| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/30/2017 | $900K | — | — → — | $506/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GERALD CALIENDO ARCHITECTS | 2 | 05/11/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/20/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 12/20/2025 | Mechanical Systems | — | special |
| 12/20/2025 | Concrete - Cast-In-Place | — | special |
| 12/20/2025 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 12/20/2025 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 12/20/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 12/20/2025 | Masonry | — | special |
| 12/20/2025 | Subgrade Inspections | — | special |
| 12/20/2025 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 12/20/2025 | Final | — | progress |
| 12/20/2025 | Energy Code Compliance Inspections | — | progress |
| 12/20/2025 | Fire-Resistance Rated Construction | — | progress |
| 12/20/2025 | Air barrier — testing | — | energy_progress |
| 12/20/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 12/20/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 12/20/2025 | Permanent certificate | — | energy_progress |
| 12/20/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 12/20/2025 | Ventilation and air distribution system | — | energy_progress |
| 12/20/2025 | Exterior lighting power | — | energy_progress |
| 12/20/2025 | Fenestration areas | — | energy_progress |
| 12/20/2025 | Insulation placement and R values | — | energy_progress |
| 12/20/2025 | Protection of exposed foundation insulation | — | energy_progress |
| 12/20/2025 | Air barrier - visual inspection | — | energy_progress |
| 12/20/2025 | Maintenance information | — | energy_progress |
| 12/20/2025 | Duct leakage testing, insulation and design | — | energy_progress |