| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2025 | Signed-off | ORBIT PLBG & HTG INC | Gas, Water/Sanitary |
| 02/04/2022 | Permit Issued | ACCURATE MECHANICAL INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | BASS ELECTRICAL CORP. | General Wiring |
| 03/10/2026 | Permit Issued | WCK ELECTRIC CORP. | General Wiring |
| 11/12/2024 | Complete | EMPIRE LIC ELECL CONTRS | General Wiring |
| 10/01/2024 | Complete | ULTRA ELECTRIC CORP | General Wiring |
| 05/16/2024 | Complete | MER ELECTRIC, INC | General Wiring |
| 04/11/2024 | Complete | OM ELECTRIC, INC | General Wiring |
| 03/25/2024 | Cancelled | ROB ELECTRIC LLC | General Wiring |
| 06/14/2023 | Permit Issued | SOURCE ELECTRIC INC | General Wiring, Lighting |
| 04/29/2023 | Complete | J.G.C. ELECTRIC, LLC | General Wiring |
| 03/31/2023 | Complete | KJK ELECTRIC INC | General Wiring |
| 03/22/2023 | Complete | INTELOGIC ELECTRIC, INC. | — |
| 01/27/2023 | Permit Issued | ELPO ELECTRICAL CONTG INC | General Wiring |
| 05/17/2022 | Complete | POS ELECTRICAL CONTRS INC | — |
| 04/14/2022 | Complete | METROPOLIS ELECTRIC CORP | General Wiring |
| 01/18/2022 | Permit Issued | ACCURATE ELEC'L CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2023 | Permit Issued | DC PROJECTS INC | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2025 | Signed-off | MC CONSTR CONSULTING INC | Suspended Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2025 | Signed-off | MC CONSTR CONSULTING INC | Suspended Scaffold (SC) |
| 12/18/2023 | Permit Issued | STANDARD WATERPROOFING C | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| VCAREOBGYNPC | 7 | 07/08/2026 |
| KARTEN EQUITIES | 6 | 04/09/2026 |
| J C LAMB MANAGEMENT | 17 | 04/08/2026 |
| LLS OF NEW YORK LLC | 5 | 03/22/2026 |
| SARATOGA | 11 | 03/22/2026 |
| BELL MARC REALTY | 1 | 03/22/2026 |
| SHERWOOD ASSOCIATES | 4 | 03/22/2026 |
| TO THE OWNER OF 330 EAST | 1 | 03/22/2026 |
| TULGA PRODUCE CORP | 2 | 03/22/2026 |
| BETTINA EQUINTIES CO | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HC ARCHITECT, PC | 4 | 05/07/2026 |
| DAN CHOI ARCHITECTURE P.C | 3 | 07/31/2025 |
| DAVID JIMENEZ, RA | 1 | 02/20/2024 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 10/10/2023 |
| JARMEL KIZEL ARCHITECTS & ENGINEERS | 10 | 06/28/2023 |
| NY RESTORATION TECHNOLOGY CORP | 1 | 12/12/2022 |
| JACK GREEN ASSOCIATES | 1 | 11/17/2022 |
| ENTHINK ENGINEERS LLC | 3 | 09/16/2022 |
| JACOBSON SHINODA ARCHITECTS | 1 | 03/31/2022 |
| A. CAPRIO ARCHITECT, PLLC | 2 | 02/04/2022 |
| GERALD CALIENDO ARCHITECTS | 1 | 08/13/2021 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 07/15/2021 |
| GREEN DESIGN | 2 | 03/25/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEEKODESIGN | 3 | 03/21/2026 |
| A K EXPEDITING | 2 | 03/21/2026 |
| GERALD J CALIENDO ARCHITECT | 2 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 22 | 03/21/2026 |
| I L CONSULTING | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| A D BUILDING SOLUTIONS | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| EMPIRE CITY CONSULTANTS, INC. | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANDAMIO SCAFFOLDING LLC | General Contractor | 13 | 07/08/2026 |
| ALBA GROUP INC | General Contractor | 10 | 07/08/2026 |
| STANDARD WATERPROOFING C | General Contractor | 8 | 07/08/2026 |
| J.F. HUGHES BUILDERS INC | General Contractor | 4 | 07/08/2026 |
| DKC INC | General Contractor | 4 | 07/08/2026 |
| PZ PAINTERS, LLC | General Contractor | 4 | 07/08/2026 |
| FJB CONTRACTING INC | General Contractor | 3 | 07/08/2026 |
| DC PROJECTS INC | General Contractor | 3 | 06/28/2026 |
| VSP MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| J. CAIAZZO PLBG & HTG COR | Plumbing | 2 | 07/08/2026 |
