← Back
BuildNYC
Two stories - detached, small or mid-size
145-57 LAKEWOOD AVENUE
QUEENS · South Jamaica · BIN 4215466
💬 Discuss this project
1904Year Built
2.5Stories
A1Building Class
R4-1Zoning
2,410 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 6,511 sf lot · 0.37 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Attic5p · 1 filing · 18 docs
Floor 28p · 1 filing · 18 docs
Floor 110p · 1 filing · 18 docs
Cellar5p · 1 filing · 18 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/01/2018$700K—Private party → Private party$290/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Soyu Architecture403/04/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
C Plus Design Group803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Kishan PlumbingPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Korman Design & Build2055303/04/2024
Building Lifecycle
06/23/2025
Permit expired, never signed off — Plumbing
The city's record still shows this permit as issued, with no sign-off on its filing
Q00884843-S1-PL
10/22/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/11/2024
Permit renewed — Plumbing
Renewed without changes
Q00884843-S1-PL
07/30/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/09/2024
Objection resolved — Addressed
29 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedN and S Plumbing10/11/2024
DOB NOWPlumbingPermit IssuedN and S Plumbing09/22/2023
1 project · most recent 03/04/2024
Gas Water/Sanitary
FiledStatusContractorScope
03/04/2024Permit IssuedN and S PlumbingGas, Water/Sanitary
1 project · most recent 05/10/2024
General Wiring
FiledStatusContractorScope
05/10/2024Permit IssuedLuna NYC ElectricGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
10/22/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/09/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/09/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/09/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
05/03/2024Fire-Resistant Penetrations and Joints—special
05/03/2024Maintenance informationYOUNGSAM YUenergy_progress
03/04/2024Air barrier - visual inspectionYOUNGSAM YUenergy_progress
03/04/2024Fenestration and door U-factor and product ratingsYOUNGSAM YUenergy_progress
03/04/2024Fire-Resistant Penetrations and JointsDAVID UHspecial
03/04/2024Insulation placement and R valuesYOUNGSAM YUenergy_progress
03/04/2024Fenestration air leakageYOUNGSAM YUenergy_progress
03/04/2024Fenestration areasYOUNGSAM YUenergy_progress
03/04/2024Energy Code Compliance InspectionsYOUNGSAM YUprogress
18 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account