0Year Built
—Stories
M9Building Class
R6Zoning
13,659 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Miscellaneous religious facility · Owner of record: 1427-49 LLC · 4,007 sf lot · 3.41 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof5 story community mechanical work61p · 2 filings · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 55 story community mechanical work76p · 2 filings · 20 docs
Floor 45 story community mechanical work74p · 2 filings · 20 docs
Floor 35 story community mechanical work75p · 2 filings · 20 docs
Floor 25 story community mechanical work77p · 2 filings · 20 docs
Floor 15 story community mechanical work80p · 4 filings · 20 docs
Cellar5 story community mechanical work75p · 2 filings · 20 docs
Site & exteriorInstallation of temporary pipe scaffold25p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Calvary303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/30/2020$2.7M—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Eretz Builders Assistance3003/21/2026
BMB Building Consulting803/21/2026
NYC Expediting Source103/21/2026
Herschel Rieger103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Good Quality Builders andGeneral Contractor1707/08/2026
CavalryGeneral Contractor1207/08/2026
Jodom MechanicalPlumbing507/08/2026
Good Quality Builders andScaffold507/08/2026
Reliable EnterprisesScaffold307/08/2026
CavalryScaffold203/21/2026
Centro Paz ConstructionScaffold203/21/2026
Safety Fire SprinklerFire Protection107/08/2026
Alef ConstructionGeneral Contractor106/27/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services56161808/20/2026
Skyline Rigging7880103/18/2024
Building Lifecycle
All (183)Filed (24)Permit Issued (31)Signed Off (11)Violation (3)Inspection (7)Objection (77)Special Inspection (30)
09/15/2026
Objection resolved — Addressed
09/14/2026
Objection raised — Other
08/20/2026
Filed — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-A1
08/06/2026
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
08/06/2026
Special inspection requirement — Interior lighting power
FAHAD FATEH
08/06/2026
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
08/06/2026
Special inspection requirement — Metering
FAHAD FATEH
08/06/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
08/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
08/06/2026
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
08/06/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
08/06/2026
Special inspection requirement — Exterior lighting power
FAHAD FATEH
08/06/2026
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
08/06/2026
Special inspection requirement — Fenestration areas
FAHAD FATEH
08/06/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
08/06/2026
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
08/06/2026
Special inspection requirement — Lighting controls
FAHAD FATEH
08/06/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Daniel Boss
04/29/2026
Permit issued — General Construction
B00515862-I1-GC
03/19/2026
Special inspection requirement — Lighting controls
FAHAD FATEH
03/19/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
03/19/2026
Special inspection requirement — Interior lighting power
FAHAD FATEH
03/19/2026
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
03/19/2026
Special inspection requirement — Metering
FAHAD FATEH
03/19/2026
Special inspection requirement — Fenestration areas
FAHAD FATEH
03/19/2026
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
03/19/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
03/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
03/19/2026
Special inspection requirement — Exterior lighting power
FAHAD FATEH
03/19/2026
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
03/19/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Daniel Boss
03/19/2026
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
03/19/2026
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
03/19/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
03/09/2026
Objection resolved — Addressed
03/03/2026
Objection raised — Other
02/18/2026
Filed — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-P9
11/20/2025
Signed off — Alteration
Mechanical work filed in conjunction with GC Application Job #B00515862-I1.
B00961978-I1
10/27/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/22/2025
Signed off — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-S8
07/21/2025
Signed off — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-S3
07/03/2025
Signed off — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-S6
06/26/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
06/13/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/13/2025
Objection resolved — Addressed
06/12/2025
Filed — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-P7
06/12/2025
Objection resolved — Addressed
06/12/2025
Objection resolved — Addressed
06/10/2025
Objection raised — Energy
06/10/2025
Objection raised — Cost
06/09/2025
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
06/09/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/06/2025
Signed off — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-S1
06/06/2025
Signed off — New Building
Sprinkler filed in conjunction with GC Application Job #B00515862-I1.
B00515862-S4
06/04/2025
Objection raised — Scope
06/04/2025
Objection resolved — Addressed
06/04/2025
Objection resolved — Addressed
05/30/2025
Objection resolved — Addressed
05/28/2025
Filed — Alteration
Mechanical work filed in conjunction with GC Application Job #B00515862-I1.