| OM ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| POS ELECTRICAL CONTRS INC | Electrical | 1 | 03/22/2026 |
| S.A.L. ELECTRIC CO INC. | Electrical | 1 | 03/22/2026 |
| SANDHA GENERAL CONTRACTIN | Electrical | 1 | 03/21/2026 |
| ULTRA ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| V. CLOUD PAINTING AND CON | Electrical | 1 | 03/21/2026 |
| VMA ELECTRICAL CORP. | Electrical | 1 | 03/22/2026 |
| BOROWIDE ELECT'L CONTR'S | Electrical | 1 | 03/22/2026 |
| ALL AMERICAN CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| BIG APPLE HOLDINGS GROUP | General Contractor | 1 | 04/09/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 1 | 07/08/2026 |
| FRED J. RIEHM INC | Plumbing | 1 | 06/28/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| TOP DOG PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BEYOND ARCH LLC | 3600 | 4 | 05/07/2026 |
| KZ ENGINEERING, P.C. | 4665 | 1 | 09/11/2025 |
| DC DESIGN CONSULTING INC | 8078 | 3 | 07/31/2025 |
| ALAN MARGOLIN & ASSOC | 423 | 1 | 02/20/2024 |
| CATALPA SPECIAL INSPECTIO | 2004 | 10 | 06/28/2023 |
| NY RESTORATION TECHNOLOGY | 6187 | 1 | 12/12/2022 |
| JACK GREEN ASSOCIATES | 422 | 1 | 11/17/2022 |
| ENTHINK ENGINEERS LLC | 6247 | 2 | 06/15/2022 |
| KATZ ENGINEERING | 238 | 2 | 02/04/2022 |
| DOYUN KIM; RA | 7415 | 1 | 08/13/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | DC PROJECTS INC | 06/26/2026 |
| DOB NOW | Plumbing | Permit Issued | FRED J. RIEHM INC | 05/21/2026 |
| DOB NOW | General Construction | Permit Issued | FJB CONTRACTING INC | 05/11/2026 |
| DOB NOW | General Construction | Permit Issued | FJB CONTRACTING INC | 03/26/2026 |
| DOB NOW | General Construction | Permit Issued | FJB CONTRACTING INC | 03/16/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | MC CONSTR CONSULTING INC | 11/12/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | DC PROJECTS | 10/10/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | MC CONSTR CONSULTING INC | 09/16/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/02/2025 |
| DOB NOW | General Construction | Permit Issued | BIG APPLE HOLDINGS GROUP | 05/19/2025 |
| DOB NOW | Plumbing | Signed-off | ORBIT PLBG & HTG INC | 05/09/2025 |
| DOB NOW | Plumbing | Permit Issued | J. CAIAZZO PLBG & HTG COR | 11/14/2024 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | STANDARD WATERPROOFING C | 09/24/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | STANDARD WATERPROOFING C | 09/23/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/09/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | STANDARD WATERPROOFING C | 09/06/2024 |
| DOB NOW | General Construction | Signed-off | J.F. HUGHES BUILDERS INC | 08/13/2024 |
| DOB NOW | General Construction | Signed-off | J.F. HUGHES BUILDERS INC | 02/28/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | STANDARD WATERPROOFING C | 01/10/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | STANDARD WATERPROOFING C | 09/22/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/12/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | STANDARD WATERPROOFING C | 09/01/2023 |
| DOB NOW | Plumbing | Permit Issued | ANTHONY DISABATO | 07/25/2023 |
| DOB NOW | General Construction | Permit Issued | DKC | 07/21/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | STANDARD WATERPROOFING C | 05/19/2023 |
| DOB NOW | General Construction | Permit Issued | DKC | 05/12/2023 |
| DOB NOW | Sprinklers | Signed-off | FULL CAPACITY FIRE CORP | 11/29/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/16/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/18/2022 |
| DOB NOW | Plumbing | Permit Issued | ANTHONY DISABATO | 06/02/2022 |
