← Back
Two family converted from one family
144-46 177 STREET
QUEENS · BIN 4285182
💬 Discuss this project
1925Year Built
2.5Stories
B3Building Class
R3-2Zoning
1,278 sfGross Floor Area
2Units
8 Open Violations ▸FDNY Report ↗
Two family converted from one family · 2,500 sf lot · 0.51 FAR built · Flood zone X500
Locations of Work
Architecture
Floor 28p · 1 filing · 14 docs
Floor 18p · 1 filing · 14 docs
Cellar10p · 1 filing · 14 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASKON ARCHITECTS, P.C.504/22/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ASSURED BUILDERS INCGeneral Contractor203/21/2026
G.M.A. PLUMBING & HEATINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ASKON ARCHITECT, P.C.3596504/22/2024
Building Lifecycle
All (42)Filed (5)Permit Issued (2)Signed Off (1)Violation (9)Inspection (7)Objection (4)Special Inspection (14)
11/25/2025
Violation issued (HPD, open)
I
12/05/2024
Violation issued (HPD, open)
I
06/20/2024
Signed off — Alteration
FILING FOR PLUMBING WORK
Q00640435-I1
06/12/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/14/2024
Special inspection requirement — Air barrier - visual inspection
Akeeb Shekoni
05/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
05/14/2024
Special inspection requirement — Fenestration areas
Akeeb Shekoni
05/14/2024
Special inspection requirement — Insulation placement and R values
Akeeb Shekoni
05/14/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Akeeb Shekoni
05/14/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Akeeb Shekoni
05/04/2024
Objection resolved — Addressed
05/02/2024
Objection raised — Zoning
04/22/2024
Filed — Alteration CO
FILING FOR INTERIOR WORK TO CONVERT FROM ONE FAMILY TO TWO FAMILIES. NEW CERTIFICATE OF OCCUPANCY IS REQUIRED.
Q00611331-P1
02/14/2024
Special inspection requirement — Insulation placement and R values
Akeeb Shekoni
02/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
02/14/2024
Special inspection requirement — Air barrier - visual inspection
Akeeb Shekoni
02/14/2024
Special inspection requirement — Fenestration areas
Akeeb Shekoni
02/14/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Akeeb Shekoni
02/14/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Akeeb Shekoni
11/30/2023
Violation issued (HPD, open)
I
08/28/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
08/21/2023
Filed — Alteration
FILING FOR PLUMBING WORK
Q00640435-P2
06/27/2023
Filed — Alteration
FILING FOR PLUMBING WORK
Q00640435-P1
06/26/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/13/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
06/08/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/06/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/06/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/06/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/29/2022
Permit issued — Plumbing
Q00640435-I1-PL
11/18/2022
Violation issued (HPD, open)
I
11/18/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/07/2022
Permit issued — General Construction
Q00611331-I1-GC
03/17/2022
Violation issued (HPD, open)
I
12/13/2021
Objection raised — Zoning
12/13/2021
Objection resolved — Addressed
12/12/2021
Filed — Alteration
FILING FOR PLUMBING WORK
Q00640435-I1
10/23/2021
Filed — Alteration CO
FILING FOR INTERIOR WORK TO CONVERT FROM ONE FAMILY TO TWO FAMILIES. NEW CERTIFICATE OF OCCUPANCY IS REQUIRED.
Q00611331-I1
04/22/2021
Violation issued (HPD, open)
I
11/08/2019
Violation issued (HPD, open)
I
01/11/2018
Violation issued (HPD, open)
I
08/10/2001
Violation issued (ECB, closed)
Site Safety
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offG.M.A. PLUMBING & HEATING11/29/2022
DOB NOWGeneral ConstructionPermit IssuedASSURED BUILDERS INC10/07/2022
BISOTISSUEDSUNCO CAPITAL LLC03/14/2023
BISOTISSUEDGREEN STREET POWER PARTNE03/04/2016
2 projects · most recent 03/16/2023
General Wiring
FiledStatusContractorScope
03/16/2023CompleteBERGER QUALITY ELEC'L CON—
12/22/2022CompletePOWER SURGE ELECTRIC, INCGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
06/12/2024Pass-Final CND-Occupancy InspectionPassView ↗
06/26/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/08/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/06/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/06/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/06/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/18/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
05/14/2024Air barrier - visual inspectionAkeeb Shekonienergy_progress
05/14/2024Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
05/14/2024Fenestration areasAkeeb Shekonienergy_progress
05/14/2024Insulation placement and R valuesAkeeb Shekonienergy_progress
05/14/2024Fenestration and door U-factor and product ratingsAkeeb Shekonienergy_progress
05/14/2024HVAC-R and service water piping design and insulationAkeeb Shekonienergy_progress
02/14/2024Insulation placement and R valuesAkeeb Shekonienergy_progress
02/14/2024Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
02/14/2024Air barrier - visual inspectionAkeeb Shekonienergy_progress
02/14/2024Fenestration areasAkeeb Shekonienergy_progress
02/14/2024Fenestration and door U-factor and product ratingsAkeeb Shekonienergy_progress
02/14/2024HVAC-R and service water piping design and insulationAkeeb Shekonienergy_progress
08/28/2023Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
06/13/2023Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
▾Documents — 65 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/24/2026Q00640435-P2Request digital key ↗
08/24/2026Q00640435-P1Request digital key ↗
08/22/2026Q00611331-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
03/13/2023440772576Open ↗
02/10/2016440285362Open ↗
▸BISWORK PERMIT APPLICATION2
03/14/2023440772576Open ↗
03/04/2016440285362Open ↗
▸Seals & Professional Certifications16
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/22/2026Q00611331-P1Open ↗
08/22/2026Q00611331-I1Open ↗
08/13/2026Q00640435-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/26/2026Q00640435-P1Open ↗
08/26/2026Q00611331-I1Open ↗
08/24/2026Q00640435-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
03/13/2023440772576Open ↗
02/10/2016440285362Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026Q00611331-I1Open ↗
08/22/2026Q00611331-P1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/10/2016440285362Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
03/13/2023440772576Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/10/2016440285362Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist2
08/22/2026Q00611331-I1Open ↗
08/14/2026Q00611331-P1Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
03/14/2023440772576Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
02/10/2016440285362Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/22/2026Q00611331-I1Open ↗
08/14/2026Q00611331-P1Open ↗
08/13/2026Q00640435-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
03/13/2023440772576Open ↗
02/10/2016440285362Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
11/28/2023440772576Open ↗
03/14/2023440772576Open ↗
03/13/2023440772576Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
03/13/2023440772576Open ↗
02/10/2016440285362Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/28/2023440772576Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/22/2017440285362Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
02/10/2016440285362Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
05/22/2017440285362Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
11/28/2023440772576Open ↗
03/14/2023440772576Open ↗
03/13/2023440772576Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
11/29/2023440772576Open ↗
05/22/2017440285362Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
05/22/2017440285362Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT3
03/13/2023440772576Open ↗
05/22/2017440285362Open ↗
02/10/2016440285362Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
11/28/2023440772576Open ↗
▸Filing & Intake Forms3
▸BISEFILING JOB APPLICATION COVER SHEET2
03/13/2023440772576Open ↗
02/10/2016440285362Open ↗
▸BISADDITIONAL INFORMATION1
03/13/2023440772576Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification2
08/22/2026Q00611331-I1Open ↗
08/14/2026Q00611331-P1Open ↗
▸BISTax Abatement Miscellaneous1
11/29/2023440772576Open ↗