| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/29/2024 | $1.2M | — | NEXT DREAM HOME CORP. → Private party | $528/sf building |
| 03/31/2023 | $435K | — | Private party → NEXT DREAM HOME CORP. | $192/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| J.K.DESIGN | 6 | 02/02/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| YAFE MEOD CORP | General Contractor | 12 | 03/21/2026 |
| K & Y PLBG AND HTG INC | Plumbing | 2 | 07/08/2026 |
| INDY ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| ISLAND ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 5 | 02/02/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | YAFE MEOD CORP | 10/24/2023 |
| DOB NOW | Structural | Signed-off | YAFE MEOD CORP | 10/24/2023 |
| DOB NOW | Plumbing | Signed-off | K & Y PLBG AND HTG INC | 10/11/2023 |
| DOB NOW | Plumbing | Signed-off | K & Y PLBG AND HTG INC | 07/25/2023 |
| DOB NOW | Foundation | Permit Issued | YAFE MEOD CORP | 06/14/2023 |
| DOB NOW | Construction Fence | Signed-off | YAFE MEOD CORP | 05/25/2023 |
| BIS | OT | ISSUED | PRO CUSTOM SOLAR LLC | 09/17/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2023 | Complete | INDY ELECTRIC CORP. | General Wiring |
| 09/28/2018 | Complete | ISLAND ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/02/2024 | Signed-off | YAFE MEOD CORP | Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/29/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/22/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 11/09/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/31/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/12/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/14/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/26/2024 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 02/26/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 02/26/2024 | Permanent certificate | FAHAD FATEH | energy_progress |
| 02/26/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 02/26/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 02/26/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 02/26/2024 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 02/26/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 02/26/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 02/26/2024 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 02/26/2024 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 02/26/2024 | Structural Wood Frame | FAHAD FATEH | progress |
| 02/26/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 02/26/2024 | Footing and Foundation | FAHAD FATEH | progress |
| 02/26/2024 | Final | FAHAD FATEH | progress |
| 02/26/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 02/26/2024 | Subgrade Inspections | FAHAD FATEH | special |
| 02/26/2024 | Chimneys and vents | FAHAD FATEH | special |
| 02/26/2024 | Subsurface Investigations (Borings/Test Pits) | FAHAD FATEH | special |
| 02/26/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/26/2024 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 02/01/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 02/01/2024 | Chimneys and vents | FAHAD FATEH | special |
| 02/01/2024 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 02/01/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |