| Owner | Filings | Most Recent |
|---|---|---|
| GR BUILDERS | 11 | 09/13/2026 |
| VARG CONSTRUCTION | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/21/2024 | $405K | — | — → — | $311/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TOM PETERSEN ARCHITECT, LLC | 1 | 08/17/2026 |
| TABRIZ DESIGN GROUP | 3 | 12/12/2025 |
| TABRIZ GROUP ENTERPRISES | 1 | 09/29/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J&J DESIGNS INC | General Contractor | 3 | 07/10/2026 |
| AYYUB ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| VOLTAIC SOLAIRE LLC | General Contractor | 1 | 08/25/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| THOMAS PETERSEN ARCHITECT | 7854 | 1 | 08/17/2026 |
| TABRIZ GROUP ENTERPRISES | 3275 | 3 | 12/12/2025 |
| TRIANGLE INSPECTION & TES | 7495 | 1 | 12/12/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | VOLTAIC SOLAIRE LLC | 08/24/2026 |
| DOB NOW | Structural | Permit Issued | J&J DESIGNS INC | 07/08/2026 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 12/19/2025 |
| DOB NOW | General Construction | Permit Issued | J&J DESIGNS INC | 11/14/2025 |
| DOB NOW | Construction Fence | Signed-off | J&J DESIGNS INC | 10/03/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2026 | Permit Issued | BERGER QUALITY ELEC'L CON | — |
| 06/17/2026 | Complete | AYYUB ELECTRIC CORP | General Wiring |
| 11/30/2025 | Complete | AYYUB ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2025 | Permit Issued | J&J DESIGNS INC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2026 | Permit Issued | VOLTAIC SOLAIRE LLC | 26 panels, 11.44 kw, 2,488 roof_area_sqft |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/22/2025 | Signed-off | J&J DESIGNS INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/24/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/24/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2026 | Fire-Resistant Penetrations and Joints | TOM PETERSEN | special |
| 08/07/2026 | Final | TOM PETERSEN | progress |
| 08/07/2026 | Structural Stability – Alterations of existing buildings | TOM PETERSEN | special |
| 08/07/2026 | Air barrier - visual inspection | TOM PETERSEN | energy_progress |
| 08/07/2026 | Energy Code Compliance Inspections | TOM PETERSEN | progress |
| 12/12/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | BAKHTIAR SHAMLOO | special |
| 12/12/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 09/29/2025 | Energy Code Compliance Inspections | BAKHTIAR SHAMLOO | progress |
| 09/29/2025 | Fire-Resistance Rated Construction | BAKHTIAR SHAMLOO | progress |
| 09/29/2025 | Structural Wood Frame | BAKHTIAR SHAMLOO | progress |
| 09/29/2025 | Permanent certificate | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 09/29/2025 | Structural Stability – Alterations of existing buildings | BAKHTIAR SHAMLOO | special |
| 09/29/2025 | Concrete - Cast-In-Place | BAKHTIAR SHAMLOO | special |
| 09/29/2025 | Excavations - Sheeting, Shoring, and Bracing | BAKHTIAR SHAMLOO | special |
| 09/29/2025 | Fire-Resistant Penetrations and Joints | BAKHTIAR SHAMLOO | special |
| 09/29/2025 | Masonry | BAKHTIAR SHAMLOO | special |
| 09/29/2025 | Insulation placement and R values | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Interior lighting power | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Air barrier — testing | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Air barrier - visual inspection | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Electric vehicle service equipment requirements | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Fenestration and door U-factor and product ratings | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Fenestration areas | BAKHTIAR SHAMLOO | energy_progress |
| 09/29/2025 | Maintenance information | BAKHTIAR SHAMLOO | energy_progress |