← Back
Miscellaneous two family
1425 CARROLL STREET
BROOKLYN · BIN 3033743
💬 Discuss this project
1920Year Built
2Stories
B9Building Class
R4Zoning
3,784 sfGross Floor Area
2Units
Rent Stabilized7 Open Violations ▸FDNY Report ↗
Miscellaneous two family · Owner of record: 1425 CARROLL LLC · 3,373 sf lot · 1.12 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingFire Protection
Roof1p · 1 filing · 20 docs
Floor 256p · 3 filings · 20 docs
Floor 152p · 2 filings · 20 docs
Cellar56p · 4 filings · 20 docs
1 job · most recent 01/07/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
01/07/2025Signed-offP.H. WORKS INCGas, Storm, Water/Sanitary
1 job · most recent 03/26/2025
General Wiring
FiledStatusContractorScope
03/26/2025CompleteLND ELECTRIC LLCGeneral Wiring
1 job · most recent 03/09/2023
Steel Concrete Masonry
FiledStatusContractorScope
03/09/2023Signed-offG BUILDERS MANAGEMENT INCSteel, Concrete, Masonry
Building Lifecycle
All (179)Filed (15)Permit Issued (23)Signed Off (5)Violation (13)Inspection (13)Objection (80)Special Inspection (30)
06/24/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/01/2026
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
03/18/2026
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
10/28/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/07/2025
Signed off — Alteration
installation of pipe scaffolding. no change in use, occupancy or egress under this application. all work to comply with chapter 33 of nycc
B01235035-I1
06/11/2025
Permit issued — Supported Scaffold
B01235035-I1-SF
06/10/2025
Filed — Alteration
installation of pipe scaffolding. no change in use, occupancy or egress under this application. all work to comply with chapter 33 of nycc
B01235035-I1
05/23/2025
Signed off — Alteration
Plumbing
B00522638-I1
05/23/2025
Signed off — Alteration
INSTALLAITON OF SPRINKLER SYSTEM FOR ENTIRE BUILDING IN CONJUNCTION WITH ALTERATION APPLICATION # B00514089. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00523077-I1
05/20/2025
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
05/20/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/15/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/12/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/12/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/12/2025
Special inspection requirement — Post-installed Anchors
VIJAY KUMAR
05/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
VIJAY KUMAR
05/12/2025
Special inspection requirement — Sprinkler Systems
VIJAY KUMAR
05/05/2025
Objection resolved — Addressed
05/05/2025
Objection resolved — Addressed
05/05/2025
Objection resolved — Addressed
05/05/2025
Objection resolved — Addressed
05/05/2025
Objection resolved — Addressed
05/05/2025
Special inspection requirement — Post-installed Anchors
05/01/2025
Objection raised — Scope
05/01/2025
Objection raised — Structural
05/01/2025
Objection raised — Structural
05/01/2025
Objection raised — Admin
05/01/2025
Objection raised — Inspections
04/23/2025
Signed off — Alteration
FILING POST APPROVAL AMENDMENT TO STRUCTURE AND FOUNDATION WORK IN CONJUNCTION WITH ASSOCIATED ALTERATION APPLICATION IN ORDER TO WAIVE BOTH TR2 AND TR3 REQUIREMENTS
B00534329-I1
04/23/2025
Objection resolved — Addressed
04/22/2025
Objection raised — Scope
04/10/2025
Filed — Alteration
INSTALLAITON OF SPRINKLER SYSTEM FOR ENTIRE BUILDING IN CONJUNCTION WITH ALTERATION APPLICATION # B00514089. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00523077-P2
04/08/2025
Special inspection requirement — Sprinkler Systems
VIJAY KUMAR
04/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
VIJAY KUMAR
04/01/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/27/2025
Filed — Alteration
INSTALLAITON OF SPRINKLER SYSTEM FOR ENTIRE BUILDING IN CONJUNCTION WITH ALTERATION APPLICATION # B00514089. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00523077-P1
03/26/2025
Special inspection requirement — Sprinkler Systems
VIJAY KUMAR
03/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
VIJAY KUMAR
03/04/2025
Permit issued — General Construction
B00514089-I1-GC
02/27/2025
Permit issued — Foundation
B00534329-I1-GC-CX
02/27/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/16/2025
Signed off — Alteration
B00522756-I1
01/07/2025