| DOB NOW | General Construction | Permit Issued | DKC | 05/16/2022 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 05/04/2022 |
| DOB NOW | General Construction | Signed-off | ALL AMERICAN CONSTRUCTION | 04/21/2022 |
| DOB NOW | Plumbing | Signed-off | TOP DOG PLBG & HTG CORP | 04/19/2022 |
| DOB NOW | General Construction | Permit Issued | ALBA GROUP INC | 04/08/2022 |
| DOB NOW | Mechanical Systems | Signed-off | ALBA GROUP INC | 04/08/2022 |
| DOB NOW | General Construction | Permit Issued | ALBA GROUP INC | 03/29/2022 |
| DOB NOW | General Construction | Permit Issued | ALBA GROUP INC | 01/08/2022 |
| DOB NOW | General Construction | Signed-off | PZ PAINTERS, LLC | 11/17/2021 |
| DOB NOW | General Construction | Signed-off | PZ PAINTERS, LLC | 09/14/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/28/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/16/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/04/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/30/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/30/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/11/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/24/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/27/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/27/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/09/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/21/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/01/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/09/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/08/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/05/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/22/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/16/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/02/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/19/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/25/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/28/2026 | Tenant Protection Plan Compliance | Hackjong Choi | special |
| 04/28/2026 | Fire-Resistant Penetrations and Joints | Hackjong Choi | special |
| 02/18/2026 | Fire-Resistance Rated Construction | Hackjong Choi | progress |
| 02/18/2026 | Energy Code Compliance Inspections | Hackjong Choi | progress |
| 02/18/2026 | Final | Hackjong Choi | progress |
| 02/18/2026 | Tenant Protection Plan Compliance | Hackjong Choi | special |
| 02/18/2026 | Fire-Resistant Penetrations and Joints | Hackjong Choi | special |
| 02/18/2026 | Final | Hackjong Choi | progress |
| 02/18/2026 | Tenant Protection Plan Compliance | Hackjong Choi | special |
| 02/18/2026 | Interior lighting power | Hackjong Choi | energy_progress |
| 09/10/2025 | Post-installed Anchors | Karol Zdancewicz | special |
| 09/10/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 08/21/2025 | Fire-Resistant Penetrations and Joints | DAN CHOI | special |
| 07/30/2025 | Fire-Resistant Penetrations and Joints | DAN CHOI | special |
| 12/04/2024 | Tenant Protection Plan Compliance | DAN CHOI | special |
| 07/12/2023 | Fire-Resistance Rated Construction | ERIC BERLENT | progress |
| 07/12/2023 | Lighting controls | ERIC BERLENT | energy_progress |
| 07/12/2023 | Interior lighting power | ERIC BERLENT | energy_progress |
| 07/12/2023 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 06/07/2023 | Interior lighting power | ERIC BERLENT | energy_progress |
| 06/07/2023 | Fire-Resistance Rated Construction | ERIC BERLENT | progress |
| 06/07/2023 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 06/07/2023 | Lighting controls | ERIC BERLENT | energy_progress |
| 01/27/2023 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 01/27/2023 | Fire-Resistance Rated Construction | ERIC BERLENT | progress |