B00961978-P1
05/27/2025
Objection raised — Scope
Latest 60 of 183 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedAlef Construction04/29/2026
DOB NOWPlumbingPermit IssuedJodom Mechanical04/02/2025
DOB NOWMechanical SystemsSigned-offCavalry02/04/2025
DOB NOWBoiler EquipmentSigned-offJodom Mechanical09/05/2024
DOB NOWGeneral ConstructionPermit IssuedCavalry05/28/2024
DOB NOWSuspended ScaffoldSigned-offDoria05/01/2024
DOB NOWSprinklersSigned-offSafety Fire Sprinkler04/08/2024
DOB NOWGeneral ConstructionPermit IssuedCavalry03/26/2024
DOB NOWConstruction FenceSigned-offCavalry03/26/2024
DOB NOWSuspended ScaffoldSigned-offDoria03/18/2024
DOB NOWStructuralSigned-offGood Quality Builders and01/12/2024
DOB NOWGeneral ConstructionPermit IssuedGood Quality Builders and01/09/2024
DOB NOWSupported ScaffoldSigned-offReliable Enterprises01/08/2024
DOB NOWConstruction FenceSigned-offGood Quality Builders and01/05/2024
DOB NOWSidewalk ShedSigned-offReliable Enterprises12/04/2023
DOB NOWPlumbingPermit IssuedJodom Mechanical11/17/2023
DOB NOWSidewalk ShedSigned-offReliable Enterprises07/17/2023
DOB NOWStructuralSigned-offGood Quality Builders and01/09/2023
DOB NOWFoundationSigned-offGood Quality Builders and01/04/2023
DOB NOWSupport of ExcavationSigned-offGood Quality Builders and01/04/2023
DOB NOWFoundationPermit IssuedGood Quality Builders and01/04/2023
DOB NOWGeneral ConstructionPermit IssuedGood Quality Builders and01/04/2023
DOB NOWConstruction FenceSigned-offGood Quality Builders and01/03/2023
DOB NOWConstruction FenceSigned-offGood Quality Builders and07/27/2022
DOB NOWStructuralSigned-offGood Quality Builders and06/10/2022
DOB NOWSupport of ExcavationSigned-offGood Quality Builders and06/02/2022
DOB NOWFoundationSigned-offGood Quality Builders and06/02/2022
DOB NOWGeneral ConstructionPermit IssuedGood Quality Builders and06/02/2022
DOB NOWFoundationPermit IssuedGood Quality Builders and06/02/2022
DOB NOWConstruction FenceSigned-offGood Quality Builders and07/27/2021
DOB NOWConstruction FenceSigned-offCentro Paz Construction03/10/2021
1 project · most recent 08/20/2026
Sprinkler System
FiledStatusContractorScope
08/20/2026Signed-offSafety Fire SprinklerSprinkler System
1 project · most recent 08/20/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/20/2026Permit IssuedJodom MechanicalGas, Storm, Water/Sanitary
5 projects · most recent 09/05/2024
General Wiring
FiledStatusContractorScope
09/05/2024Permit IssuedHivolts ElectricalGeneral Wiring
02/22/2024CompleteHivolts Electrical—
01/23/2024CompletePower Direct Electric—
11/24/2023Permit IssuedPrime ElectricalGeneral Wiring
07/17/2023CompleteRichard Neu—
1 project · most recent 08/20/2026
Steel Concrete Masonry
FiledStatusContractorScope
08/20/2026Permit IssuedAlef ConstructionSteel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
10/27/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/26/2025Pass-Final Boiler Equipment InspectionPassView ↗
06/13/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/09/2025Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
06/09/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/08/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/13/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 143
DateRequirementInspectorRole
08/06/2026Fenestration air leakageFAHAD FATEHenergy_progress
08/06/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
08/06/2026Subsurface Investigations (Borings/Test Pits)Daniel Bossspecial
08/06/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
08/06/2026Fire-Resistance Rated ConstructionFAHAD FATEHprogress
08/06/2026Maintenance informationFAHAD FATEHenergy_progress
08/06/2026Fenestration areasFAHAD FATEHenergy_progress
08/06/2026Insulation placement and R valuesFAHAD FATEHenergy_progress
08/06/2026Exterior lighting powerFAHAD FATEHenergy_progress
08/06/2026Interior lighting powerFAHAD FATEHenergy_progress
08/06/2026Electrical motors and elevatorsFAHAD FATEHenergy_progress
08/06/2026Air barrier - visual inspectionFAHAD FATEHenergy_progress
08/06/2026Lighting controlsFAHAD FATEHenergy_progress
08/06/2026Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
08/06/2026MeteringFAHAD FATEHenergy_progress
03/19/2026Interior lighting powerFAHAD FATEHenergy_progress
03/19/2026Lighting controlsFAHAD FATEHenergy_progress
03/19/2026Maintenance informationFAHAD FATEHenergy_progress
03/19/2026Subsurface Investigations (Borings/Test Pits)Daniel Bossspecial
03/19/2026Fire-Resistance Rated ConstructionFAHAD FATEHprogress
03/19/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
03/19/2026Air barrier - visual inspectionFAHAD FATEHenergy_progress
03/19/2026Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
03/19/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
03/19/2026Insulation placement and R valuesFAHAD FATEHenergy_progress
Latest 25 of 143.
