| Owner | Filings | Most Recent |
|---|---|---|
| NY ISLAND BUILDERS INC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/08/2024 | $550K | — | Private party → Private party | $470/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TABRIZ DESIGN GROUP | 2 | 03/26/2025 |
| TABRIZ GROUP ENTERPRISES | 1 | 02/28/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| TABRIZ GROUP ENTERPRISE | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NY ISLAND BUILDERS INC | General Contractor | 3 | 07/08/2026 |
| M & M PIPING AND HEATING | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TABRIZ GROUP ENTERPRISES | 3275 | 2 | 03/26/2025 |
| TRIANGLE INSPECTION & TES | 7495 | 1 | 03/26/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | NY ISLAND BUILDERS INC | 04/13/2026 |
| DOB NOW | Plumbing | Permit Issued | M & M PIPING AND HEATING | 12/19/2025 |
| DOB NOW | Foundation | Permit Issued | NY ISLAND BUILDERS INC | 05/27/2025 |
| DOB NOW | Construction Fence | Signed-off | NY ISLAND BUILDERS INC | 04/25/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/26/2025 | Permit Issued | M & M PIPING AND HEATING | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2025 | Complete | AYYUB ELECTRIC CORP | — |
| 11/06/2025 | Complete | AYYUB ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/28/2025 | Permit Issued | NY ISLAND BUILDERS INC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/26/2025 | Signed-off | NY ISLAND BUILDERS INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/28/2025 | Air barrier — testing | BAKHTIAR SHAMLOO | energy_progress |
| 03/26/2025 | Fire-Resistant Penetrations and Joints | BAKHTIAR SHAMLOO | special |
| 03/26/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 03/26/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | BAKHTIAR SHAMLOO | special |
| 02/27/2025 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 02/27/2025 | Energy Code Compliance Inspections | BAKHTIAR SHAMLOO | progress |
| 02/27/2025 | Fire-Resistance Rated Construction | BAKHTIAR SHAMLOO | progress |
| 02/27/2025 | Fenestration air leakage | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Fenestration areas | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Concrete - Cast-In-Place | BAKHTIAR SHAMLOO | special |
| 02/27/2025 | Insulation placement and R values | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Air barrier - visual inspection | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Maintenance information | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Fenestration and door U-factor and product ratings | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Metering | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Electric vehicle service equipment requirements | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Permanent certificate | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Interior lighting power | BAKHTIAR SHAMLOO | energy_progress |
| 02/27/2025 | Excavations - Sheeting, Shoring, and Bracing | BAKHTIAR SHAMLOO | special |
| 02/27/2025 | Fire-Resistant Penetrations and Joints | BAKHTIAR SHAMLOO | special |
| 02/27/2025 | Masonry | BAKHTIAR SHAMLOO | special |
| 02/22/2025 | Footing and Foundation | BAKHTIAR SHAMLOO | progress |
| 02/22/2025 | Final | HARI SONI | progress |
| 02/22/2025 | Structural Stability – Alterations of existing buildings | BAKHTIAR SHAMLOO | special |