Two family converted from one family
145-17 105 AVENUE
QUEENS · Jamaica · BIN 4214851
💬 Discuss this project
1910Year Built
2Stories
B3Building Class
R4-1Zoning
1,872 sfGross Floor Area
2Units
28 Open Violations ▸FDNY Report ↗
Two family converted from one family · 2,500 sf lot · 0.75 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Cellar16p · 2 filings · 20 docs
Site & exterior12p · 1 filing · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
INTEROFFICE603/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/08/2020$557K—Private party → DEBNATH, LLC$298/sf building
08/12/2016$254K—— → —$136/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CHANDA ENGINEERING CONSULTANT PC410/14/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DNS FINE BUILDERS INCGeneral Contractor203/21/2026
ALL PRO PLBG & HTG INCPlumbing207/08/2026
RONALD STEWARTElectrical103/21/2026
STEWART RONALDElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CHANDA ENG. CONSULTANT PC6842410/14/2024
Building Lifecycle
All (76)Filed (4)Permit Issued (3)Signed Off (2)Violation (38)Inspection (11)Objection (12)Special Inspection (6)
11/19/2024
Signed off — Alteration
REMOVE PARTITION WALLS, ILLEGAL KITCHEN ENCLOSURE, PIPING AND SEWER PIPING FROM CELLAR. INSTALL SHOWER & CONVERT EXISTING TWO TO THREE FIXTURE BATHROOM AT CELLAR. INSTALL LAUNDRY WASHER, DRYER & SINK IN CELLAR. GAS TEST FOR 1ST FLOOR METER ONLY.
Q00455680-S1
10/28/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
10/14/2024
Filed — Alteration
REMOVE PARTITION WALLS, ILLEGAL KITCHEN ENCLOSURE, PIPING AND SEWER PIPING FROM CELLAR. INSTALL SHOWER & CONVERT EXISTING TWO TO THREE FIXTURE BATHROOM AT CELLAR. INSTALL LAUNDRY WASHER, DRYER & SINK IN CELLAR. GAS TEST FOR 1ST FLOOR METER ONLY.
Q00455680-P1
09/08/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
08/30/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/21/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/19/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/19/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/15/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/17/2024
Permit issued — Plumbing
Q00455680-S1-PL
04/20/2024
Objection resolved — Addressed
04/20/2024
Objection resolved — Addressed
04/20/2024
Objection resolved — Addressed
04/01/2024
Objection resolved — Addressed
04/01/2024
Objection resolved — Addressed
03/26/2024
Objection raised — Mechanical
03/26/2024
Objection raised — Scope
03/26/2024
Objection raised — Admin
03/26/2024
Objection raised — Scope
03/26/2024
Objection raised — Scope
03/14/2024
Filed — Alteration
REMOVE PARTITION WALLS, ILLEGAL KITCHEN ENCLOSURE, PIPING AND SEWER PIPING FROM CELLAR. INSTALL SHOWER & CONVERT EXISTING TWO TO THREE FIXTURE BATHROOM AT CELLAR. INSTALL LAUNDRY WASHER, DRYER & SINK IN CELLAR. GAS TEST FOR 1ST FLOOR METER ONLY.
Q00455680-S1
01/10/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/10/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/05/2024
Inspection — Fail-Final PL - Underground
Fail
View inspection ↗
12/21/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/30/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/22/2022
Signed off — Alteration
Q00453849-I1
02/17/2022
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/10/2022
Permit issued — Plumbing
Q00455680-I1-PL
10/06/2021
Permit issued — General Construction
Q00453849-I1-GC
02/04/2021
Objection raised — Scope
02/04/2021
Objection resolved — Addressed
01/18/2021
Filed — Alteration
Q00453849-I1
01/18/2021
Filed — Alteration
REMOVE PARTITION WALLS, ILLEGAL KITCHEN ENCLOSURE, PIPING AND SEWER PIPING FROM CELLAR. INSTALL SHOWER & CONVERT EXISTING TWO TO THREE FIXTURE BATHROOM AT CELLAR. INSTALL LAUNDRY WASHER, DRYER & SINK IN CELLAR. GAS TEST FOR 1ST FLOOR METER ONLY.
