← Back
Three families
1442 HERKIMER STREET
BROOKLYN · Ocean Hill · BIN 3042764
💬 Discuss this project
1925Year Built
3Stories
C0Building Class
R6BZoning
2,799 sfGross Floor Area
3Units
Rent Stabilized17 Open Violations ▸FDNY Report ↗
Three families · 1,927 sf lot · 1.45 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof2p · 2 filings · 20 docs
Basement1p · 1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC201/16/2026
TOM PETERSEN ARCHITECT, LLC110/07/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S R SOLAR DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYS ESSENTIAL POWER INCGeneral Contractor303/21/2026
EGBERT BAPTISTEElectrical103/21/2026
SOLAR ONE INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244201/16/2026
THOMAS PETERSEN ARCHITECT7854110/07/2024
Building Lifecycle
All (47)Filed (3)Permit Issued (2)Signed Off (1)Violation (26)Objection (2)Special Inspection (13)
05/04/2026
Violation issued (HPD, open)
A
02/26/2026
Signed off — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
B01156582-I1
02/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
02/09/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
02/09/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
02/09/2026
Special inspection requirement — Final
NARESH MAHANGU
01/16/2026
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
B01156582-P1
12/31/2025
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
12/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
12/31/2025
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
12/31/2025
Special inspection requirement — Final
NARESH MAHANGU
11/20/2025
Violation issued (HPD, open)
I
06/09/2025
Violation issued (HPD, open)
A
04/15/2025
Permit issued — Solar
B01156582-I1-SL
03/11/2025
Objection resolved — Addressed
03/04/2025
Objection raised — Other
02/28/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
B01156582-I1
11/29/2024
Violation issued (HPD, open)
I
10/15/2024
Permit issued — Solar
B01122722-I1-SL
10/07/2024
Filed — Alteration
Installation of PV System on existing rooftop. No changes to Egress or use of occupancy.
B01122722-I1
10/07/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
10/07/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
10/07/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
10/07/2024
Special inspection requirement — Final
TOM PETERSEN
10/07/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
08/23/2024
Violation issued (HPD, open)
B
08/23/2024
Violation issued (HPD, closed)
C
08/23/2024
Violation issued (HPD, open)
C
08/23/2024
Violation issued (HPD, open)
A
08/23/2024
Violation issued (HPD, open)
A
08/23/2024
Violation issued (HPD, open)
B
08/23/2024
Violation issued (HPD, open)
A
08/23/2024
Violation issued (HPD, open)
A
08/23/2024
Violation issued (HPD, open)
C
08/23/2024
Violation issued (HPD, open)
A
08/23/2024
Violation issued (HPD, open)
C
04/10/2024
Violation issued (HPD, open)
A
01/31/2024
Violation issued (HPD, open)
C
03/23/2023
Violation issued (HPD, closed)
A
11/14/2022
Violation issued (HPD, closed)
I
02/25/2022
Violation issued (HPD, closed)
I
02/25/2022
Violation issued (HPD, closed)
A
04/09/2021
Violation issued (HPD, closed)
A
10/18/2018
Violation issued (HPD, closed)
I
11/09/2016
Violation issued (HPD, closed)
I
02/20/2015
Violation issued (HPD, closed)
I
11/22/2006
Violation issued (HPD, open)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR ONE INC04/15/2025
DOB NOWSolarPermit IssuedNYS ESSENTIAL POWER INC10/15/2024
BISPLISSUEDLLOYD G DRUMMOND PLBG&GEN03/04/2005
2 projects · most recent 02/25/2025
FiledStatusContractorScope
02/25/2025CompleteNEWGRANGE ELECTRIC, INC—
09/16/2024Permit IssuedJD ELECTRICAL ENTERPRISES—
1 project · most recent 10/07/2024
FiledStatusContractorScope
10/07/2024Permit IssuedNYS ESSENTIAL POWER INC8 panels, 3.4 kw, 860 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
02/09/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
02/09/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
02/09/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
02/09/2026FinalNARESH MAHANGUprogress
12/31/2025Air barrier - visual inspectionNARESH MAHANGUenergy_progress
12/31/2025Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
12/31/2025Energy Code Compliance InspectionsNARESH MAHANGUprogress
12/31/2025FinalNARESH MAHANGUprogress
10/07/2024Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
10/07/2024Fire-Resistant Penetrations and JointsTOM PETERSENspecial
10/07/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
10/07/2024FinalTOM PETERSENprogress
10/07/2024Energy Code Compliance InspectionsTOM PETERSENprogress
▾Documents — 21 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/23/2026B01122722-I1Request digital key ↗
08/22/2026B01156582-I1Request digital key ↗
08/22/2026B01156582-P1Request digital key ↗
▸Seals & Professional Certifications14
▸DOB NOWProgress Inspector Seal & Signature7
08/27/2026B01156582-P1Open ↗
08/27/2026B01156582-P1Open ↗
08/26/2026B01156582-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/27/2026B01156582-P1Open ↗
08/26/2026B01156582-I1Open ↗
08/23/2026B01122722-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/23/2026B01122722-I1Open ↗
08/22/2026B01156582-I1Open ↗
08/22/2026B01156582-P1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/23/2026B01122722-I1Open ↗
08/22/2026B01156582-P1Open ↗
08/22/2026B01156582-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01156582-I1Open ↗