RoofUnder Construction87p · 7 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Sidewalk Shed · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new plumbing system: Install new plumbing fixtures and associated piping on the Cellar, 1-38th Floor & Roof (CO)/ Cellar, 1, 3-21, M1, Club1, Club2, 26-35, PH1, PH2A, PH2B, M2, M3, M4, RF1 (Marketing Floors) as per plans.
On file for this project
19 documents · 3 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 39Under Construction33p · 1 filing · 3 docs
Mechanical
Issued Permit Scope
Mechanical Systems
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Floor 38Under Construction121p · 7 filings · 20 docs
ArchitectureCivilElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
INSTALLATION OF A TEMPORARY HOIST COMPLEX AS PER PLANS DURING NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. HOIST COMPLEX INSTALLED IN ACCORDANCE WITH 2022 NYC BUILDING CODE, CHAPTER 33
On file for this project
6 documents · 2 drawing sheets
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Latest 3 of 7 filings on this floor.
Floor 37Under Construction126p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
Installation of three (3) new condensing boilers and associated pumps and suction diffusers on the 37th Floor (CO)/ M3 (Mktg) and install drain, flow bypass valve, differential pressure sensor and future boiler connections on the Cellar as per plans.
On file for this project
9 documents · 1 drawing sheet
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 36Under Construction120p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
Floor 35Under Construction121p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
Floor 34Under Construction121p · 6 filings · 20 docs
EquipmentFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 33Under Construction119p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 32Under Construction119p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 31Under Construction119p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
Floor 30Under Construction118p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 29Under Construction118p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
Floor 28Under Construction118p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 27Under Construction118p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 26Under Construction118p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 25Under Construction118p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 1 drawing sheet
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Latest 3 of 6 filings on this floor.
Floor 24Under Construction118p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 1 drawing sheet
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Latest 3 of 6 filings on this floor.
Floor 23Under Construction118p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Latest 3 of 6 filings on this floor.
Floor 22Under Construction121p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 1 drawing sheet
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 21Under Construction120p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 1 drawing sheet
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Latest 3 of 7 filings on this floor.
Floor 20Under Construction122p · 8 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 8 filings on this floor.
Floor 19Under Construction120p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 18Under Construction120p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 17Under Construction120p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 16Under Construction122p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 15Under Construction122p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 3 drawing sheets
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 14Under Construction120p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 13Under Construction119p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 12Under Construction120p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 11Under Construction119p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Installation of new HVAC System throughout the building: Install new ductwork, intake air louvers, exhaust fans, Cooling tower, AC and Condensing Units, ductwork and pipe connections, refrigerant piping risers, DOAS, electric heaters, VAVs as per plans.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 10Under Construction119p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 9Under Construction121p · 6 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 8Under Construction124p · 8 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sidewalk Shed · Sprinklers · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY SYSTEM STAIRS TOWER AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SYSTEM STAIRS TOWER FROM THE FIRST FLOOR TO THE EIGHTH FLOOR AT EAST 82ND STREET ELEVATION
On file for this project
36 documents
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Latest 3 of 8 filings on this floor.
Floor 7Under Construction122p · 7 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 6Under Construction124p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Herewith filing Superstructure application filed in conjunction with New Building # M00995463-I1
On file for this project
12 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 5Under Construction266p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 3 drawing sheets
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Latest 3 of 7 filings on this floor.
Floor 4Under Construction267p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 2 drawing sheets
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Latest 3 of 7 filings on this floor.
Floor 3Under Construction266p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 1 drawing sheet
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Latest 3 of 7 filings on this floor.
Floor 2Under Construction267p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 3 drawing sheets
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Latest 3 of 7 filings on this floor.
Floor 1Under Construction269p · 10 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sidewalk Shed · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT E 82ND STREET AND 3RD AVENUE ELEVATIONS. THE SIDEWALK SHED AT 2ND FLOOR ROOF, AT 170 E 83RD STREET AND BALCONY OF 167 E 82 STREET
On file for this project
12 documents
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Latest 3 of 8 filings on this floor.
CellarUnder Construction241p · 9 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingOther
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
Installation of three (3) new condensing boilers and associated pumps and suction diffusers on the 37th Floor (CO)/ M3 (Mktg) and install drain, flow bypass valve, differential pressure sensor and future boiler connections on the Cellar as per plans.
On file for this project
9 documents · 2 drawing sheets
HEREWITH FILING SUPPORT OF EXCAVATION WORK IN CONJUNCTION WITH NEW BUILDING.
On file for this project
113 documents · 4 drawing sheets
TEMPORARY STANDPIPE INSTALLATION, ALL AS PER PLAN AND REFERENCE TO PERMANENT STANDPIPE UNDER M01030152.
On file for this project
2 documents
Latest 3 of 8 filings on this floor.