Energy Code Compliance InspectionsHackjong Choiprogress
02/27/2022FinalHackjong Choiprogress
▾Documents — 42 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/24/2026X00688365-I1Request digital key ↗
08/23/2026X00727361-P1Request digital key ↗
08/22/2026X00858600-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/23/2026X00727361-P1Open ↗
08/23/2026X00727361-I1Open ↗
08/22/2026X00858600-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/29/2026X00858600-P1Open ↗
09/23/2026X00858600-I1Open ↗
08/31/2026X00727361-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/31/2026X00727361-P1Open ↗
08/31/2026X00727361-P1Open ↗
08/30/2026X00688365-I1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/13/2026X00727361-I1Open ↗
08/13/2026X00727361-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X00727361-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/23/2026X00727361-P1Open ↗
08/22/2026X00858600-P3Open ↗
08/22/2026X00858600-P2Open ↗
Showing 3 of 7 on file for this type
▸Approvals, Objections & Sign-offs7
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/22/2026X00858600-P3Open ↗
08/22/2026X00858600-P2Open ↗
08/22/2026X00858600-P1Open ↗
Showing 3 of 7 on file for this type
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
08/23/2026X00727361-P1Open ↗
08/15/2026X00727361-I1Open ↗