1931Year Built
3Stories
C2Building Class
R6Zoning
4,500 sfGross Floor Area
6Units
Rent Stabilized25 Open Violations ▸FDNY Report ↗
Five to six families · Owner of record: 1433 GREENE AVE LLC · 2,359 sf lot · 1.91 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 32p · 2 filings · 20 docs
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FERHATI907/08/2026
1433 GREENE AVE LLC203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AA BLDG & INSP SVC LLC301/29/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FERHATI LLCGeneral Contractor107/08/2026
ALL PRO PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519301/29/2024
Building Lifecycle
All (112)Filed (3)Permit Issued (2)Signed Off (2)Violation (60)Inspection (3)Objection (36)Special Inspection (6)
04/16/2026
Violation issued (HPD, closed)
A
09/17/2025
Violation issued (HPD, closed)
C
09/17/2025
Violation issued (HPD, closed)
C
01/03/2025
Violation issued (HPD, closed)
B
01/03/2025
Violation issued (HPD, closed)
B
01/03/2025
Violation issued (HPD, closed)
C
09/18/2024
Violation issued (HPD, closed)
C
09/18/2024
Violation issued (HPD, open)
B
09/18/2024
Violation issued (HPD, closed)
C
09/18/2024
Violation issued (HPD, open)
B
09/18/2024
Violation issued (HPD, closed)
C
09/18/2024
Violation issued (HPD, closed)
C
09/18/2024
Violation issued (HPD, closed)
C
07/24/2024
Signed off — Alteration
REPAIR FIRE DAMAGE. RPLC EX RES. GAS STOVE ON NEW GAS ROUGHING PER PLANS ON THE 3RD FLR APT. RPLC GAS RISER PIPES FOR APTS ON 1ST & 2ND FLRS. RE-ISSUE GAS AUTHORIZATION FOR EX. (6) RESI GAS STOVES, EX. (1) HWH & EX (1) BOILER.
B00815416-I1
06/24/2024
Signed off — Alteration
REPAIR FIRE DAMAGED PARTITIONS ON THE 3RD FLOORS APARTMENT ONLY PER PROVIDED PLANS . NO CHANGE IN USE , EGRESS OR OCCUPANCY UNDER THIS FILING.
B00815409-I1
06/17/2024
Violation issued (HPD, closed)
C
06/17/2024
Violation issued (HPD, closed)
C
06/17/2024
Violation issued (HPD, closed)
B
05/02/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/01/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/15/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/22/2024
Permit issued — General Construction
B00815409-I1-GC
03/20/2024
Special inspection requirement — Tenant Protection Plan Compliance
Younes Abouyaala
03/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
03/20/2024
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
03/18/2024
Objection resolved — Addressed
03/15/2024
Objection raised — Scope
03/14/2024
Objection resolved — Addressed
03/07/2024
Objection resolved — Addressed
03/01/2024
Objection resolved — Addressed
02/28/2024
Objection raised — Scope
02/21/2024
Objection resolved — Addressed
02/13/2024
Objection resolved — Addressed
02/07/2024
Objection raised — Other
02/07/2024
Objection raised — Scope
02/01/2024
Objection raised — Scope
01/31/2024
Objection resolved — Addressed
01/31/2024
Objection resolved — Addressed
01/30/2024
Objection raised — Scope
01/30/2024
Objection raised — Scope
01/30/2024
Objection resolved — Addressed
01/30/2024
Objection resolved — Addressed
01/29/2024
Filed — Alteration
REPAIR FIRE DAMAGE. RPLC EX RES. GAS STOVE ON NEW GAS ROUGHING PER PLANS ON THE 3RD FLR APT. RPLC GAS RISER PIPES FOR APTS ON 1ST & 2ND FLRS. RE-ISSUE GAS AUTHORIZATION FOR EX. (6) RESI GAS STOVES, EX. (1) HWH & EX (1) BOILER.
B00815416-P1
01/24/2024
Permit issued — Plumbing
B00815416-I1-PL
01/10/2024
Objection raised — Scope
01/03/2024
Objection raised — Scope
01/03/2024
Objection resolved — Addressed
01/03/2024
Objection resolved — Addressed
01/03/2024
Objection resolved — Addressed
01/02/2024
Objection resolved — Addressed
12/27/2023
Objection raised — Scope
12/20/2023
Objection resolved — Addressed
12/20/2023
Objection resolved — Addressed
12/20/2023
Objection resolved — Addressed
12/20/2023
Objection resolved — Addressed
12/12/2023
Objection raised — Scope
12/12/2023
Objection raised — Scope
12/12/2023
Objection raised — Scope
12/11/2023
Filed — Alteration
REPAIR FIRE DAMAGE. RPLC EX RES. GAS STOVE ON NEW GAS ROUGHING PER PLANS ON THE 3RD FLR APT. RPLC GAS RISER PIPES FOR APTS ON 1ST & 2ND FLRS. RE-ISSUE GAS AUTHORIZATION FOR EX. (6) RESI GAS STOVES, EX. (1) HWH & EX (1) BOILER.
B00815416-I1
11/06/2023
Objection raised — Scope
Latest 60 of 112 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offFERHATI LLC03/22/2024
DOB NOWPlumbingSigned-offALL PRO PLBG & HTG INC01/24/2024
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
05/02/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/01/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/15/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
03/20/2024Tenant Protection Plan ComplianceYounes Abouyaalaspecial
03/20/2024Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
03/20/2024Energy Code Compliance InspectionsYounes Abouyaalaprogress
03/06/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
03/06/2023Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
01/19/2023FinalNAVEEN KUMARprogress
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/26/2026B00815416-I1Request digital key ↗
08/15/2026B00815416-P1Request digital key ↗
08/15/2026B00815409-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/26/2026B00815416-P1Open ↗
08/26/2026B00815416-I1Open ↗
08/13/2026B00815409-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/30/2026B00815416-I1Open ↗
08/28/2026B00815409-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/30/2026B00815416-I1Open ↗
08/28/2026B00815409-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/26/2026B00815416-I1Open ↗
08/15/2026B00815416-P1Open ↗
08/13/2026B00815409-I1Open ↗
▸Other Documents6
▸DOB NOWHPD4: CONH Pilot Program3
08/13/2026B00815409-I1Open ↗
08/13/2026B00815416-P1Open ↗
08/13/2026B00815416-I1Open ↗
▸DOB NOWDHCR Document3
08/13/2026B00815416-I1Open ↗
08/13/2026B00815416-P1Open ↗
08/13/2026B00815409-I1Open ↗