| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/05/2024 | $2.2M | — | — → — | $570/sf building |
| 01/28/2022 | $1.1M | — | Private party → ATLANTIC AUTO SHOW LLC | $280/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SELF EMPLOYED | 3 | 02/19/2024 |
| IMA ENGINEERING, PC | 7 | 10/17/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| IMA ENGINEERING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MASTORAS BUILDERS LLC | General Contractor | 32 | 07/08/2026 |
| GO SOLAR/GREEN NY LLC | General Contractor | 3 | 03/21/2026 |
| POWER SURGE ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 5 | 02/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | GO SOLAR/GREEN NY LLC | 03/07/2024 |
| DOB NOW | Construction Fence | Signed-off | MASTORAS BUILDERS LLC | 02/02/2023 |
| DOB NOW | Structural | Signed-off | MASTORAS BUILDERS LLC | 01/27/2023 |
| DOB NOW | Foundation | Permit Issued | MASTORAS BUILDERS LLC | 01/27/2023 |
| DOB NOW | Earth Work | Signed-off | MASTORAS BUILDERS LLC | 01/27/2023 |
| DOB NOW | Earth Work | Signed-off | MASTORAS BUILDERS LLC | 01/27/2023 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 01/10/2023 |
| DOB NOW | Foundation | Signed-off | MASTORAS BUILDERS LLC | 12/22/2022 |
| DOB NOW | Earth Work | Signed-off | MASTORAS BUILDERS LLC | 12/22/2022 |
| DOB NOW | Earth Work | Signed-off | MASTORAS BUILDERS LLC | 12/22/2022 |
| DOB NOW | Earth Work | Permit Issued | MASTORAS BUILDERS LLC | 12/22/2022 |
| DOB NOW | Foundation | Signed-off | MASTORAS BUILDERS LLC | 09/19/2022 |
| DOB NOW | Support of Excavation | Signed-off | MASTORAS BUILDERS LLC | 09/02/2022 |
| DOB NOW | Construction Fence | Signed-off | MASTORAS BUILDERS LLC | 08/05/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/06/2024 | Complete | JOE ELECTRICAL INC | — |
| 08/17/2023 | Complete | POWER SURGE ELECTRIC, INC | General Wiring |
| 08/19/2022 | Complete | POWER SURGE ELECTRIC, INC | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2023 | Signed-off | MASTORAS BUILDERS LLC | Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/29/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/17/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/27/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/26/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/15/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/20/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/20/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/20/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/12/2024 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 02/12/2024 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 02/12/2024 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 02/12/2024 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 02/12/2024 | Final | NAVEEN KUMAR | progress |
| 04/28/2023 | Interior lighting power | Younes Abouyaala | energy_progress |
| 04/28/2023 | Fenestration and door U-factor and product ratings | Younes Abouyaala | energy_progress |
| 04/28/2023 | Protection of exposed foundation insulation | Younes Abouyaala | energy_progress |
| 04/28/2023 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 04/28/2023 | Exterior Insulation and Finish Systems (EIFS) | Younes Abouyaala | special |
| 04/28/2023 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 04/28/2023 | Subgrade Inspections | Younes Abouyaala | special |
| 04/28/2023 | Wood – Prefabricated I-Joists | Younes Abouyaala | special |
| 04/28/2023 | Final | NAVEEN KUMAR | progress |
| 04/28/2023 | Footing and Foundation | Younes Abouyaala | progress |
| 04/28/2023 | Structural Wood Frame | Younes Abouyaala | progress |
| 04/28/2023 | Permanent certificate | Younes Abouyaala | energy_progress |
| 04/28/2023 | Metering | Younes Abouyaala | energy_progress |
| 04/28/2023 | Maintenance information | Younes Abouyaala | energy_progress |
| 04/28/2023 | Fenestration air leakage | Younes Abouyaala | energy_progress |
| 04/28/2023 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 04/28/2023 | Electric vehicle service equipment requirements | Younes Abouyaala | energy_progress |
| 04/28/2023 | Air barrier — testing | Younes Abouyaala | energy_progress |
| 04/28/2023 | Insulation placement and R values | Younes Abouyaala | energy_progress |
| 08/31/2022 | Footing and Foundation | Younes Abouyaala | progress |