| Owner | Filings | Most Recent |
|---|---|---|
| Gabrielle Associates | 8 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Enthink Engineers | 1 | 03/09/2022 |
| Palette Architecture | 2 | 02/16/2022 |
| LL Engineering | 1 | 09/08/2021 |
| Ivan Design Engineering Analysis | 1 | 08/27/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC Department of Housing Preservation and Development | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LLNY Group | General Contractor | 7 | 07/08/2026 |
| Andamio Scaffolding | Scaffold | 3 | 03/21/2026 |
| LMD Residential | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LL Engineering | 1618 | 1 | 09/08/2021 |
| CNS Inspection Services | 7566 | 2 | 08/27/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | LLNY Group | 05/05/2022 |
| DOB NOW | Structural | Signed-off | LLNY Group | 05/05/2022 |
| DOB NOW | Mechanical Systems | Signed-off | LLNY Group | 05/05/2022 |
| DOB NOW | Mechanical Systems | Signed-off | LMD Residential | 03/29/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Andamio Scaffolding | 03/09/2022 |
| BIS | — | ISSUED | Gabrielle Associates | 08/22/2011 |
| BIS | FP | ISSUED | Active Fire Extinguisher Co | 03/19/2004 |
| BIS | PL | ISSUED | Maccarone Plumbing | 03/18/1998 |
| BIS | OT | ISSUED | Dhi Construction Services | 07/18/1997 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/19/2022 | Complete | Power Surge Electric | General Wiring |
| 06/27/2022 | Complete | RNH Electric Company | HVAC Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/26/2022 | Fire-Resistant Penetrations and Joints | John Nucatola | special |
| 02/26/2022 | Interior lighting power | John Nucatola | energy_progress |
| 02/26/2022 | Lighting controls | John Nucatola | energy_progress |
| 02/26/2022 | Air barrier - visual inspection | John Nucatola | energy_progress |
| 02/26/2022 | Exterior lighting power | John Nucatola | energy_progress |
| 02/26/2022 | Insulation placement and R values | John Nucatola | energy_progress |
| 02/26/2022 | Final | John Nucatola | progress |
| 02/15/2022 | Air barrier - visual inspection | — | energy_progress |
| 02/15/2022 | Lighting controls | — | energy_progress |
| 02/15/2022 | Exterior lighting power | — | energy_progress |
| 02/15/2022 | Insulation placement and R values | — | energy_progress |
| 02/15/2022 | Interior lighting power | — | energy_progress |
| 02/10/2022 | Final | — | progress |
| 02/10/2022 | Fire-Resistant Penetrations and Joints | — | special |
| 04/25/2021 | Maintenance information | LOUIS LEE | energy_progress |
| 04/25/2021 | HVAC-R and service water heating system controls | LOUIS LEE | energy_progress |
| 04/25/2021 | HVAC-R and service water heating equipment | LOUIS LEE | energy_progress |
| 04/25/2021 | Mechanical Systems | LOUIS LEE | special |
| 04/25/2021 | Final | LOUIS LEE | progress |
| 04/25/2021 | Energy Code Compliance Inspections | LOUIS LEE | progress |
| 04/25/2021 | Fire-Resistant Penetrations and Joints | LOUIS LEE | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| ACS | Government / Civic | Cellar, Floors 1–3, Roof | Project Q00509980 Project Q00503155 |