▾Documents — 180 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch24
09/01/2026B00481981-I1Request digital key ↗
08/27/2026B00900718-I1Request digital key ↗
08/26/2026B00985941-I1Request digital key ↗
Showing 3 of 24 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly1
08/23/2026B01152846-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
08/18/2021340819092Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
07/24/2024340819092Open ↗
▸Zoning, Tax Lot & Property Records15
▸DOB NOWZD1: DOB Zoning Diagram7
08/18/2026B00515862-A1Open ↗
08/13/2026B00515862-P8Open ↗
08/13/2026B00515862-P9Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWZoning Exhibit form (1-5)7
08/18/2026B00515862-A1Open ↗
08/13/2026B00515862-P9Open ↗
08/13/2026B00515862-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00515862-I1Open ↗
▸Seals & Professional Certifications69
▸DOB NOWDPL-1: Design Professional Seal & Signature25
09/01/2026B00481981-I1Open ↗
08/25/2026B01019943-I1Open ↗
08/24/2026B00961978-I1Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWProgress Inspector Seal & Signature21
09/01/2026B01152846-I1Open ↗
08/30/2026B00515862-S1Open ↗
08/30/2026B00515862-S1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature21
08/30/2026B00515862-S1Open ↗
08/30/2026B00515862-S1Open ↗
08/29/2026B00515862-P8Open ↗
Showing 3 of 21 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/18/2021340819092Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
08/18/2021340819092Open ↗
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)6
08/13/2026B00515862-P9Open ↗
08/13/2026B00515862-P7Open ↗
08/13/2026B00515862-P1Open ↗
Showing 3 of 6 on file for this type
▸Safety & Tenant Protection12
▸DOB NOWStreet Tree Checklist7
08/18/2026B00515862-A1Open ↗
08/18/2026B00515862-P8Open ↗
08/18/2026B00515862-P7Open ↗
Showing 3 of 7 on file for this type
▸BISBPP: STREET TREES SITE PLAN1
04/12/2024340819092Open ↗
▸BISSTREET TREE CHECKLIST1
08/18/2021340819092Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00515862-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00515862-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00515862-I1Open ↗
▸Energy Compliance4
▸DOB NOWPreliminary Commissioning Report Certification3
08/13/2026B00961978-I1Open ↗
08/13/2026B00515862-S8Open ↗
08/13/2026B00515862-S5Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00515862-I1Open ↗
▸Inspections & Test Reports12
▸DOB NOWSOIL REPORT8
08/18/2026B00515862-A1Open ↗
08/13/2026B00515862-P9Open ↗
08/13/2026B00515862-P7Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026B00515862-I1Open ↗
08/13/2026B00515862-S1Open ↗
▸DOB NOWTR4 Plot Diagram2
08/13/2026B00515862-S1Open ↗
08/13/2026B00515862-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
05/02/2025340819092Open ↗
▸Cost, Insurance & Ownership2
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026B00515862-I1Open ↗
▸DOB NOWCertificate of Insurance1
08/13/2026B00515862-I1Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
08/18/2021340819092Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
08/18/2021340819092Open ↗
▸Other Documents30
▸DOB NOWSite Survey: Initial7
08/18/2026B00515862-A1Open ↗
08/13/2026B00515862-P1Open ↗
08/13/2026B00515862-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone7
08/18/2026B00515862-A1Open ↗
08/13/2026B00515862-P1Open ↗
08/13/2026B00515862-P8Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWPD1 Document7
08/18/2026B00515862-A1Open ↗
08/13/2026B00515862-P1Open ↗
08/13/2026B00515862-P2Open ↗
Showing 3 of 7 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION4
07/24/2024340819092Open ↗
07/10/2024340819092Open ↗
04/12/2024340819092Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAdditional Insured Authorizations1
08/13/2026B00515862-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00515862-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00515862-S2Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026B01019943-I1Open ↗
▸DOB NOWCalculations1
08/13/2026B01019943-I1Open ↗