Filed — Alteration
Plumbing
B00522638-P2
10/30/2024
Objection resolved — Addressed
10/30/2024
Special inspection requirement — Maintenance information
VIJAY KUMAR
10/30/2024
Special inspection requirement — Fenestration air leakage
VIJAY KUMAR
10/30/2024
Special inspection requirement — Insulation placement and R values
VIJAY KUMAR
10/30/2024
Special inspection requirement — Protection of exposed foundation insulation
VIJAY KUMAR
10/30/2024
Special inspection requirement — Fenestration areas
VIJAY KUMAR
10/30/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
VIJAY KUMAR
10/30/2024
Special inspection requirement — Energy Code Compliance Inspections
VIJAY KUMAR
10/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
VIJAY KUMAR
10/30/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
VIJAY KUMAR
10/30/2024
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
VIJAY KUMAR
10/30/2024
Special inspection requirement — Air barrier — testing
VIJAY KUMAR
10/30/2024
Special inspection requirement — Fire-Resistance Rated Construction
VIJAY KUMAR
10/30/2024
Special inspection requirement — Air barrier - visual inspection
VIJAY KUMAR
10/30/2024
Special inspection requirement — Permanent certificate
VIJAY KUMAR
10/30/2024
Special inspection requirement — Metering
VIJAY KUMAR
10/30/2024
Special inspection requirement — Interior lighting power
VIJAY KUMAR
Latest 60 of 179 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
J G CONSTRUCTION SRVCS503/22/2026
G BUILDERS MANAGEMENT203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/18/2017$1.5M—Private party → 1425 CARROLL LLC$403/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASHRAF CORP106/10/2025
LEVIN ENGINEERING PLLC304/10/2025
AMR OUDA401/07/2025
SOLOMON ROSENZWEIG P.E P.C.403/09/2023
CORNERSTONE DESIGNS310/06/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ISLE CONSULTING803/21/2026
KMA DESIGNS LLC203/21/2026
LEVIN ENGINEERING PLLC603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
G BUILDERS MANAGEMENT INCGeneral Contractor4207/08/2026
P.H. WORKS INCPlumbing507/08/2026
J & G CONSTRUCTION SVCSGeneral Contractor303/21/2026
F.S. WORKS INCFire Protection107/08/2026
F S WORKSPlumbing103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AZ PROFESSIONAL ENGINEERI7661204/10/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offJ & G CONSTRUCTION SVCS06/11/2025
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC03/04/2025
DOB NOWFoundationSigned-offG BUILDERS MANAGEMENT INC02/27/2025
DOB NOWPlumbingSigned-offP.H. WORKS INC07/24/2024
DOB NOWSprinklersSigned-offP.H. WORKS INC05/17/2024
DOB NOWSprinklersSigned-offF.S. WORKS INC05/17/2024
DOB NOWConstruction FenceSigned-offG BUILDERS MANAGEMENT INC04/16/2024
DOB NOWFoundationSigned-offG BUILDERS MANAGEMENT INC04/16/2024
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC04/16/2024
DOB NOWGeneral ConstructionSigned-offG BUILDERS MANAGEMENT INC03/11/2024
DOB NOWConstruction FenceSigned-offG BUILDERS MANAGEMENT INC02/28/2024
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC02/23/2024
DOB NOWPlumbingSigned-offP.H. WORKS INC07/29/2023
DOB NOWConstruction FenceSigned-offG BUILDERS MANAGEMENT INC03/03/2023
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC03/03/2023
DOB NOWStructuralSigned-offG BUILDERS MANAGEMENT INC02/28/2023
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC11/18/2022
DOB NOWConstruction FenceSigned-offG BUILDERS MANAGEMENT INC11/09/2022
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC05/27/2022
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC03/28/2022
DOB NOWStructuralSigned-offG BUILDERS MANAGEMENT INC03/17/2022
DOB NOWGeneral ConstructionPermit IssuedG BUILDERS MANAGEMENT INC12/27/2021
DOB NOWConstruction FenceSigned-offG BUILDERS MANAGEMENT INC11/10/2021
▾Field Inspections (DOB CAP) — 13
DateTypeResultReport
06/24/2026Pass-Final CND-Occupancy InspectionPassView ↗
04/01/2026Fail-Final CND-Occupancy InspectionFailView ↗
03/18/2026Fail-Final CND-Occupancy InspectionFailView ↗
10/28/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/20/2025Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
05/20/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/15/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/12/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/12/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
