| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/26/2025 | $570K | — | Private party → SARA DEVELOPMENT LLC | $416/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| J.K.DESIGN | 4 | 07/13/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RECORD GROUP INC | General Contractor | 3 | 03/21/2026 |
| EUSEBIO MCQUEEN | Electrical | 1 | 03/21/2026 |
| MCQUEEN EUSEBIO | Electrical | 1 | 03/21/2026 |
| CHANDRABALI RAMANAND | General Contractor | 1 | 04/09/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 3 | 07/13/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 01/28/2026 |
| DOB NOW | General Construction | Permit Issued | RECORD GROUP INC | 11/03/2025 |
| DOB NOW | Construction Fence | Signed-off | CHANDRABALI RAMANAND | 07/02/2025 |
| BIS | PL | ISSUED | PRECISION PLBG SVCS., INC | 09/16/2014 |
| BIS | OT | RE-ISSUED | A&A BUILDING CONSULTANTS | 08/14/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | Permit Issued | ALL PRO PLBG & HTG INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/12/2026 | Permit Issued | ASCUATECH ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | Permit Issued | ALL PRO PLBG & HTG INC | Concrete, Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/30/2026 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 07/30/2026 | Subsurface Investigations (Borings/Test Pits) | FAHAD FATEH | special |
| 07/30/2026 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 07/30/2026 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 07/30/2026 | Subgrade Inspections | Younes Abouyaala | special |
| 07/30/2026 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 07/30/2026 | Excavations - Sheeting, Shoring, and Bracing | Younes Abouyaala | special |
| 07/30/2026 | Final | NAVEEN KUMAR | progress |
| 07/30/2026 | Footing and Foundation | Younes Abouyaala | progress |
| 07/30/2026 | Fire-Resistance Rated Construction | Younes Abouyaala | progress |
| 07/30/2026 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 07/30/2026 | Structural Wood Frame | Younes Abouyaala | progress |
| 07/30/2026 | Fenestration and door U-factor and product ratings | Younes Abouyaala | energy_progress |
| 07/30/2026 | Insulation placement and R values | Younes Abouyaala | energy_progress |
| 07/30/2026 | Metering | Younes Abouyaala | energy_progress |
| 07/30/2026 | Fenestration areas | Younes Abouyaala | energy_progress |
| 07/30/2026 | Fenestration air leakage | Younes Abouyaala | energy_progress |
| 07/30/2026 | Protection of exposed foundation insulation | Younes Abouyaala | energy_progress |
| 07/30/2026 | Electric vehicle service equipment requirements | Younes Abouyaala | energy_progress |
| 07/30/2026 | Interior lighting power | Younes Abouyaala | energy_progress |
| 07/30/2026 | Maintenance information | Younes Abouyaala | energy_progress |
| 07/30/2026 | Permanent certificate | Younes Abouyaala | energy_progress |
| 07/13/2026 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 07/13/2026 | Excavations - Sheeting, Shoring, and Bracing | Younes Abouyaala | special |
| 07/13/2026 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |