RoofUnder Construction3p · 5 filings · 20 docs
ArchitectureFire Protection
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
REPAIR OF EXTERIOR WALLS AND APPURTENANCES INCLUDING: BRICK AND TERRA COTTA MORTAR JOINTS, CRACKED TERRACOTTA AND STONE MASONRY, STONE SEALANT JOINTS, LINTEL REMOVAL, REPLACEMENT, AND/OR REPAIR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
Remove one (1) existing steel sprinkler tank (ST- 1) and Replace one (1) existing steel sprinkler tank with new (ST-2) on the roof level and cap/install new associated sprinkler piping on the 26th Floor as per plans. No change to use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
BulkheadUnder Construction1p · 1 filing · 15 docs
Equipment
Installation of suspended scaffold for facade work or inspection.
On file for this project
15 documents · 1 drawing sheet
Floor 251p · 1 filing · 2 docs
Architecture
No filed description on record for this project.
On file for this project
2 documents · 1 drawing sheet
Floor 24
Floor 23
Floor 22Under Construction7p · 2 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Sprinklers
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 4 drawing sheets
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
42 documents · 1 drawing sheet
Floor 21Under Construction18p · 4 filings · 19 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
Plumbing work as shown on plans.
On file for this project
3 documents · 1 drawing sheet
Filing for phone booth installs as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
General construction work as shown on plans.
On file for this project
4 documents · 3 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 203p · 2 filings · 6 docs
Fire ProtectionPlumbing
Plumbing work associated with new Commercial tenant (WeWork)
On file for this project
3 documents · 1 drawing sheet
Modification of existing sprinkler system associated with new Commercial tenant (WeWork)
On file for this project
3 documents · 2 drawing sheets
Floor 19Under Construction11p · 5 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modification of sprinkler system on the 19th floor - phase 2
On file for this project
19 documents · 7 drawing sheets
Sprinkler work for cafe space as shown on plans filed herewith. No change to use egress or occupancy.
On file for this project
17 documents · 6 drawing sheets
Modifications to the existing sprinkler system on the 23rd floor as per plans. No change to use, egress occupancy.
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 185p · 3 filings · 9 docs
ArchitectureFire ProtectionPlumbing
General construction as shown on plans.
On file for this project
3 documents · 2 drawing sheets
Plumbing work associated with new Commercial tenant (WeWork)
On file for this project
3 documents · 1 drawing sheet
Modification of existing sprinkler system associated with new Commercial tenant (WeWork)
On file for this project
3 documents · 2 drawing sheets
Floor 174p · 3 filings · 19 docs
ArchitectureFire ProtectionPlumbing
Filing for phone booth installs as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
Plumbing work as shown on plans.
On file for this project
6 documents · 1 drawing sheet
Modification to an existing sprinkler system.
On file for this project
7 documents · 2 drawing sheets
Floor 164p · 3 filings · 19 docs
ArchitectureFire ProtectionPlumbing
Filing for phone booth installs as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
Plumbing work as shown on plans.
On file for this project
6 documents · 1 drawing sheet
Modification to an existing sprinkler system.
On file for this project
7 documents · 2 drawing sheets
Floor 153p · 2 filings · 13 docs
Fire ProtectionPlumbing
Plumbing work as shown on plans.
On file for this project
6 documents · 1 drawing sheet
Modification to an existing sprinkler system.
On file for this project
7 documents · 2 drawing sheets
Floor 146p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Filing for phone booth installs as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
Plumbing work as shown on plans.
On file for this project
6 documents · 1 drawing sheet
Mechanical work as shown on plans.
On file for this project
12 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 13Under Construction8p · 3 filings · 20 docs
DMFire ProtectionGeneralPlumbing
Issued Permit Scope
Sprinklers
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 2 drawing sheets
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
42 documents · 2 drawing sheets
No filed description on record for this project.
On file for this project
4 documents · 2 drawing sheets
Floor 128p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Plumbing work as shown on plans.
