| Owner | Filings | Most Recent |
|---|---|---|
| A4533 ARLINGTON | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/20/2017 | $750K | — | — → — | $311/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ASKON ARCHITECTS, P.C. | 4 | 08/10/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BANUMA CONSTRUCTION LLC | General Contractor | 2 | 08/16/2026 |
| CARLIN CONTRACTING OF NY | General Contractor | 2 | 07/08/2026 |
| INAAM BACCHUS | Electrical | 1 | 03/21/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 1 | 07/30/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SJS INSPECTIONS AND CONSU | 8286 | 2 | 08/10/2026 |
| ASKON ARCHITECT, P.C. | 3596 | 1 | 04/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | BANUMA CONSTRUCTION LLC | 08/25/2026 |
| DOB NOW | Plumbing | Permit Issued | JOHN FITZGERALD PLBG &HTG | 07/29/2026 |
| DOB NOW | Earth Work | Permit Issued | BANUMA CONSTRUCTION LLC | 04/22/2026 |
| DOB NOW | Construction Fence | Permit Issued | CARLIN CONTRACTING OF NY | 11/06/2025 |
| DOB NOW | Earth Work | Permit Issued | CARLIN CONTRACTING OF NY | 10/01/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | Permit Issued | JOHN FITZGERALD PLBG &HTG | Plumbing-Sprinkler, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/19/2025 | Permit Issued | AYYUB ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/28/2026 | Fire-Resistant Penetrations and Joints | SERGEY BOLOTOV | special |
| 08/28/2026 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 08/28/2026 | Maintenance information | Akeeb Shekoni | energy_progress |
| 08/28/2026 | HVAC-R and service water piping design and insulation | Akeeb Shekoni | energy_progress |
| 08/06/2026 | Maintenance information | Akeeb Shekoni | energy_progress |
| 08/06/2026 | Fire-Resistant Penetrations and Joints | SERGEY BOLOTOV | special |
| 08/06/2026 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 08/06/2026 | HVAC-R and service water piping design and insulation | Akeeb Shekoni | energy_progress |
| 05/10/2025 | Interior lighting power | Akeeb Shekoni | energy_progress |
| 05/10/2025 | Maintenance information | Akeeb Shekoni | energy_progress |
| 04/09/2025 | Excavations - Sheeting, Shoring, and Bracing | Akeeb Shekoni | special |
| 04/09/2025 | Metering | Akeeb Shekoni | energy_progress |
| 04/09/2025 | Concrete - Cast-In-Place | Akeeb Shekoni | special |
| 04/09/2025 | Subgrade Inspections | Akeeb Shekoni | special |
| 04/07/2025 | Air barrier - visual inspection | Akeeb Shekoni | energy_progress |
| 04/07/2025 | Fenestration air leakage | Akeeb Shekoni | energy_progress |
| 04/07/2025 | Fenestration and door U-factor and product ratings | Akeeb Shekoni | energy_progress |
| 04/07/2025 | Fenestration areas | Akeeb Shekoni | energy_progress |
| 04/07/2025 | Permanent certificate | Akeeb Shekoni | energy_progress |
| 04/07/2025 | Air barrier — testing | Akeeb Shekoni | energy_progress |
| 04/07/2025 | Insulation placement and R values | Akeeb Shekoni | energy_progress |
| 04/06/2025 | Designated Seismic System | Akeeb Shekoni | special |
| 04/06/2025 | Masonry | Akeeb Shekoni | special |
| 03/10/2025 | Final | HANSA PERSAUD | progress |
| 03/10/2025 | Footing and Foundation | Akeeb Shekoni | progress |