Q00455680-I1
01/18/2021
Special inspection requirement — Interior lighting power
KARTIK CHANDA
01/18/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
01/13/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
01/13/2021
Special inspection requirement — Fire-Resistance Rated Construction
KARTIK CHANDA
03/13/2018
Violation issued (HPD, open)
I
03/09/2018
Violation issued (HPD, closed)
C
03/09/2018
Violation issued (HPD, closed)
C
08/29/2014
Violation issued (ECB, closed)
Plumbing
06/12/2014
Violation issued (HPD, open)
B
06/12/2014
Violation issued (HPD, open)
B
06/12/2014
Violation issued (HPD, open)
A
06/12/2014
Violation issued (HPD, open)
A
06/12/2014
Violation issued (HPD, open)
A
06/12/2014
Violation issued (HPD, open)
A
06/12/2014
Violation issued (HPD, open)
B
06/12/2014
Violation issued (HPD, open)
B
06/12/2014
Violation issued (HPD, open)
A
06/12/2014
Violation issued (HPD, open)
B
06/12/2014
Violation issued (HPD, open)
A
06/12/2014
Violation issued (HPD, open)
B
09/11/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/28/2013
Violation issued (ECB, closed)
Construction
08/14/2013
Violation issued (ECB, closed)
Construction
08/11/2013
Violation issued (HPD, open)
B
08/11/2013
Violation issued (HPD, open)
B
08/11/2013
Violation issued (HPD, open)
B
Latest 60 of 76 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offALL PRO PLBG & HTG INC06/17/2024
DOB NOWPlumbingPermit IssuedALL PRO PLBG & HTG INC02/10/2022
DOB NOWGeneral ConstructionSigned-offDNS FINE BUILDERS INC10/06/2021
BISPLISSUEDJOE TRUCE PLG INC12/20/2001
BIS—ISSUEDPRESIDEN INC.11/15/2001
1 project · most recent 10/14/2024
Gas Water/Sanitary
FiledStatusContractorScope
10/14/2024Signed-offALL PRO PLBG & HTG INCGas, Water/Sanitary
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
08/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/21/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/19/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/19/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/15/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/10/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/10/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/05/2024Fail-Final PL - UndergroundFailView ↗
12/21/2022Pass-Final CND-Occupancy InspectionPassView ↗
03/30/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/17/2022Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
10/28/2024Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
09/08/2024Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
01/18/2021Interior lighting powerKARTIK CHANDAenergy_progress
01/18/2021Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
01/13/2021Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
01/13/2021Fire-Resistance Rated ConstructionKARTIK CHANDAprogress
▾Documents — 22 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch2
08/21/2026Q00455680-P1Request digital key ↗
08/21/2026Q00455680-S1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing Legalization1
08/15/2026Q00455680-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/27/2026Q00453849-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWRestrictive Declaration/Easement 13
08/13/2026Q00455680-P1Open ↗
08/13/2026Q00455680-S1Open ↗
08/13/2026Q00455680-I1Open ↗
▸Seals & Professional Certifications10
▸DOB NOWSpecial Inspector Seal & Signature4
08/31/2026Q00455680-P1Open ↗
08/28/2026Q00455680-I1Open ↗
08/25/2026Q00455680-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026Q00453849-I1Open ↗
08/13/2026Q00455680-I1Open ↗
08/13/2026Q00455680-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/25/2026Q00453849-I1Open ↗
08/25/2026Q00453849-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/27/2026Q00453849-I1Open ↗
08/13/2026Q00455680-I1Open ↗
08/13/2026Q00455680-S1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00453849-I1Open ↗