On file for this project
6 documents · 3 drawing sheets
Additions/modifications to an existing sprinkler system.
On file for this project
7 documents · 2 drawing sheets
Mechanical work as shown on plans.
On file for this project
30 documents · 3 drawing sheets
Floor 116p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Plumbing work as shown on plans.
On file for this project
6 documents · 2 drawing sheets
Additions/modifications to an existing sprinkler system.
On file for this project
7 documents · 2 drawing sheets
Mechanical work as shown on plans.
On file for this project
30 documents · 2 drawing sheets
Floor 10Under Construction7p · 2 filings · 20 docs
DMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Sprinklers
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 2 drawing sheets
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
42 documents · 3 drawing sheets
Floor 93p · 2 filings · 20 docs
DMPlumbing
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 2 drawing sheets
Sprinkler as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
14 documents · 1 drawing sheet
Floor 84p · 2 filings · 20 docs
DMMechanicalPlumbing
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 3 drawing sheets
Sprinkler as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
14 documents · 1 drawing sheet
Floor 74p · 2 filings · 20 docs
ArchitectureDMPlumbing
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 3 drawing sheets
Sprinkler as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
14 documents · 1 drawing sheet
Floor 64p · 2 filings · 20 docs
ArchitectureDMPlumbing
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 3 drawing sheets
Sprinkler as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
14 documents · 1 drawing sheet
Floor 5Under Construction5p · 2 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Sprinklers
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
27 documents · 1 drawing sheet
Sprinkler work as shown on plans filed herewith. No change to use, egress or occupancy.
On file for this project
42 documents · 2 drawing sheets
Floor 4
Floor 31p · 1 filing · 12 docs
Architecture
General construction work to include interior renovation as shown on plans.
On file for this project
12 documents · 1 drawing sheet
Floor 250p · 10 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Interior renovation of existing Retail store 'CVS'. No change to use, egress or occupancy.
On file for this project
6 documents · 7 drawing sheets
Modification to the existing Sprinkler system. INSTALL OF (1) NEW SP HEAD ON THE BAS LEVEL, (7) SP HEADS TO BE REMOVED, (6) TO BE INSTALLED ON THE 1ST FL. (24) SP HEADS TO BE REMOVED, (21) TO BE INSTALLED ON 2ND FL. No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modification to an existing sprinkler system.
On file for this project
7 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 119p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Modification to the existing Sprinkler system. INSTALL OF (1) NEW SP HEAD ON THE BAS LEVEL, (7) SP HEADS TO BE REMOVED, (6) TO BE INSTALLED ON THE 1ST FL. (24) SP HEADS TO BE REMOVED, (21) TO BE INSTALLED ON 2ND FL. No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modification to an existing sprinkler system.
On file for this project
7 documents · 1 drawing sheet
Removal of existing of plumbing fixtures and associated piping as per plans.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Cellar1p · 1 filing · 11 docs
Fire Protection
Modifications to the existing sprinkler system as per plans. No change to use, egress or occupancy.
On file for this project
11 documents · 1 drawing sheet
Sub-Cellar1p · 1 filing · 4 docs
Structural
Conversion of Preaction Sprinkler to Wet Sprinkler System. No change in use, egress, or occupancy.
On file for this project
4 documents · 1 drawing sheet
Sub-Basement14p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Modification to the existing Sprinkler system. INSTALL OF (1) NEW SP HEAD ON THE BAS LEVEL, (7) SP HEADS TO BE REMOVED, (6) TO BE INSTALLED ON THE 1ST FL. (24) SP HEADS TO BE REMOVED, (21) TO BE INSTALLED ON 2ND FL. No change to use, egress or occupancy.
On file for this project
6 documents
Removal of existing of plumbing fixtures and associated piping as per plans.
On file for this project
4 documents
Modification to the existing HVAC system on the bas, 1, 2 floors as per plans. No change to use and egress or occupancy.
On file for this project
11 documents