02/27/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/07/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
09/05/2023Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 86
DateRequirementInspectorRole
05/12/2025Fire-Resistant Penetrations and JointsVIJAY KUMARspecial
05/12/2025Sprinkler SystemsVIJAY KUMARspecial
05/12/2025Post-installed AnchorsVIJAY KUMARspecial
05/05/2025Post-installed Anchors—special
04/08/2025Sprinkler SystemsVIJAY KUMARspecial
04/08/2025Fire-Resistant Penetrations and JointsVIJAY KUMARspecial
03/26/2025Sprinkler SystemsVIJAY KUMARspecial
03/26/2025Fire-Resistant Penetrations and JointsVIJAY KUMARspecial
10/30/2024HVAC-R and service water piping design and insulationVIJAY KUMARenergy_progress
10/30/2024Fenestration areasVIJAY KUMARenergy_progress
10/30/2024Fenestration and door U-factor and product ratingsVIJAY KUMARenergy_progress
10/30/2024Air barrier - visual inspectionVIJAY KUMARenergy_progress
10/30/2024MeteringVIJAY KUMARenergy_progress
10/30/2024Air barrier — testing VIJAY KUMARenergy_progress
10/30/2024Interior lighting powerVIJAY KUMARenergy_progress
10/30/2024Fenestration air leakageVIJAY KUMARenergy_progress
10/30/2024Protection of exposed foundation insulationVIJAY KUMARenergy_progress
10/30/2024Maintenance informationVIJAY KUMARenergy_progress
10/30/2024Exterior Insulation and Finish Systems (EIFS)VIJAY KUMARspecial
10/30/2024Fire-Resistant Penetrations and JointsVIJAY KUMARspecial
10/30/2024Fire-Resistance Rated ConstructionVIJAY KUMARprogress
10/30/2024Energy Code Compliance InspectionsVIJAY KUMARprogress
10/30/2024Permanent certificateVIJAY KUMARenergy_progress
10/30/2024Insulation placement and R valuesVIJAY KUMARenergy_progress
10/28/2024HVAC-R and service water piping design and insulationVIJAY KUMARenergy_progress
Latest 25 of 86.
▾Documents — 99 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
09/01/2026B00522638-I1Request digital key ↗
09/01/2026B00522638-P1Request digital key ↗
09/01/2026B00522638-P2Request digital key ↗
Showing 3 of 15 on file for this type
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZoning Exhibit form (1-5)3
08/13/2026B00514089-I1Open ↗
08/13/2026B00514089-P2Open ↗
08/13/2026B00514089-P1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026B00514089-P1Open ↗
08/13/2026B00514089-P2Open ↗
08/13/2026B00514089-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00514089-I1Open ↗
▸Seals & Professional Certifications38
▸DOB NOWDPL-1: Design Professional Seal & Signature15
09/01/2026B00522638-I1Open ↗
09/01/2026B00522638-P1Open ↗
09/01/2026B00522638-P2Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature13
09/28/2026B00534329-S1Open ↗
09/02/2026B00534329-P2Open ↗
09/01/2026B00523077-P2Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
09/28/2026B00534329-S1Open ↗
09/02/2026B00534329-P2Open ↗
08/28/2026B00514089-I1Open ↗
Showing 3 of 10 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist3
08/15/2026B00514089-I1Open ↗
08/14/2026B00514089-P2Open ↗
08/14/2026B00514089-P1Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
09/01/2026B00522638-I1Open ↗
09/01/2026B00522638-P1Open ↗
09/01/2026B00522638-P2Open ↗
Showing 3 of 13 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026B00522638-I1Open ↗
08/13/2026B00514089-I1Open ↗
▸Cost, Insurance & Ownership4
▸DOB NOWCertificate of Insurance2
08/13/2026B00514089-I1Open ↗
08/13/2026B00534329-I1Open ↗
▸DOB NOWCertification by Insurance Broker or Agency2
08/13/2026B00534329-I1Open ↗
08/13/2026B00514089-I1Open ↗
▸Other Documents17
▸DOB NOWSite Survey: Initial5
08/13/2026B00534329-P2Open ↗
08/13/2026B00534329-I1Open ↗
08/13/2026B00514089-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlot Diagram3
08/13/2026B00514089-I1Open ↗
08/13/2026B00514089-P2Open ↗
08/13/2026B00514089-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026B00514089-P1Open ↗
08/13/2026B00514089-P2Open ↗
08/13/2026B00514089-I1Open ↗
▸DOB NOWSURVEY: INITIAL3
08/13/2026B00514089-I1Open ↗
08/13/2026B00514089-P1Open ↗
08/13/2026B00514089-P2Open ↗
▸DOB NOWAdditional Insured Authorizations2
08/13/2026B00534329-I1Open ↗
08/13/2026B00514089-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00514089-I1Open ↗